Supercomputers/Systems/AWS Ridgeland Campus
USA · operational · ai training
AWS Ridgeland Campus
Deep dive: Project Rainier: Amazon's Anthropic cluster
Also known as AWS Ridgeland Mississippi
Operated by Amazon at AWS Ridgeland Data Center Campus .
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- -
- Rpeak
- -
- Rmax ÷ Rpeak
- -
- Cores
- -
- Power
- -
- Per watt
- - GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - AWS builds and operates the Ridgeland, Madison County, Mississippi data center campus | Amazon | - | Reported | mississippi.orgmississippifreepress.org |
| Accelerator | AWS Trainium2 Accelerators NeuronCore-v3 · TSMC 5nm Epoch AI estimate: about 261,200 AWS Trainium2 chips (modelled, not disclosed by Amazon) | Amazon | 261,200 estimated | Reported | epoch.ai |
Engineering, funding and access
What AWS Ridgeland Campus runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Funded by | Amazon, as part of a USD 25 billion planned Mississippi investment announced on 9 April 2026 with Mississippi Major Economic Impact Authority supportThe state release names Madison County, Clinton and Vicksburg, not Ridgeland as a project site. | 2026-04-09 | Operator stated | mississippi.org |
| Stated cost | 8,600 USD mEpoch AI estimate for the current capacity of Buildings 1 to 4; its projection for the full 2028 build-out is USD 31.8 billion. | 2026-07-22 | Third-party estimate | epoch.ai |
AI datacenter metrics
Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.
| Metric | Value | As of | Basis | Note | Source |
|---|---|---|---|---|---|
| Accelerators | 261,200 accelerators | 2026-10-02 | Third-party estimate | About 261,200 Trainium2; Epoch projects about 502,400 Trainium3 by Q3 2028. Epoch AI chip estimate (modelled from satellite imagery, cooling equipment and chip availability); not an operator disclosure. | epoch.ai |
| Stated investment | 8.6 USD bn | 2026-10-02 | Third-party estimate | Epoch AI modelled build cost, compute plus construction, 2025 USD, scaled from IT power; not a disclosed spend. | epoch.ai |
| IT power | 228 MW | 2026-10-02 | Third-party estimate | Epoch AI modelled IT power from satellite imagery and permits; not operator-stated. Epoch projects 840 MW by Q3 2028. | epoch.ai |
How it is powered
| Source | Provider | MW | Status | As of | Basis | Note | Source link |
|---|---|---|---|---|---|---|---|
| Grid | Entergy Mississippi | - | operating | 2026-10 | Third-party estimate | Mississippi Development Authority cites Entergy Mississippi power commitment for Amazon; Epoch lists Entergy as the energy company for Ridgeland. No MW stated. | mississippi.orgepoch.ai |
How AI campuses are powered: capacities are what the operator, utility or filing states, not what has been delivered.
The read
Amazon Web Services' Ridgeland campus in Madison County, Mississippi, the second of two AWS campuses there with Canton. The Mississippi Free Press reports Ridgeland uses groundwater only about 9 percent of the year and plans over 800 backup diesel generators across the Madison County campuses, and the state's 9 April 2026 announcement adds 11 billion dollars of Madison County investment framed around generative AI; neither gives per-campus hardware or MW. Epoch AI's AI data centers dataset (CC BY 4.0) estimates about 261,200 Trainium2 chips and 228 MW of IT power as of 2 October 2026, with buildings 1 to 4 operational by May 2026, and projects about 502,400 Trainium3 chips and 840 MW by Q3 2028. Epoch labels a link to Anthropic and Project Rainier as speculative, so this row is not tied to the Project Rainier row. All figures are modelled estimates in the metrics table only. Hardware rests on Epoch alone, so the tier is reported.
Timeline
Site & facility
AWS Ridgeland Data Center Campus
- Location
- Ridgeland, MS, USA
- Utility
- Entergy Mississippi
Change history
- 2026-10-04 Added AWS Ridgeland Campus
Nearby in scale
The machines closest to AWS Ridgeland Campus by accelerator count, smaller to larger.
- xAI Colossus 2 · USA, operational · 220,000 accelerators
- Stargate Abilene · USA, operational · 201,600 accelerators
- Microsoft Fairwater (Wisconsin) · USA, operational · 176,391 accelerators
- Microsoft Fairwater (Atlanta) · USA, operational · 304,279 accelerators
- Google Council Bluffs East TPU Campus · USA, operational · 305,600 accelerators
- AWS Madison Mega Site (Canton) · USA, operational · 326,600 accelerators
Related systems
Same operator
- AWS Madison Mega Site (Canton) · USA, operational, 2025
- Project Rainier · USA, operational, 2025
- AWS Susquehanna Campus (Salem Township) · USA, operational
- Project Ceiba · USA, under construction
- Amazon EC2 C3 Instance Cluster · USA, operational, 2013
- Amazon EC2 Cluster Compute Instances · USA, operational, 2011
Same accelerator
- AWS Trainium2 UltraServer · USA, operational
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| epoch.ai | names system only | - |
| mississippi.org | could not be fetched | - |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.