Supercomputers/Systems/rzVernal
USA · operational · hpc
rzVernal
Also known as RZVernal
Operated by Lawrence Livermore National Laboratory at Livermore Computing Center .
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- -
- Rpeak
- 6.92 PFlop/s
- Rmax ÷ Rpeak
- -
- Cores
- 2,432
- Power
- -
- Per watt
- - GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - HPE Cray EX (CORAL-2 early access) | Hewlett Packard Enterprise | - | Reported | hpc.llnl.gov |
| Accelerator | AMD Instinct MI250X Accelerators ROCm (CDNA 2) · 1.7 GHz · TSMC N6 · 560 W AMD MI-250X | AMD | 152 reported | Reported | hpc.llnl.gov |
| CPU | AMD EPYC 7A53 (Trento) CPUs x86-64 · 64C · 2 GHz · 7 nm · 280 W AMD Trento, 64 cores per compute node | AMD | - | Reported | hpc.llnl.gov |
| Interconnect | HPE Slingshot-11 Interconnect Dragonfly · 200 Gb/s per port · Around 2 microseconds HPE Slingshot 11 | Hewlett Packard Enterprise | - | Reported | hpc.llnl.gov |
| Operating system | Tri-Lab Operating System Stack Operating systems Linux distribution, RHEL-derived, HPC-tuned · Open source, LLNL-maintained TOSS 4 | Lawrence Livermore National Laboratory | - | Reported | hpc.llnl.gov |
Engineering, funding and access
What rzVernal runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 38 nodes36 debug nodes and 2 login nodes, 64 AMD Trento cores per node; 152 MI250X GPUs in total. | 2026-11 | Operator stated | hpc.llnl.gov |
| Total memory | 16 TBLLNL lists 16,384 GiB total (512 GB per node), which is 16 TiB. | 2026-11 | Operator stated | hpc.llnl.gov |
| Interconnect and topology | HPE Slingshot 11 | 2026-11 | Operator stated | hpc.llnl.gov |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Job scheduler | SlurmThe same page also gives a Flux queue command (flux jobs -A). | 2026-11 | Operator stated | hpc.llnl.gov |
| Programming and software stack | TOSS 4 operating system | 2026-11 | Operator stated | hpc.llnl.gov |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Funding programme | NNSA Advanced Simulation and Computing (ASC); platform class ATS-4 early access, CORAL-2 | 2026-11 | Operator stated | hpc.llnl.gov |
Access
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| How researchers get time | Limited-access El Capitan early access system for development and debugging only, no production runs; pdebug pool of 36 nodes with 3 nodes and 4 hours per job | 2026-11 | Operator stated | hpc.llnl.gov |
The read
CORAL-2 early-access system for El Capitan on LLNL's Restricted Zone network, sister of Tioga and Tenaya. LLNL's hardware page lists 38 nodes (2 login, 36 debug), 2,432 CPU cores (AMD Trento, 64 per compute node), 152 AMD MI250X GPUs (listed as 8 per compute node), HPE Slingshot 11, TOSS 4 and a combined CPU+GPU peak of 6.916 PFLOPS, commissioned 2022 under ATS-4/EA. It is not a TOP500 entry. The platform index page lists the same system at 6.9 PFLOPS. Both pages come from the same operator, so the tier is reported.
Timeline
- 2022 First operational source
Site & facility
Livermore Computing Center
- Location
- Livermore, CA, USA
- Cooling
- Direct liquid cooling (warm water)
- Commissioned
- 1996
Change history
- 2026-10-02 Added rzVernal, LLNL's restricted-zone El Capitan early-access system
Related systems
Same site
- Tenaya · USA, operational, 2022
- Tioga · USA, operational, 2022
- Bengal · USA, operational, 2023
- Dane · USA, operational, 2023
- RZHound · USA, operational, 2023
- El Capitan · USA, operational, 2024
Same operator
- Magma (LLNL) · USA, operational, 2020
- Ruby (LLNL) · USA, operational, 2020
- rzAdams · USA, operational, 2024
- Corona · USA, operational, 2019
- Matrix · USA, operational, 2025
- Tuolumne · USA, operational, 2025
Same accelerator
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| hpc.llnl.gov | names system, part and count | AMD EPYC 7A53 (Trento), Tri-Lab Operating System Stack · counts: 152 |
| hpc.llnl.gov | names system, part and count | AMD EPYC 7A53 (Trento), Tri-Lab Operating System Stack · counts: 152 |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect