Supercomputers/Systems/Microsoft Fairwater (Wisconsin)

USA · operational · ai training

Microsoft Fairwater (Wisconsin)

Deep dive: Microsoft Fairwater: two sites, few numbers

Operated by Microsoft at Microsoft Mount Pleasant AI datacenter site .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Accelerator NVIDIA GB200 NVL72
Accelerators
Arm CPU + CUDA GPU · TSMC 4NP
NVIDIA GB200 servers with 72 NVIDIA Blackwell GPUs per rack
NVIDIA - Reported w.media

Engineering, funding and access

What Microsoft Fairwater (Wisconsin) runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Cooling designClosed-loop liquid cooling for more than 90% of the facility, filled during construction and recirculated; the rest uses outside air and water only on the hottest days2025-09-18Operator statedblogs.microsoft.com

Funding

ItemDetailAs ofBasisSource
Funded byMicrosoft, with more than $7 billion committed to Wisconsin across two datacenters2025-09-18Operator statedblogs.microsoft.com
Stated cost3,300 USD mInitial pledge for the first datacenter; a further $4 billion over three years is committed for a second datacenter of similar scale.2025-09-18Operator statedblogs.microsoft.com

Results

ItemDetailAs ofBasisSource
Notable resultMicrosoft claims ten times the performance of today's fastest supercomputers for training frontier AI models; the metric is not definedQualitative marketing claim, not a measured FLOPS figure.2025-09-18Operator statedblogs.microsoft.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Accelerators 176,391 accelerators 2026-04-16 Third-party estimate Epoch AI chip estimate, latest per chip type (B200); some rows are company disclosures, others modelled. epoch.ai
Stated investment 7 USD bn 2025-09 Operator stated Microsoft: extra $4 bn for a second datacenter brings total Wisconsin investment to more than $7 bn; covers both Fairwater datacenters, floor value blogs.microsoft.com
Facility power 442 MW 2026-05-15 Third-party estimate Epoch AI modelled gross facility power (IT plus cooling and overhead) at this timeline date. epoch.ai
IT power 369 MW 2026-05-15 Third-party estimate Epoch AI modelled IT power from satellite imagery and permits at this timeline date; not operator-stated. epoch.ai
Rack power 140 kW 2025-11 Operator stated Microsoft: Fairwater design rates about 140 kW per rack, 72 Blackwell GPUs per rack; blog describes the design of each Fairwater site, Wisconsin is site one; not a Wisconsin-only figure blogs.microsoft.com

How it is powered

SourceProviderMWStatusAs ofBasisNoteSource link
Grid We Energies - operating 2025-09 Operator stated Microsoft pre-pays energy and electrical infrastructure under WE Energies tariffs for Mount Pleasant; no MW stated. Epoch lists WE Energies as the energy company. blogs.microsoft.comepoch.ai
Wind and solar - 250 contracted 2025-09 Operator stated New 250 MW Portage County solar project, under construction, to match fossil-sourced kWh one for one. An offset on the grid, not a direct supply. blogs.microsoft.com

How AI campuses are powered: capacities are what the operator, utility or filing states, not what has been delivered.

The read

The first Fairwater site, in Mount Pleasant, Wisconsin. Microsoft states hundreds of thousands of NVIDIA GPUs, closed-loop liquid cooling for over 90% of the site, and completion in early 2026; only the trade-press report of 24 June 2026 says it is fully operational, and it derives from Microsoft's own release, so the tier stays reported. The GB200 servers at 72 GPUs per rack come from that same report, not from Microsoft's blog. No exact GPU count or power is published. Microsoft's qualitative claim of ten times today's fastest supercomputers is not a FLOPS figure and is not recorded as one.

Timeline

  • 2025-09 Announced source
  • 2025-09-18 Microsoft commits a further $4 billion over three years to a second datacenter of similar size in Mount Pleasant source
  • 2026-04 Epoch AI records Building 1 as operational, citing a Microsoft post of mid-April 2026 source
  • 2026-06 First operational source

Site & facility

Microsoft Mount Pleasant AI datacenter site

Location
Mount Pleasant, WI, USA
Cooling
Closed-loop liquid cooling
Commissioned
2025

Where sources disagree

We record conflicts instead of picking a winner quietly. All open questions.

Change history

Nearby in scale

The machines closest to Microsoft Fairwater (Wisconsin) by accelerator count, smaller to larger.

Same operator

Same accelerator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
blogs.microsoft.comnames system only-
w.medianames system and partNVIDIA GB200 NVL72

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.

Related news

  • Microsoft links Fairwater Atlanta and Wisconsin into one "AI superfactory" · Microsoft
    The two Fairwater sites are joined over a dedicated AI WAN fiber backbone so training jobs can span both facilities as one system rather than two separate clusters, a different scaling strategy than the single site gigawatt campuses xAI and Meta are building. Each rack carries up to 72 NVIDIA Blackwell GPUs; Microsoft has not disclosed a total GPU count for either site.

All news →