COMPUTE ATLAS Supercomputer supply-chain graph
1153 systems 482 sites Sourced data

Supercomputers/Systems/Stargate Milam County

USA · under construction · ai training

Stargate Milam County

Also known as OpenAI Stargate Milam County

Operated by SB Energy at SB Energy Milam County Campus .

Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
SB Energy builds and operates the 1.2 GW site for OpenAI
SB Energy
- Reported prnewswire.comsbenergy.com
Power -
SB Energy plans to build new generation to serve the site
SB Energy
- Reported sbenergy.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Facility power 1,200 MW 2026-01 Design target OpenAI/SoftBank/SB Energy release: 1.2 GW data center site in Milam County, Texas; planned capacity, IT vs facility not stated prnewswire.com

How it is powered

SourceProviderMWStatusAs ofBasisNoteSource link
Other SB Energy - planned 2026-01 Operator stated SB Energy plans new generation (type undisclosed) for the 1.2 GW site; first SB Energy facilities enter service from 2026. Epoch lists on-site, type unknown. prnewswire.comepoch.ai

How AI campuses are powered: capacities are what the operator, utility or filing states, not what has been delivered.

Compute deals

All compute deals. Headline values are as announced, not additive.

The read

A 1.2 GW OpenAI Stargate data center site in Milam County, Texas, announced on 9 January 2026 with SB Energy (a SoftBank Group company) to build and operate it, OpenAI having signed a lease for the site and OpenAI and SoftBank each investing 500 million dollars in SB Energy. The announcement says SB Energy plans to build new generation to serve the site and that it will enter service starting in 2026; it names no accelerator type or count. Epoch AI's Stargate site tracker independently lists the same site with SB Energy as developer at 1.2 GW projected and a Q4 2028 completion, with steel framing and roofing visible. Power is blank because 1.2 GW is a site design capacity.

Timeline

Site & facility

SB Energy Milam County Campus

Location
Milam County, TX, USA

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
epoch.ainames system only-
prnewswire.comnames system only-

Checked 2026-10-09 by pnpm verify. Re-run it and the table changes with the web.

Further reading