The AI datacenter tables show what is being built. This one shows who is paying for it. 76 announced deals are recorded, from labs buying cloud capacity to developers leasing powered shells to chip suppliers taking equity. 39 state a headline value, which adds up to $1337 billion on paper. That total should not be read as money committed. Headline values are usually multi-year maximums, overlap with each other (a lab's cloud contract and the cloud's lease with a developer can be the same capacity counted twice), and several have been restructured since they were announced.

  • Stated by a party or in a filing
  • Press reported
Headline value of compute deals by seller (USD bn) Horizontal bars of the summed headline contract value announced for each seller of compute capacity, split into values stated by a party or in a filing and values from press reports. Oracle 1 deal Oracle: $300.0bn stated by a party or in a filing, $0.0bn press reported, across 1 deals Oracle: $300.0bn stated by a party or in a filing, $0.0bn press reported, across 1 deals $300bn Microsoft 2 deals Microsoft: $280.0bn stated by a party or in a filing, $0.0bn press reported, across 2 deals Microsoft: $280.0bn stated by a party or in a filing, $0.0bn press reported, across 2 deals $280bn Amazon 5 deals Amazon: $243.0bn stated by a party or in a filing, $0.0bn press reported, across 5 deals Amazon: $243.0bn stated by a party or in a filing, $0.0bn press reported, across 5 deals $243bn NVIDIA 7 deals NVIDIA: $102.0bn stated by a party or in a filing, $0.0bn press reported, across 7 deals NVIDIA: $102.0bn stated by a party or in a filing, $0.0bn press reported, across 7 deals $102bn CoreWeave 6 deals CoreWeave: $59.9bn stated by a party or in a filing, $0.0bn press reported, across 6 deals CoreWeave: $59.9bn stated by a party or in a filing, $0.0bn press reported, across 6 deals $60bn Nscale 7 deals Nscale: $50.8bn stated by a party or in a filing, $0.0bn press reported, across 7 deals Nscale: $50.8bn stated by a party or in a filing, $0.0bn press reported, across 7 deals $51bn Fluidstack 2 deals Fluidstack: $50.0bn stated by a party or in a filing, $0.0bn press reported, across 2 deals Fluidstack: $50.0bn stated by a party or in a filing, $0.0bn press reported, across 2 deals $50bn Nebius 3 deals Nebius: $47.3bn stated by a party or in a filing, $0.0bn press reported, across 3 deals Nebius: $47.3bn stated by a party or in a filing, $0.0bn press reported, across 3 deals $47bn TeraWulf 4 deals TeraWulf: $32.2bn stated by a party or in a filing, $0.0bn press reported, across 4 deals TeraWulf: $32.2bn stated by a party or in a filing, $0.0bn press reported, across 4 deals $32bn Broadcom 3 deals Broadcom: $21.0bn stated by a party or in a filing, $0.0bn press reported, across 3 deals Broadcom: $21.0bn stated by a party or in a filing, $0.0bn press reported, across 3 deals $21bn Valor Equity Partners 1 deal Valor Equity Partners: $20.2bn stated by a party or in a filing, $0.0bn press reported, across 1 deals Valor Equity Partners: $20.2bn stated by a party or in a filing, $0.0bn press reported, across 1 deals $20bn Cerebras 1 deal Cerebras: $20.0bn stated by a party or in a filing, $0.0bn press reported, across 1 deals Cerebras: $20.0bn stated by a party or in a filing, $0.0bn press reported, across 1 deals $20bn 075150225300
Summed headline value of announced deals by the party that sells the capacity. Values are as announced, are not additive across overlapping deals, and a missing bar means no value was stated, not that the deal was small.
Table view: Headline value of compute deals by seller
SellerDealsStated ($bn)Press reported ($bn)Stated MW
Oracle1300.00.04500
Microsoft2280.00.01000
Amazon5243.00.05000
NVIDIA7102.00.010560
CoreWeave659.90.00
Nscale750.80.0660
Fluidstack250.00.040
Nebius347.30.00
TeraWulf432.20.0929
Broadcom321.00.013500
Valor Equity Partners120.20.00
Cerebras120.00.0750

All deals

DateBuyerSellerTypeMWAcceleratorsValue ($bn)BasisConfidenceSourceNote
2026-09-08 OpenAI Firmus Technologies Cloud contract - - - Company stated rep firmus.co Multi-year deal: OpenAI contracts dedicated capacity from two Firmus AI Factory sites in Malaysia (Nvidia Vera Rubin NVL72). MW, GPUs, value and term not stated.
2026-08-25 Anthropic Nscale Cloud contract - - 44.6 Regulatory filing rep sec.gov Four GPU services agreements at Monarch campus, West Virginia, NVIDIA Vera Rubin NVL72, up to about $44.6bn. Nscale has no binding financing yet; tranches terminable for delay.
2026-08-17 OpenAI SB Energy Datacenter lease 8,000 - - Regulatory filing ver sec.govsec.gov PORTS campus, Pike County OH: 17 leases, about 8.0 GW-IT, 20-year terms. Nvidia guaranty (cap $105bn) covers first 4.25 GW; option for 3.8 GW more. Ready for service from 2028.
2026-07-06 Anthropic TeraWulf Datacenter lease · Justified Data (Anthropic) 401 - 19 Regulatory filing rep sec.govsec.gov 20-year lease, about 401 MW critical IT at Hawesville, Kentucky, delivery late 2027 to early 2028, about $19bn contracted revenue, investment-grade credit support expected.
2026-05-05 Microsoft Nscale Cloud contract · SINES Data Campus GB300 Deployment 200 66,000 - Company stated rep nscale.com More than 66,000 Vera Rubin GPUs from late 2027 in a second 200MW building at Start Campus, Sines. Nscale to invest EUR 230M shared infrastructure and EUR 465M for the building.
2026-05 Anthropic xAI Cloud contract - 325,000 - Regulatory filing rep sec.gov SpaceX (xAI) cloud agreements: about 325,000 NVIDIA GPUs across Colossus and Colossus II, $1.25bn per month through May 2029, cancellable on 90 days notice after month three.
2026-05 xAI Valor Equity Partners Other - - 20.206 Regulatory filing rep sec.gov SpaceX prospectus: three Valor equipment leases of computing equipment to xAI units, payments $6.986bn, $6.633bn and $6.587bn (summed), SpaceX-guaranteed. Lease dates not given.
2026-04-22 EuroHPC JU E4 Computer Engineering Other · IT4LIA - - - Company stated rep eurohpc-ju.europa.eu EuroHPC JU procurement contract with E4 and Dell for a liquid-cooled GB200 NVL4 AI supercomputer for IT4LIA (CINECA, Bologna). Contract price not shown on the page read.
2026-04-20 Anthropic Amazon Cloud contract 5,000 - 100 Company stated ver anthropic.comsec.gov Up to 5 GW of new capacity; Anthropic commits more than $100bn over ten years to AWS (Graviton, Trainium2 to 4); nearly 1 GW of Trainium2/3 by end 2026. Value is a floor.
2026-04-14 Microsoft Nscale Cloud contract · Microsoft Azure AI datacenter (Narvik, Norway) 230 30,000 - Company stated rep nscale.comdatacenter-forum.com Adds more than 30,000 Vera Rubin GPUs for 2027 on the 230MW Narvik campus (MW is the campus, not the increment). Bloomberg: takes capacity once slated for OpenAI's Stargate Norway.
2026-04-10 Anthropic CoreWeave Cloud contract - - - Company stated rep coreweave.comsec.gov Multi-year agreement with phased roll-out from later in 2026 and potential to expand. No value, MW or chip count disclosed.
2026-04-06 Anthropic Broadcom Chip supply 3,500 - - Press report rep anthropic.comigorslab.de Anthropic says multiple gigawatts of TPU capacity from 2027, mostly US; Reuters (via Igor's Lab) puts it near 3.5GW via Broadcom. Financial terms undisclosed.
2026-03-31 Meta Platforms CoreWeave Cloud contract - - 21 Regulatory filing rep sec.govsec.gov Order form of 31 Mar 2026: Meta committed about $21bn incl. new capacity through Dec 2032 and exercise of an option under an earlier order through Apr 2032.
2026-03-13 Meta Platforms Nebius Cloud contract - - 27 Regulatory filing rep sec.gov Up to about $27bn: $12bn of firm 5-year dedicated GPU cluster orders from early 2027 plus up to $15bn for Meta to buy any unsold capacity on specified clusters.
2026-02-27 OpenAI Amazon Cloud contract - - 100 Regulatory filing rep sec.gov Amazon 10-Q: Q1 2026 expansion of the $38bn commitment by $100bn over 8 years, incl. obligations tied to AWS chips. Source gives no GW figure.
2026-02-23 Meta Platforms AMD Equity for compute 6,000 - - Regulatory filing rep sec.gov AMD Instinct purchases by Meta with a warrant for 160m AMD shares at $0.01, vesting with purchases up to 6 GW equivalent and price targets to $600; first 1 GW binding. No USD value.
2026-02-18 Yotta Data Services NVIDIA Chip supply · Yotta D2 Blackwell Ultra Cluster 60 20,736 2 Company stated rep cxotoday.com 20,736 HGX B300 GPUs at the 60MW D2 center, Greater Noida, live by Aug 2026; over $2B total investment (not a chip price). Nvidia separately commits over $1B over four years for DGX Cloud there.
2026-02-17 Meta Platforms NVIDIA Chip supply - - - Company stated rep nvidianews.nvidia.com Multiyear, multigenerational partnership: NVIDIA CPUs, millions of Blackwell and Rubin GPUs and Spectrum-X networking for Meta data centers. No MW or USD disclosed.
2026-01-09 OpenAI SB Energy Datacenter lease · Stargate Milam County 753 - - Regulatory filing rep sec.gov SB Energy S-1/A: Milam County leases total about 753 MW critical IT in two buildings, 15-year initial terms, OpenAI tenant, tied to the Jan 2026 Foundation Agreement. USD not stated.
2026-01 OpenAI Cerebras Cloud contract 750 - 20 Regulatory filing rep sec.gov MRA Dec 2025: 750 MW committed over 2026-2028 plus option for 1.25 GW more by 2030; prospectus says valued above $20bn (press first said over $10bn). OpenAI holds a warrant.
2025-12-17 Fluidstack Hut 8 Datacenter lease · River Bend (Fluidstack) 245 - 7 Company stated rep sec.govsec.gov 15-year triple-net lease for 245 MW IT at River Bend LA, $7.0bn base term (up to $17.7bn with renewals), Google backstop, first hall Q2 2027, ROFO on 1,000 MW more.
2025-12-11 Anthropic Broadcom Chip supply - - 21 Company stated rep sdxcentral.com Broadcom CEO said on its earnings call that Anthropic placed a $10B then an $11B order for Google Ironwood TPU racks, the later one for delivery in 2026. Total is the sum of two orders.
2025-12-05 OpenAI NEXTDC Datacenter lease · NEXTDC S7 Sydney AI Campus - - - Regulatory filing rep nextdc.comw.media ASX-announced MoU for an AI campus and GPU supercluster at S7 Eastern Creek, first phase H2 2027 subject to approvals. AUD 7B plan per w.media (not converted). Not a lease yet.
2025-11-20 Nscale Verne Datacenter lease · Nscale Verne Iceland Cluster 15 4,600 - Company stated ver nscale.comverne.co 15MW deployment of about 4,600 Blackwell Ultra GPUs at Verne's Keflavik campus through 2026. Lease terms and value not stated.
2025-11-19 xAI HUMAIN Other 500 - - Press report rep middleeastainews.comw.media Framework agreement for a 500MW-plus xAI GPU data center in Saudi Arabia, announced at the US-Saudi Investment Forum. No value, GPU count or term in the sources read.
2025-11-18 Anthropic Microsoft Cloud contract 1,000 - 30 Company stated ver anthropic.comblogs.microsoft.com Anthropic commits $30bn of Azure compute and up to 1 GW more on Grace Blackwell and Vera Rubin. Nvidia to invest up to $10bn and Microsoft up to $5bn in Anthropic.
2025-11-12 Anthropic Fluidstack Other - - 50 Company stated rep anthropic.com Anthropic announces $50bn US data center investment with Fluidstack in Texas and New York, sites online through 2026. MW and own-versus-lease structure not stated.
2025-11-04 Deutsche Telekom NVIDIA Chip supply · Industrial AI Cloud - 10,000 - Company stated rep blogs.nvidia.comtelekom.com Industrial AI Cloud in Munich on up to 10,000 Blackwell GPUs (DGX B200, RTX PRO servers), operating since 2026-02-04. Investment value not stated in the pages read.
2025-11-03 Microsoft G42 Other - - 15.2 Company stated rep blogs.microsoft.com Microsoft UAE spend 2023-2029: $7.3B to 2025 (incl. $1.5B G42 equity) plus $7.9B planned; GB300 export licences worth 60,400 A100-equivalents. Total investment, not a G42 contract.
2025-11-03 ByteDance Omnia Data Centers Datacenter lease · Omnia Pecem (TikTok) 200 - - Press report rep infomoney.com.brthenextweb.com Reuters: ByteDance expected sole client of the Pecem campus (300MW envelope, 200MW IT). TNW reports ByteDance $7-8B for IT gear and Omnia ~$2B; not confirmed by the firms.
2025-11-03 Microsoft IREN Cloud contract · IREN Childress Horizons 1-4 (Microsoft) 200 - 9.7 Regulatory filing rep sec.govsec.gov GB300 GPU services at Childress Horizon 1-4, about 200 MW IT, five-year average term, about $9.7bn through 2031. Microsoft accepted Horizon 1 in Aug 2026.
2025-11-03 Amazon Cipher Mining Datacenter lease · Cipher Black Pearl (AWS) 300 - 5.5 Company stated rep sec.gov About $5.5bn 15-year lease to AWS for turnkey space and power; 300 MW delivered in 2026 in two phases (from Jul 2026), rent from Aug 2026.
2025-11 OpenAI Amazon Cloud contract - - 38 Company stated rep aboutamazon.comsec.gov Amazon: $38bn agreement growing over seven years, hundreds of thousands of NVIDIA GB200/GB300 GPUs, capacity targeted before end 2026. Expanded Feb 2026 (next row).
2025-11 Meta Platforms Nebius Cloud contract - - 2.9 Regulatory filing rep sec.gov First order under Meta agreement: two dedicated GPU clusters delivered Dec 2025 and Feb 2026, about $2.9bn over five years; Meta may extend or add capacity.
2025-10-30 Hyundai Motor Group NVIDIA Chip supply · Hyundai Motor Group Blackwell AI Factory - 50,000 - Company stated rep nvidianews.nvidia.comkoreatimes.co.kr Part of Nvidia's 260,000-GPU Korea plan (Samsung 50k, SK 50k, Hyundai 50k, Naver 60k, govt 50k), MoU-level. The ~$3B Hyundai-Nvidia physical-AI investment is not a chip price.
2025-10-29 Anthropic Amazon Cloud contract · Project Rainier - - - Company stated rep aboutamazon.com Amazon: Rainier fully operational with nearly half a million Trainium2 chips; Claude expected on over 1M Trainium2 chips by end 2025. MW and USD not stated.
2025-10-28 HUMAIN Qualcomm Chip supply · HUMAIN Qualcomm AI 100 Cluster 200 - - Company stated rep de.tradingview.commiddleeastainews.com HUMAIN targets 200MW of Qualcomm AI200/AI250 racks from 2026; no dollar value. Phase one reported as 1,024 Cloud AI 100 accelerators delivered Feb 2026.
2025-10-28 OpenAI Microsoft Cloud contract - - 250 Company stated rep blogs.microsoft.com Microsoft states OpenAI contracted an incremental $250bn of Azure services in the restructured agreement; Microsoft loses its right of first refusal. Term not stated.
2025-10-28 Fluidstack TeraWulf Joint venture · Abernathy (Fluidstack) 168 - 9.5 Company stated rep sec.govsec.gov Fluidstack JV (TeraWulf 51 percent) for 168 MW at Abernathy TX, 25-year lease about $9.5bn, Google backstop $1.3bn. TeraWulf agreed in Jul 2026 to sell its stake for about $530m.
2025-10-23 Anthropic Alphabet Cloud contract · Google TPU (Ironwood) capacity for Anthropic 1,000 1,000,000 - Company stated rep anthropic.comnasdaq.com Up to 1,000,000 TPUs and well over 1GW online in 2026 (MW is a lower bound); value described as tens of billions of dollars, no figure given.
2025-10-21 CoreWeave Galaxy Digital Datacenter lease · Galaxy Helios (CoreWeave) 800 - - Regulatory filing rep sec.govsec.gov CoreWeave commits to the full 800 MW of approved power at Helios, Texas, after the Phase II lease and final 133 MW option. 15-year Phase I lease; 133 MW IT delivered by mid 2026.
2025-10-16 Firmus Technologies CDC Data Centres Other 150 54,000 - Company stated rep firmus.cow.media Alliance with CDC and Nvidia: first stages up to 150MW and 54,000 GB300 by mid-2026; A$4.5B initial, A$73.3B and 1.6GW through 2028 (AUD, not converted).
2025-10-15 Microsoft Nscale Cloud contract - 200,000 - Company stated rep nscale.comlp.startcampus.pt About 200,000 GB300 GPUs: Texas ~104k (240MW), Narvik ~52k, Loughton ~23k (50MW), Sines ~12.6k. Overlaps the Narvik and Loughton deals. Multi-year; no value stated by Nscale.
2025-10-13 OpenAI Broadcom Chip supply 10,000 - - Company stated rep seekingalpha.com Joint release: 10 GW of OpenAI-designed accelerators and Broadcom Ethernet racks, deployment targeted 2H 2026 to end 2029. No financial terms disclosed.
2025-10-06 OpenAI AMD Equity for compute 6,000 - - Regulatory filing rep sec.govir.amd.com 6 GW of AMD Instinct GPUs, first 1 GW of MI450 from 2H 2026. AMD warrant for 160m shares vests with purchases up to 6 GW and price targets to $600. No USD value stated.
2025-10 Meta Platforms Blue Owl Capital Joint venture · Meta Hyperion - - 12.3 Regulatory filing rep sec.gov Richland Parish LA JV: Blue Owl funds hold 80 percent ($7.0bn cash), Meta 20 percent. Meta leases from 2029: initial commitment about $12.3bn over 4 years, renewable to 20; $28bn residual guarantee.
2025-09-30 Meta Platforms CoreWeave Cloud contract - - 14.2 Regulatory filing rep sec.govsec.gov Order form of 25 Sep 2025 under Dec 2023 MSA: Meta initially committed up to about $14.2bn through 14 Dec 2031, with an option to expand materially through 2032.
2025-09-25 OpenAI CoreWeave Cloud contract - - 6.5 Regulatory filing rep sec.govsec.gov Order form of 23 Sep 2025: OpenAI committed up to about $6.5bn through 31 May 2031 under the May 2025 MSA. Separate from the $11.9bn March 2025 contract.
2025-09-25 Fluidstack Cipher Mining Datacenter lease · Barber Lake (Fluidstack) 168 - 3 Regulatory filing rep sec.govsec.gov 168 MW critical IT, 10-year lease, about $3bn; Google backstops $1.4bn and gets warrants. Sep 2026 amendment: an unnamed AI lab committed to a further 10-year lease, about $5.2bn.
2025-09-22 OpenAI NVIDIA Equity for compute 10,000 - 100 Company stated rep nvidianews.nvidia.comsec.gov Letter of intent: 10 GW of NVIDIA systems, Nvidia to invest up to $100bn per GW deployed. Never finalised: Feb 2026 10-K says still finalising; press reported a $30bn equity deal instead.
2025-09-18 NVIDIA Intel Equity for compute - - 5 Company stated rep nvidianews.nvidia.comthe-decoder.com Nvidia buys $5B of Intel stock at $23.28 a share (subject to approvals) and co-develops x86 RTX SoCs and custom x86 CPUs for Nvidia data centers. Equity plus co-design, no compute volume.
2025-09-17 Microsoft Nscale Cloud contract · Microsoft Azure AI datacenter (Narvik, Norway) - 52,000 6.2 Company stated ver filingreader.comnews.microsoft.com Binding five-year agreement via the Aker-Nscale JV, about $6.2B, staged from 2026; about 52,000 GB300 GPUs per Nscale's Oct 2025 release. Included in the Oct 2025 umbrella deal.
2025-09-16 OpenAI Nscale Cloud contract - 8,000 - Company stated rep nscale.comtechzine.eu OpenAI to explore offtake of up to 8,000 GPUs from Q1 2026, scalable to 31,000. Apr 2026 reports: OpenAI put Stargate UK on hold (energy costs, regulation). No value stated.
2025-09-09 NVIDIA CoreWeave Cloud contract - - 6.3 Regulatory filing rep sec.gov Order form with initial value $6.3bn: Nvidia must buy CoreWeave's residual unsold cloud capacity through 13 Apr 2032 (a capacity backstop). Nvidia also supplies GPUs and is a shareholder.
2025-09-08 Microsoft Nebius Cloud contract · Nebius Vineland (Microsoft) - - 17.4 Regulatory filing rep sec.gov Dedicated GPU capacity in tranches at Vineland NJ, five years, about $17.4bn through 2031 (up to $19.4bn if Microsoft adds services); tranches deploy across 2025 and 2026.
2025-08-29 CoreWeave Applied Digital Datacenter lease · Polaris Forge 1 (Ellendale) 150 - 4 Regulatory filing rep sec.gov Third lease: CoreWeave exercised its option for 150 MW Building 4, about $4.0bn over about 15 years, service-ready mid 2027; total leased 400 MW. Applied Digital issued warrants.
2025-08-21 Meta Platforms Alphabet Cloud contract - - 10 Press report rep cnbc.comdatacentrereview.com Press reports citing sources: six-year Google Cloud deal worth more than $10bn (servers, storage, networking). Not confirmed by either company; value is a floor.
2025-08-18 Fluidstack TeraWulf Datacenter lease · Lake Mariner (Fluidstack) 160 - - Regulatory filing rep sec.govsec.gov CB-5 lease for over 160 MW, delivery by end 2026, same terms. Lake Mariner total now over 360 MW and $6.7bn; Google backstop rises to $3.2bn.
2025-08-14 Fluidstack TeraWulf Datacenter lease · Lake Mariner (Fluidstack) 200 - 3.7 Regulatory filing rep sec.govsec.gov Two 10-year leases (CB-3, CB-4), over 200 MW critical IT at Lake Mariner NY, about $3.7bn (up to $8.7bn with extensions); Google backstops $1.8bn and gets warrants.
2025-07-31 OpenAI Nscale Cloud contract · Microsoft Azure AI datacenter (Narvik, Norway) 230 100,000 - Company stated rep nscale.comdatacenter-forum.com OpenAI named initial offtaker, target 100,000 GPUs by end-2026. Apr 2026 (Bloomberg): no agreement concluded and Microsoft took the capacity; OpenAI says it still explores Norway.
2025-07-22 OpenAI Oracle Cloud contract 4,500 - 300 Company stated ver group.softbanktomshardware.com 4.5 GW added Jul 2025; joint release says partnership exceeds $300bn over five years (WSJ: starts 2027). Oracle said Mar 2026 leasing for the 4.5 GW is complete. Multi-site.
2025-07-07 CoreWeave Core Scientific Datacenter lease 590 - - Regulatory filing rep sec.govsec.gov About 590 MW leased power to CoreWeave. $9bn all-stock merger agreed Jul 2025 was voted down 30 Oct 2025 and terminated; leases continue. Lease USD not stated.
2025-06-25 KDDI Hewlett Packard Enterprise Chip supply · KDDI GPU Cloud - - - Company stated rep telecomtv.comnewsroom.kddi.com HPE builds Nvidia GB200 NVL72 rack-scale systems and hybrid cooling for KDDI's Osaka Sakai AI data center. KDDI targets operations by end of FY2025. No value, MW or GPU count.
2025-06-20 Amazon SK Telecom Joint venture · SK Ulsan AI Data Center 100 60,000 - Press report rep lightreading.comtechblog.comsoc.org AWS AI Zone data center in Ulsan: 100MW (103MW at full build), 60,000 GPUs reported. Firms did not disclose investment; Yonhap/Reuters cite 7 trillion won incl. $4B AWS.
2025-06-11 Mistral AI NVIDIA Chip supply · Mistral Campus AI (Bruyeres-le-Chatel) - 18,000 - Company stated rep blogs.nvidia.comblogs.nvidia.com 18,000 Blackwell-class GPUs planned for Mistral Compute's initial phase; Nvidia's 2026 blog says the first deployment is operational at Bruyeres-le-Chatel. No dollar value.
2025-06-11 Mistral AI MGX Joint venture · Campus AI Fouju 1,400 - - Company stated rep blogs.nvidia.comlavoixdefrance.fr Mistral, Nvidia, Bpifrance and MGX plan a 1.4GW Paris-region AI campus; June 2026 agreement lifted the Campus AI target to 3GW. Ownership split and value not stated.
2025-06-02 CoreWeave Applied Digital Datacenter lease · Polaris Forge 1 (Ellendale) 250 - 7 Regulatory filing rep sec.gov Two leases signed 28 May 2025 at Ellendale ND: 100 MW Building 2 (about $3bn) and 150 MW Building 3 (about $4bn), about 15 years each plus three 5-year options.
2025-05-13 HUMAIN NVIDIA Chip supply · HUMAIN AI Factory Phase 1 500 18,000 - Company stated rep nvidianews.nvidia.comfastcompanyme.com Up to 500MW and several hundred thousand Nvidia GPUs over five years; accelerators is the stated first phase (18,000 GB300) only. No dollar value stated.
2025-05-13 HUMAIN AMD Chip supply 500 - 10 Company stated rep newsroom.amd.com Parties to invest up to $10B to deploy 500MW of AMD Instinct-based compute over five years across Saudi Arabia and the US. Headline maximum, not a contract price.
2025-05-13 HUMAIN Amazon Other - - 5 Company stated rep press.aboutamazon.com AWS and HUMAIN to invest $5B-plus in an AI Zone with dedicated AWS AI infrastructure in Saudi Arabia. Minimum combined investment, not a contract price; no MW or chip named.
2025-05 OpenAI G42 Joint venture · Stargate UAE 1,000 - - Company stated rep g42.aithenationalnews.com 1GW cluster built by G42 and operated by OpenAI and Oracle with Nvidia GB300 systems; first 200MW due 2026 (The National: Q3 2026). No dollar value stated.
2025-05 DataVolt Supermicro Chip supply - - 20 Press report rep baxtel.com Multi-year $20B agreement for Supermicro GPU platforms and rack systems for DataVolt campuses in Saudi Arabia and the US. Headline value; delivery schedule and term not stated.
2025-03-04 Mistral AI Fluidstack Cloud contract · Mistral Campus AI (Bruyeres-le-Chatel) 40 18,000 - Company stated rep silicon.co.uktechnologies.org Fluidstack and Eclairion to build a cluster of 18,000-plus GPUs for Mistral at Eclairion's 40MW Bruyeres-le-Chatel site, first phase summer 2025. No value or term stated.
2025-03-03 SoftBank Corp. OpenAI Joint venture - - - Company stated rep softbank.jpw.media 50:50 SB OpenAI Japan JV; SoftBank Group to spend $3B a year on OpenAI solutions (per year, not recorded). Sakai plant bought for about 100B yen for a data center that may host Stargate.
2025-03 OpenAI CoreWeave Cloud contract - - 11.9 Regulatory filing rep sec.govsec.gov Master agreement Mar 2025: OpenAI committed up to $11.9bn through Oct 2030; CoreWeave issued OpenAI 8.75m IPO shares ($350m). A later May 2025 expansion is not sourced here.
2025-02-09 Aramco Digital Groq Other · GroqCloud Dammam Inference Cluster - 19,000 1.5 Press report rep middleeastainews.comgroq.com Dammam GroqCloud region reported live on 19,000 LPUs, backed by a $1.5B Saudi investment; partnership began as a Sept 2024 MoU. Investment figure, not a contract price.

Most active buyers

BuyerDealsStated MWHeadline value ($bn)
OpenAI1741233826.4
Anthropic1110901264.6
Meta Platforms8600087.4
Microsoft763048.5
Fluidstack594123.2
HUMAIN4120015.0
CoreWeave4179011.0
Mistral AI31440-
xAI250020.2
NVIDIA2-11.3
Amazon24005.5
DataVolt1-20.0

How to read these

Deal types differ. A cloud contract sells compute as a service, a datacenter lease rents powered space for the tenant's own hardware, a joint venture shares ownership of a campus, chip supply moves accelerators, and equity for compute ties ownership stakes to purchases. cloud contract, datacenter lease, joint venture, chip supply, equity for compute, other are all in the table, and a single campus often sits at the end of a chain of several of them.

Only announced deals with a source are recorded. Talks, letters of intent that were never followed by a contract, and rumours are left out, and cancellations or restructurings are noted on the row. Where a deal has a stated capacity but no value, or the reverse, the other column is blank.