COMPUTE ATLAS Supercomputer supply-chain graph
1153 systems 482 sites Sourced data

Forecast

Systems to watch

Which machines could reach a public list next? We do not predict ranks, and we do not reproduce any list. This page takes the planned and under-construction systems in our own dataset and shows the delivery window each operator has stated, with the source, so you can see what is plausible when a new list drops.

A window is not a ranking. A system appears on a list only if its operator submits a run, and many of the largest never do. Read "could be submitted" as a possibility, not a prediction; every date is the operator's own statement as of the date shown.

Could be submitted for the next list or two

SystemStatusStated windowBasisAs of
DAEDALUS under construction Fall 2026 (full services via Pharos) Greek press (citing GRNET/NTUA) reports installation at Lavrio in summer 2026 with full services through the Pharos AI Factory expected by fall 2026; GRNET's own June 2026 TOP500 announcement only says 'operational during 2026' without a specific season and, per this dataset's notes, GRNET and EuroHPC JU still described the system as not yet fully available to users as of that same month. Source 2026-10-01
Doudna planned Late 2026 NERSC states full production is due in late 2026, after an early-access system was delivered in January 2026. Source 2026-03-17
El Khawarizmi Supercomputer under construction Q4 2026 (after 3+ month pilot phase) Tunisian press covering the 23 July 2026 inauguration reports a pilot and training phase for the university community lasting more than three months before the system's effective, official operation begins; no source gives an exact end date for that trial phase or a precise commissioning date beyond it. Source 2026-10-01
Equinox planned 2026 NVIDIA says the first half of 2026 and the DOE says delivered in 2026; neither says it is running. Source 2025-10-28
Google TPU (Ironwood) capacity for Anthropic under construction 2026 (well over 1GW of capacity online) Google and Anthropic both state well over a gigawatt of the committed TPU capacity comes online in 2026. Source 2025-10-23
Horizon under construction Fall 2026 (phase one) TACC's systems page gives fall 2026; its November 2025 post said spring 2026, so the date is contested. Source 2025-11-17
KISTI-6 under construction December 2026 (official service) The Korean science ministry says installation finished in August 2026 and official service is targeted for December 2026, with pilot applications from 23 September. Source 2026-09-20
Lux (ORNL) planned 2026 ORNL says Lux will be deployed in 2026; we found no confirmation that it has. Source 2026-03-05
Microsoft Azure AI datacenter (Narvik, Norway) under construction 2026 (staged deployment begins) Nscale and Microsoft's five-year agreement begins staged capacity delivery in 2026. Source 2025-09-17
Stargate UAE under construction 2026 (first 200 MW) G42 says the first 200 MW is on track for 2026; the head of Abu Dhabi's wealth fund told The National it would be ready in Q3 2026. Source 2025-12-05

Not before 2027

SystemStatusStated windowBasisAs of
Alice Recoque planned 2027 GENCI and CEA say installation starts in 2026 and users arrive in 2027. Source 2025-11-18
Blue Lion planned 2027 LRZ schedules Blue Lion for 2027. Source 2025-11-13
Crusoe Abilene Campus (Microsoft) under construction Mid-2027 (first building energized) Crusoe's own announcement of the new 900 MW campus states the first of its two buildings is expected to be energized in mid-2027; no completion date has been given for the second building or for the full 900 MW campus. Source 2026-10-01
Microsoft Azure AI supercomputer (Loughton, UK) under construction Q1 2027 (initial GB300 delivery) Nscale's own release states the 23,040-GPU commitment is delivered in Q1 2027. Source 2025-09-17

Later still

SystemStatusStated windowBasisAs of
Discovery (ORNL) planned 2028 ORNL says Discovery will be delivered in 2028. Source 2026-03-05
Meta Hyperion under construction 2030 (initial operational target) Local Louisiana press reports Meta's own project timeline targets the Hyperion data center being operational by 2030, with a transmission substation online by end of 2026 and Entergy's dedicated power plants by end of 2028; independent infrastructure-tracking research instead frames 2030 as only a roughly 2 GW milestone with the full 5 GW buildout not expected until around 2032, and Meta itself has not published a specific operational date. Source 2026-10-01