Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 17.19 PFlop/s
- Rpeak
- 27.96 PFlop/s
- Rmax ÷ Rpeak
- 61.5%
- Cores
- 149,760
- Power
- 725.9 kW
- Per watt
- 23.7 GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of SuperMUC-NG Phase 2, and those in Germany. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 17.19 PFlop/s | - | #10 of 95 · top 10% |
| Energy efficiency | 23.7 GF/W | - | #18 of 68 · top 25% |
| Rmax ÷ Rpeak | 61.5 % | - | #79 of 94 · bottom 17% |
| Power draw | 726 kW | - | #24 of 69 · top 34% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - 240 Lenovo ThinkSystem SD650-I V3 Neptune DWC nodes | Lenovo | 240 reported | Verified | doku.lrz.detop500.org |
| Accelerator | Intel Data Center GPU Max 1550 Accelerators oneAPI (Xe-HPC) · Intel 7 / TSMC N5 · 600 W 960 Intel Data Center GPU Max 1550 (Ponte Vecchio), four per node | Intel | 960 reported | Reported | doku.lrz.de |
| CPU | - two Xeon Platinum 8480+ per node, 240 nodes | Intel | 480 estimated | Reported | doku.lrz.de |
| Interconnect | NVIDIA InfiniBand HDR Interconnect Fat tree or dragonfly+ · 200 Gb/s per port · About 0.6 microseconds NVIDIA/Mellanox HDR InfiniBand 200 Gb/s fat tree | NVIDIA | - | Reported | doku.lrz.de |
| Storage | Intel DAOS Storage Object store, no POSIX layer underneath · 230 PB on Aurora · About 31 TB/s 1 PB DAOS tier at 750 GB/s alongside 50 PB and 20 PB file systems | Intel | - | Reported | doku.lrz.de |
| Cooling | Direct liquid cooling, warm water Cooling Direct-to-chip cold plates, facility water loop · Removes 90+ percent of node heat to liquid Lenovo Neptune direct warm-water cooling | Lenovo | - | Reported | doku.lrz.de |
Engineering, funding and access
What SuperMUC-NG Phase 2 runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 240 nodesIncludes 4 login nodes and 2 spares; each node has two Xeon Platinum 8480+ and four Intel Data Center GPU Max 1550 | 2023-11 | Operator stated | doku.lrz.de |
| Total memory | 122.88 TBDDR5 system memory; a further 122.88 TB of HBM2e on the 960 GPUs | 2023-11 | Operator stated | doku.lrz.de |
| Storage capacity | 71 PBHPPFS 50 PB and DSS 20 PB shared with Phase 1, plus 1 PB DAOS | 2023-11 | Operator stated | doku.lrz.de |
| Interconnect and topology | NVIDIA/Mellanox HDR InfiniBand 200 Gb/s fat tree, two interconnects per node, single island | 2023-11 | Operator stated | doku.lrz.detop500.org |
| Cooling design | Direct warm-water cooling | 2023-11 | Operator stated | doku.lrz.de |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Parallel filesystem | IBM Spectrum Scale (GPFS): HPPFS 50 PB at 500 GB/s and DSS 20 PB at 70 GB/s, plus 1 PB DAOS at 750 GB/s | 2023-11 | Operator stated | doku.lrz.de |
| Job scheduler | Slurm | 2023-11 | Operator stated | doku.lrz.de |
| Programming and software stack | SUSE Linux Enterprise Server, Intel oneAPI, Intel MPI and Open MPI | 2023-11 | Operator stated | doku.lrz.detop500.org |
The read
The GPU extension of LRZ's flagship: 240 Lenovo ThinkSystem SD650-I V3 nodes, each with two Xeon Platinum 8480+ and four Intel Data Center GPU Max 1550 (960 GPUs, 128 GB HBM2e each), on HDR InfiniBand with a 1 PB DAOS tier alongside 50 PB and 20 PB file systems, warm-water cooled. First ranked 51st on the November 2023 TOP500 and 127th on the June 2026 list. LRZ's documentation gives the hardware and TOP500 the 17.19 PFlop/s Rmax, 27.96 PFlop/s peak, 149,760 cores and 725.9 kW; TOP500 alone supplies those performance and core figures, so the tier is reported. LRZ's news page described the machine as in pilot operation in early 2024, so no first-operational date is recorded.
Timeline
- 2023-11 Listed at #51 on the TOP500 (November 2023) source
- 2023-11 SuperMUC-NG Phase 2 debuted at rank 51 on the November 2023 TOP500 at 17.19 PFlop/s source
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Leibniz Supercomputing Centre, Garching
- Location
- Garching, Germany
- Cooling
- Direct warm-water cooling
- Commissioned
- 2006
Change history
- 2026-10-02 Added SuperMUC-NG Phase 2 at LRZ
Nearby in scale
The machines closest to SuperMUC-NG Phase 2 by Rmax, smaller to larger.
- Sequoia · USA, decommissioned · 17.17 PFlop/s
- Pioneer-WUS2 · USA, operational · 16.59 PFlop/s
- Pioneer-WEU · Netherlands, operational · 16.59 PFlop/s
- AOBA-S · Japan, operational · 17.22 PFlop/s
- HiPerGator AI · USA, operational · 17.49 PFlop/s
- OpenCanvas GPUaaS SP1 · Japan, operational · 17.53 PFlop/s
Related systems
Same site
- HLRB-II · Germany, decommissioned, 2007
- SuperMUC · Germany, decommissioned, 2012
- CoolMUC-2 · Germany, decommissioned, 2015
- SuperMUC Phase 2 · Germany, decommissioned, 2015
- CoolMUC-3 · Germany, decommissioned, 2017
- SuperMUC-NG · Germany, operational, 2018
Same operator
- HLRB SR8000-F1 · Germany, decommissioned, 2000
- LRZ Cerebras CS-2 · Germany, operational, 2022
- CoolMUC-4 · Germany, operational, 2024
- Blue Lion · Germany, planned
Same accelerator
- Clementina XXI · Argentina, operational
- Aurora · USA, operational, 2023
- Lichtenberg II Phase 2 · Germany, operational, 2023
- Dawn · United Kingdom, operational, 2024
- Stampede3 · USA, operational, 2024
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| doku.lrz.de | blocked our fetch | - |
| top500.org | names system and part | Intel Data Center GPU Max 1550, NVIDIA InfiniBand HDR |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Inside a node
Why accelerators exist, what the memory hierarchy costs, and how the CPU and accelerator merged onto one package.
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.