Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 773.70 TFlop/s
- Rpeak
- 961.13 TFlop/s
- Rmax ÷ Rpeak
- 80.5%
- Cores
- 46,208
- Power
- 924 kW
- Per watt
- 0.8 GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Zin, and those in USA. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 773.70 TFlop/s | #41 of 179 · top 22% | #191 of 332 · bottom 44% |
| Energy efficiency | 0.8 GF/W | #66 of 133 · top 49% | #112 of 162 · bottom 32% |
| Rmax ÷ Rpeak | 80.5 % | #110 of 178 · bottom 39% | #102 of 331 · top 31% |
| Power draw | 924 kW | #39 of 135 · top 28% | #65 of 171 · top 38% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Xtreme-X GreenBlade GB512X (Appro) | Cray HPENYSE
rolls up to Hewlett Packard Enterprise | - | Reported | top500.orghpc.llnl.gov |
| CPU | Intel Xeon E5-2670 CPUs x86-64 · 8C · 2.6 GHz · 32 nm · 115 W Xeon E5 (Sandy Bridge-EP) 8C 2.60GHz | Intel | - | Reported | top500.org |
| Interconnect | Mellanox InfiniBand QDR Interconnect Fat tree · 40 Gb/s per 4x port Infiniband QDR | NVIDIA | - | Reported | top500.orghpc.llnl.gov |
| Operating system | Red Hat Enterprise Linux Operating systems Linux distribution · Open source, commercial support subscription RHEL 6.2 | Red Hat | - | Reported | top500.org |
Engineering, funding and access
What Zin runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 2,916 nodes2,742 batch, 32 debug and 20 login nodes on the decommissioned-platform page; 16 cores and 32 GiB per node. | 2026-11 | Operator stated | hpc.llnl.gov |
| Interconnect and topology | InfiniBand QDR | 2026-11 | Operator stated | hpc.llnl.gov |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Programming and software stack | TOSS 3 operating environment | 2026-11 | Operator stated | hpc.llnl.gov |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Funding programme | NNSA Advanced Simulation and Computing (ASC)LLNL lists the program as ASC and the commissioning year as 2012. | 2026-11 | Operator stated | hpc.llnl.gov |
| Procurement | Appro cluster bought in the TLCC2 (Tri-Lab Linux Capacity Cluster 2) procurement | 2026-11 | Operator stated | hpc.llnl.gov |
The read
Livermore Computing's Appro Xtreme-X GreenBlade cluster for the NNSA Advanced Simulation and Computing program, 15th on the November 2011 TOP500. TOP500 lists 46,208 Xeon E5-2670 8-core 2.6 GHz cores on InfiniBand QDR at 773.7 TFlop/s Rmax and 961.13 TFlop/s Rpeak, with TOP500 recording a 2011 installation year. LLNL's own page, now marked decommissioned, independently confirms the Appro build, the InfiniBand QDR interconnect and 2,916 nodes with 46,656 cores (it counts login and debug nodes and says commissioned 2012), and lists Zin in its SCF (secure) zone. No decommissioning date is published there, so none is recorded. TOP500 names the manufacturer as Cray/HPE while LLNL names Appro. TOP500 is the only source for Rmax and Rpeak, so the tier is reported.
Timeline
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Livermore Computing Center
- Location
- Livermore, CA, USA
- Cooling
- Direct liquid cooling (warm water)
- Commissioned
- 1996
Change history
- 2026-10-02 Added Zin, the LLNL Appro Xtreme-X cluster, 15th on the November 2011 TOP500
Nearby in scale
The machines closest to Zin by Rmax, smaller to larger.
- Tianhe-1A Hunan Solution · China, decommissioned · 0.77 PFlop/s
- GOSAT-2 RCF2 · Japan, operational · 0.77 PFlop/s
- ForHLR II · Germany, decommissioned · 0.77 PFlop/s
- XStream · USA, decommissioned · 0.78 PFlop/s
- Brown (Purdue) · USA, decommissioned · 0.79 PFlop/s
- Draco · Germany, decommissioned · 0.79 PFlop/s
Related systems
Same site
- Cab · USA, decommissioned, 2012
- Edge (LLNL) · USA, operational, 2010
- Sequoia · USA, decommissioned, 2012
- Vulcan · USA, decommissioned, 2012
- Hera (LLNL) · USA, operational, 2009
- Atlas (LLNL) · USA, decommissioned, 2007
Same operator
- Jade (LLNL) · USA, operational, 2016
- Quartz (LLNL) · USA, decommissioned, 2016
- ASC Purple · USA, decommissioned, 2005
- Ansel (LLNL) · USA, operational, 2018
- BlueGene/L · USA, decommissioned, 2004
- Lassen · USA, decommissioned, 2018
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
Every source cited on this page was readable, and none of them mentions this system. They are cited at page granularity, normally because no stable deep link could be found. That is a real weakness in this row and it is why the system carries a confidence tier below verified. See how this check works.
| Cited source | Result | Found on the page |
|---|---|---|
| hpc.llnl.gov | does not name this system | Intel Xeon E5-2670 |
| top500.org | does not name this system | Intel Xeon E5-2670, Mellanox InfiniBand QDR |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.