Supercomputers/Systems/Omnia Pecem (TikTok)

Brazil · under construction · ai training

Omnia Pecem (TikTok)

Also known as ByteDance Ceara data center; TikTok Pecem data center hub

Operated by Omnia Data Centers at Pecem Export Processing Zone Site .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Omnia develops the 200 MW IT Pecem data centre for ByteDance, which funds the IT equipment
Omnia Data Centers
- Reported thenextweb.com

Engineering, funding and access

What Omnia Pecem (TikTok) runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Funding

ItemDetailAs ofBasisSource
Funded byByteDance funds the IT equipment; Omnia (backed by Patria Investimentos) funds the site infrastructure; Casa dos Ventos funds dedicated wind capacityByteDance has not publicly confirmed the project; Brazilian officials and Reuters sources have.2026-05-18Press reportthenextweb.com
Stated cost9,800 USD mCombined investment: ByteDance $7-8 billion of IT equipment, Omnia about $2 billion of site infrastructure, Casa dos Ventos about 3.5 billion reais of wind capacity.2026-05-18Press reportthenextweb.com
ProcurementOmnia signed an energy-supply agreement of roughly $2 billion with Casa dos Ventos, which has a 350 MW wind asset earmarked for the campus; tenor and price undisclosedTNW says the $2 billion is likely cumulative contract value over the term.2026-05-18Press reportthenextweb.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Stated investment 9.8 USD bn 2026-10 Operator stated Combined three-party total: ByteDance 7 to 8 billion for IT equipment, Omnia about 2 billion for infrastructure, plus Casa dos Ventos wind capacity (about 3.5 billion reais). thenextweb.com
Facility power 300 MW 2026-10 Operator stated Power consumption envelope of 300 MW supporting the 200 MW productive load. thenextweb.cominfomoney.com.br
IT power 200 MW 2026-10 Operator stated First-phase productive load, reported by The Next Web on 18 May 2026 from the Omnia and Casa dos Ventos announcement. thenextweb.com

How it is powered

SourceProviderMWStatusAs ofBasisNoteSource link
Wind and solar Casa dos Ventos - contracted 2026-05 Third-party estimate TNW citing Reuters: about 2 bn USD energy supply deal with Casa dos Ventos for wind power to the 200 MW campus; a 350 MW wind asset earmarked. Term and MW unstated. thenextweb.com

How AI campuses are powered: capacities are what the operator, utility or filing states, not what has been delivered.

Compute deals

All compute deals. Headline values are as announced, not additive.

The read

A 200 MW data centre in the Pecem port complex export processing zone (Caucaia, Ceara, Brazil) developed by Omnia Data Centers (Patria Investments) for ByteDance (TikTok), ByteDance's first dedicated infrastructure in Latin America. The first phase has about 200 MW of productive IT load inside a 300 MW power envelope; The Next Web (18 May 2026) puts the combined investment at about 9.8 billion dollars (7 to 8 billion of ByteDance IT equipment, about 2 billion for Omnia infrastructure, and Casa dos Ventos wind capacity under a 20-year energy contract) with first-phase operations expected in 2027. InfoMoney's earlier coverage notes that ByteDance had not publicly confirmed its participation at announcement. No accelerator vendor or count is stated. The tier is reported. It has never submitted an HPL result.

Timeline

  • 2025 Announced source
  • 2025-11 Brazil's competition authority CADE approves Omnia's control of the Pecem asset and the campus architecture is publicly outlined source

Site & facility

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
thenextweb.comnames system only-
infomoney.com.brnames system only-

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.