COMPUTE ATLAS Supercomputer supply-chain graph
1153 systems 482 sites Sourced data

Supercomputers/Systems/Firmus Batam AI Factory

Indonesia · planned · mixed

Firmus Batam AI Factory

Also known as Firmus DayOne Batam

Operated by Firmus Technologies at Batam AI Factory Campus .

Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Firmus HyperCube liquid-cooled architecture with NVIDIA DSX, developed with DayOne
Firmus Technologies
- Reported firmus.co
Accelerator -
Up to 170,000 NVIDIA accelerators across Grace Blackwell, Vera Rubin and Vera platforms, delivered through 2027 and 2028
NVIDIA - Reported firmus.co

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Accelerators 170,000 accelerators 2026-06 Design target Firmus: up to 170,000 NVIDIA accelerators at the Batam campus, deployed through 2027 and 2028. Planned maximum. firmus.co
Facility power 360 MW 2026-06 Design target Firmus: 360 MW campus power for the Batam AI factory with DayOne. IT vs total not stated. Planned campus figure. firmus.co

The read

A 360 MW AI factory campus on Batam island that Firmus is developing with Singapore-based DayOne under a compute agreement with NVIDIA running through 2034, announced 28 June 2026: up to 170,000 NVIDIA accelerators across Grace Blackwell, Vera Rubin and Vera platforms, delivered through 2027 and 2028, combining Firmus's HyperCube liquid-cooled design with NVIDIA DSX, and expected to draw 25 to 30 billion dollars of offtake over six years from AI-native customers. Firmus describes the campus as in development; one trade report cites a Q1 2027 operational target that Firmus does not state. Both sources trace to the announcement, so the tier is reported.

Timeline

Site & facility

Batam AI Factory Campus

Location
Batam, Indonesia
Cooling
Liquid cooling (HyperCube)

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
firmus.conames system only-
thetechcapital.comblocked our fetch-

Checked 2026-10-09 by pnpm verify. Re-run it and the table changes with the web.

Further reading