COMPUTE ATLAS Supercomputer supply-chain graph
1581 systems 558 sites Sourced data

Supercomputers/Systems/HiPerGator AI

USA · operational · ai training

HiPerGator AI

Also known as HiPerGator 4.0 AI SuperPOD

Operated by University of Florida .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
17.49 PFlop/s
HPL measured
Rpeak
19.00 PFlop/s
Rmax ÷ Rpeak
92.1%
Cores
81,648
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

How it compares

Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of HiPerGator AI, and those in USA. Computed from our tables; a metric is ranked only when at least eight peers report it.

MetricValueAgainst its eraAgainst its country
Rmax17.49 PFlop/s#44 of 210 · top 21%#35 of 332 · top 10%
Rmax ÷ Rpeak92.1 %#8 of 207 · top 3%#12 of 331 · top 3%

Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
NVIDIA DGX B200 SuperPOD, 63 DGX B200 systems
NVIDIA 63
reported
Verified top500.orgnews.ufl.edu
Accelerator NVIDIA B200 SXM
Accelerators
CUDA (Blackwell) · TSMC 4NP · 1,000 W
504 NVIDIA Blackwell B200 GPUs (180 GB) in 63 DGX B200 nodes
NVIDIA 504
reported
Reported it.ufl.edu
Accelerator NVIDIA A100 (in DGX A100)
Accelerators
140 NVIDIA DGX A100 systems (original 2021 SuperPOD, being replaced by DGX B200)
NVIDIA - Reported news.ufl.edu
CPU Intel Xeon Platinum 8570
CPUs
x86-64 · 56C · 2.1 GHz · Intel 7
Intel Xeon Platinum 8570 56C 2.1GHz
Intel - Reported top500.org
Interconnect NVIDIA InfiniBand NDR (Quantum-2)
Interconnect
Fat tree or dragonfly+ · 400 Gb/s per port · Under 0.6 microseconds
NVIDIA Quantum-2 InfiniBand NDR400, 400 Gb/s per GPU
NVIDIA - Verified top500.orgnews.ufl.edu
Storage Lustre
Storage
Parallel filesystem, separate metadata and object servers
Two-tier Lustre: 36 PB capacity tier and 11 PB all-flash DDN tier (over 70 PB total distributed storage)
DDN
- Reported it.ufl.edu
Operating system Red Hat Enterprise Linux
Operating systems
Linux distribution · Open source, commercial support subscription
RHEL 9.5
Red Hat
IBMNYSE rolls up to IBM
- Reported top500.org

Engineering, funding and access

What HiPerGator AI runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Compute nodes63 nodes63 NVIDIA DGX B200 nodes with 8 B200 GPUs each (504 GPUs).2025-10Operator statedit.ufl.edu
Interconnect and topologyNVIDIA InfiniBand NDR4002026-06Operator statedtop500.org

Software

ItemDetailAs ofBasisSource
Parallel filesystemLustre in two tiers: Orange (36 PB, capacity) and Blue (11 PB all-flash DDN)2025-10Operator statedit.ufl.edu
Job schedulerSlurm2026Operator stateddocs.rc.ufl.edu
Programming and software stackRHEL 9.5, GCC 11.2.1, CUDA 12.8.93 and NVIDIA HPCX 2.23 (as submitted for the TOP500 HPL run)2026-06Operator statedtop500.org

Funding

ItemDetailAs ofBasisSource
Funded byUniversity of Florida investment model since 2013, backed by the Provost, the Vice President for Research and the CIO2025-10Operator statedit.ufl.edu
Stated cost33 USD mUF states the fourth-generation HiPerGator purchase cost $33 million; it covers the whole fourth generation, not only the AI SuperPOD.2025-10Operator statedit.ufl.edu

Access

ItemDetailAs ofBasisSource
How researchers get timeFaculty investors buy allocations and sponsor other users; free semester teaching allocations and a free three-month trial are offered2025-10Operator statedit.ufl.edu
Access pageit.ufl.edu/rc/hipergator2025-10Operator statedit.ufl.edu

Results

ItemDetailAs ofBasisSource
Notable result2025: UF reports HiPerGator ranks first among US university-owned supercomputers on the TOP500, TOP500 HPCG and IO500 lists2025Operator statedit.ufl.edu
Notable result2025: UF is the only academic institution submitting to MLPerf Training and says it ranks in the top three on all seven benchmarks2025Operator statedit.ufl.edu

The read

The University of Florida's NVIDIA DGX SuperPOD AI system within its HiPerGator supercomputer. The original SuperPOD, announced in July 2020 and opened to the state university system in January 2021, was 140 NVIDIA DGX A100 systems on HDR InfiniBand (UF news release), a configuration UF reports ranked 22nd on the June 2021 TOP500 and 2nd on the Green500. UF's Board of Trustees approved a 24 million dollar upgrade, and UF now lists an AI SuperPOD of 63 NVIDIA DGX B200 nodes with 504 B200 GPUs on Quantum-2 NDR InfiniBand, with first delivery in 2025. The HPL figures here (17.49 PFlop/s Rmax, 19.00 PFlop/s Rpeak, 81,648 cores) are TOP500's current entry for the DGX B200 system (Xeon Platinum 8570 hosts, Infiniband NDR400, RHEL 9.5). UF's storage is a two-tier Lustre system (36 PB capacity tier and an 11 PB all-flash DDN tier). The rest of HiPerGator (about 60,000 AMD EPYC cores, L4 and RTX PRO 6000 GPUs) is not modelled here. The UF data center location was not stated in the sources fetched, so no site is attached.

Timeline

  • 2020-07 Announced source
  • 2021 First operational source
  • 2025-10 UF unveiled the fourth generation of HiPerGator with Mark III and NVIDIA, and says it received the first DGX B200 delivery worldwide source
  • 2025-11 Listed at #106 on the TOP500 (November 2025) source

Public list appearances

Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.

Change history

Nearby in scale

The machines closest to HiPerGator AI by Rmax, smaller to larger.

Same operator

Same accelerator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
it.ufl.edunames system, part and countNVIDIA B200 SXM, Lustre · counts: 504
top500.orgnames system and partNVIDIA B200 SXM, Intel Xeon Platinum 8570, NVIDIA InfiniBand NDR (Quantum-2), NVIDIA A100 (in DGX A100)

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.

Further reading