Supercomputers/Systems/Nscale Verne Iceland Cluster

Iceland · operational · ai training

Nscale Verne Iceland Cluster

Deep dive: How Nebius and Nscale build GPU clouds

Also known as Nscale Keflavik; Verne Iceland GB300 deployment

Operated by Nscale at Verne Iceland Campus (Keflavik) .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Nscale deploys and operates the GPU capacity under a 15 MW lease at Verne's Iceland campus
Nscale
- Reported nscale.com
Integrator -
Verne hosts the deployment at its Keflavik campus; first phase delivered with Computacenter, Lenovo and Vertiv per BeBeez
Verne
- Reported verne.cobebeez.eu
Accelerator NVIDIA GB300 NVL72
Accelerators
NVIDIA GB300 NVL72 racks in the first liquid-cooled phase; approximately 4,600 GPUs planned in total (85% liquid cooled, 15% air cooled)
NVIDIA 4,600
reported
Reported nscale.comverne.co

Engineering, funding and access

What Nscale Verne Iceland Cluster runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Cooling design85% liquid-cooled and 15% air-cooledNscale and Verne state the split independently.2025-11-20Operator statednscale.comverne.co

Funding

ItemDetailAs ofBasisSource
Procurement15 MW agreement between Nscale and Verne announced 20 November 2025 for about 4,600 NVIDIA Blackwell Ultra GPUs, deployed through 2026Lease value not stated. NVIDIA is the GPU supplier.2025-11-20Operator statednscale.comverne.co

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Accelerators 2,300 accelerators 2026-10 Third-party estimate Epoch AI estimate of current B300 chips at Nscale Keflavik, projected to reach 4,600 by Q4 2026. epoch.ai
Accelerators 4,600 accelerators 2025-11 Operator stated Approximately 4,600 Blackwell Ultra GPUs for deployment through 2026; a contracted target, not an installed count. nscale.comverne.co
IT power 5 MW 2026-10 Third-party estimate Epoch AI estimate of current IT power; 15 MW projected by 31 December 2026. epoch.ai
IT power 15 MW 2025-11 Operator stated 15 MW leased capacity at Verne's Iceland campus; first phase of 7.5 MW completed April 2026. nscale.comverne.co

How it is powered

SourceProviderMWStatusAs ofBasisNoteSource link
Hydro Verne - operating 2026-10 Operator stated Verne Keflavik campus (over 140 MW) states it runs on hydroelectric and geothermal power; Nscale deploys 15 MW there. No split by source disclosed. verne.conscale.com
Geothermal Verne - operating 2026-10 Operator stated Verne states Keflavik runs on hydroelectric and geothermal power; Nscale deploys 15 MW. No split by source disclosed. verne.conscale.com

How AI campuses are powered: capacities are what the operator, utility or filing states, not what has been delivered.

Compute deals

All compute deals. Headline values are as announced, not additive.

The read

Nscale's 15 MW lease at Verne's data center campus in Keflavik, Iceland, announced in November 2025 for approximately 4,600 NVIDIA Blackwell Ultra GPUs deployed through 2026, 85 percent liquid cooled and 15 percent air cooled. BeBeez (24 April 2026) reports the first phase, 7.5 MW across 128 racks including 64 liquid-cooled GB300 racks, was completed on 23 April 2026, so the 4,600 figure is the contracted target and not a confirmed installed count. Epoch AI's directory estimates about 2,300 B300 chips and 5 MW of IT power today, rising to about 15 MW by the end of 2026. Separate from Nscale's Svartisen cluster at Glomfjord and from the Microsoft-tenanted Narvik and Loughton rows. No FLOPS or HPL figure has been published.

Timeline

Site & facility

Verne Iceland Campus (Keflavik)

Location
Keflavik, Iceland
Cooling
85% liquid cooled, 15% air cooled (Nscale deployment)

Change history

Nearby in scale

The machines closest to Nscale Verne Iceland Cluster by accelerator count, smaller to larger.

Same site

Same operator

Same accelerator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
nscale.comnames system only · counts: 4600
verne.conames system only · counts: 4600

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.