Supercomputers/Systems/Microsoft Fairwater (Atlanta)

USA · operational · ai training

Microsoft Fairwater (Atlanta)

Deep dive: Microsoft Fairwater: two sites, few numbers

Operated by Microsoft at Microsoft Atlanta AI datacenter site .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Accelerator NVIDIA GB200 NVL72
Accelerators
Arm CPU + CUDA GPU · TSMC 4NP
NVIDIA Blackwell GB200 and GB300 GPUs, up to 72 per rack
NVIDIA - Reported blogs.microsoft.com

Engineering, funding and access

What Microsoft Fairwater (Atlanta) runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Interconnect and topologyNVLink within each 72-GPU rack; two-tier Ethernet scale-out backend at 800 Gbps per GPU on one flat network, running Microsoft's SONiC switch OS; dedicated AI WAN to other Fairwater sitesMicrosoft does not name the switch vendor; one trade article says Spectrum-X, which Microsoft's post does not confirm.2025-11-12Operator statedblogs.microsoft.com
Cooling designFacility-wide closed-loop liquid cooling with no evaporation plus rack-level direct liquid cooling; initial fill equals the annual water use of about 20 homes, designed for 6+ years without replacement2025-11-12Operator statedblogs.microsoft.com

Funding

ItemDetailAs ofBasisSource
ProcurementBuilt by QTS in Fayetteville, Georgia with Microsoft as tenant, per Epoch AIEpoch's listing; Microsoft's own post does not name the builder.2026-06Press reportepoch.ai

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Accelerators 304,279 accelerators 2026-06-14 Third-party estimate Epoch AI chip estimate, latest per chip type (B200); some rows are company disclosures, others modelled. epoch.ai
Stated investment 24.1 USD bn 2026-06-14 Third-party estimate Epoch AI modelled build cost, compute plus construction, 2025 USD, scaled from IT power; not a disclosed spend. epoch.ai
Facility power 859 MW 2026-06-14 Third-party estimate Epoch AI modelled gross facility power (IT plus cooling and overhead) at this timeline date. epoch.ai
IT power 636 MW 2026-06-14 Third-party estimate Epoch AI modelled IT power from satellite imagery and permits at this timeline date; not operator-stated. epoch.ai
Rack power 140 kW 2025-11 Operator stated Microsoft Fairwater design: about 140 kW per rack and 1,360 kW per row, up to 72 Blackwell GPUs per rack, as described for the Atlanta site blogs.microsoft.com

How it is powered

SourceProviderMWStatusAs ofBasisNoteSource link
Grid Georgia Power - operating 2025-11 Operator stated Microsoft: highly available utility power lets Atlanta skip on-site generation and UPS. It does not name the utility; Epoch lists Georgia Power. No MW stated. blogs.microsoft.comepoch.ai
Battery storage Microsoft - planned 2025-11 Operator stated Microsoft describes an on-site energy storage solution to mask power oscillations from large training jobs; capacity not stated. blogs.microsoft.com

How AI campuses are powered: capacities are what the operator, utility or filing states, not what has been delivered.

The read

Microsoft describes an Atlanta AI datacenter of NVIDIA Blackwell GB200 and GB300 GPUs at up to 72 per rack, about 140 kW per rack, on a two-tier 800 Gbps Ethernet fabric and a dedicated AI wide-area network that links it to the Wisconsin site. Microsoft gives no GPU count and no facility power, and trade press repeats Microsoft's release rather than corroborating it, so this stays reported. The network vendor is a live disagreement (Microsoft's blog describes SONiC-based Ethernet, one trade article says Spectrum-X), so no interconnect row is written.

Timeline

  • 2025-10 Epoch AI estimates buildings 1 and 2 operational, about 321 MW of IT load source
  • 2025-11 Announced source
  • 2026-06 Epoch AI estimates buildings 3 and 4 operational, taking the campus to about 636 MW of IT load source

Site & facility

Microsoft Atlanta AI datacenter site

Location
Atlanta, GA, USA
Cooling
Closed-loop liquid cooling
Commissioned
2025

Where sources disagree

We record conflicts instead of picking a winner quietly. All open questions.

Change history

Nearby in scale

The machines closest to Microsoft Fairwater (Atlanta) by accelerator count, smaller to larger.

Same operator

Same accelerator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
blogs.microsoft.comnames system and partNVIDIA GB200 NVL72

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.

Related news

  • Microsoft links Fairwater Atlanta and Wisconsin into one "AI superfactory" · Microsoft
    The two Fairwater sites are joined over a dedicated AI WAN fiber backbone so training jobs can span both facilities as one system rather than two separate clusters, a different scaling strategy than the single site gigawatt campuses xAI and Meta are building. Each rack carries up to 72 NVIDIA Blackwell GPUs; Microsoft has not disclosed a total GPU count for either site.