Supercomputers/Systems/Berzelius
Sweden · operational · ai training
Berzelius
Operated by NSC at NSC Data Centre, Linkoping .
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 5.25 PFlop/s
- Rpeak
- 9.64 PFlop/s
- Rmax ÷ Rpeak
- 54.5%
- Cores
- 59,520
- Power
- -
- Per watt
- - GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Berzelius, and those in Sweden. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 5.25 PFlop/s | #103 of 210 · top 49% | #5 of 18 · top 24% |
| Rmax ÷ Rpeak | 54.5 % | #183 of 207 · bottom 13% | #17 of 18 · bottom 7% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Bull-built NVIDIA DGX SuperPOD (per TOP500 manufacturer field) | Bull | - | Reported | top500.org |
| Accelerator | NVIDIA A100 SXM4 40GB Accelerators CUDA (Ampere GA100) · 6,912C · 1.41 GHz · 7 nm · 400 W 60 thin DGX A100 nodes with 8 A100 40 GB GPUs each | NVIDIA | 480 reported | Reported | nsc.liu.se |
| Accelerator | - 34 fat DGX A100 nodes with 8 A100 80 GB GPUs each | NVIDIA | 272 reported | Reported | nsc.liu.se |
| Accelerator | NVIDIA H200 SXM Accelerators CUDA (Hopper GH100) · 16,896C · 1.98 GHz · TSMC 4N · 700 W Berzelius Hopper: 16 DGX H200 nodes with 8 H200 141 GB GPUs each | NVIDIA | 128 reported | Reported | nsc.liu.se |
| CPU | AMD EPYC 7742 (Rome) CPUs x86-64 · 64C · 2.25 GHz · 7 nm · 225 W Berzelius Ampere: 94 DGX A100 nodes, two AMD EPYC 7742 each | AMD | - | Reported | nsc.liu.setop500.org |
| CPU | Intel Xeon Platinum 8480C CPUs x86-64 · 56C · 2 GHz · Intel 7 · 350 W Berzelius Hopper DGX H200 nodes: two Intel Xeon 8480C each | Intel | - | Reported | nsc.liu.se |
| Interconnect | NVIDIA InfiniBand HDR Interconnect Fat tree or dragonfly+ · 200 Gb/s per port · About 0.6 microseconds 8x NVIDIA Mellanox HDR per DGX A100, non-blocking fat-tree | NVIDIA | - | Reported | nsc.liu.setop500.org |
| Interconnect | NVIDIA InfiniBand NDR (Quantum-2) Interconnect Fat tree or dragonfly+ · 400 Gb/s per port · Under 0.6 microseconds 8x NVIDIA Mellanox NDR per DGX H200, non-blocking fat-tree | NVIDIA | - | Reported | nsc.liu.se |
| Storage | VAST Data Platform Storage Disaggregated shared-everything 3 PB VAST Data cluster with NVMe-oF | VAST Data | - | Reported | nsc.liu.se |
Engineering, funding and access
What Berzelius runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 110 nodes94 DGX A100 nodes (Ampere) plus 16 DGX H200 nodes (Hopper); excludes 8 CPU nodes in each of the two sections. | 2025 | Operator stated | nsc.liu.se |
| Storage capacity | 3 PBInstalled physical capacity of the shared VAST Data cluster; NSC says effective capacity is higher thanks to compression and deduplication. | 2025 | Operator stated | nsc.liu.se |
| Interconnect and topology | Non-blocking fat-tree; 8 NVIDIA Mellanox HDR links per DGX A100 and 8 NDR links per DGX H200, separate networks for Ampere and HopperEach node also has a dedicated HDR link for storage. | 2025 | Operator stated | nsc.liu.se |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Parallel filesystem | VAST Data storage cluster with 8 CBoxes and 3 DBoxes over NVMe-oF, on a network separate from the compute fabric | 2025 | Operator stated | nsc.liu.se |
| Job scheduler | SlurmLogin by SSH or ThinLinc remote desktop. | 2025 | Operator stated | nsc.liu.se |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Funded by | Knut and Alice Wallenberg FoundationDonated the system to NSC in 2020 and funded the 2023 and 2025 expansions through further donations. | 2025 | Operator stated | nsc.liu.se |
| Procurement | Delivered by Atos on NVIDIA's DGX SuperPOD architecture with DDN AI400X storage; digital inauguration reported 23 March 2021 | 2021-03 | Operator stated | liu.se |
Access
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| How researchers get time | Apply in SUPR in the LiU Berzelius round; PI must be at least an assistant professor with a Knut and Alice Wallenberg Foundation affiliation and an AI/ML-focused project, reviewed monthlyMaximum requests are 28,800 GPU-h/month on Ampere and 11,520 GPU-h/month on Hopper. | 2026 | Operator stated | nsc.liu.se |
| Access page | www.nsc.liu.se/support/systems/berzelius-resource-allocationNSC page describing eligibility and the SUPR application round. | 2026 | Operator stated | nsc.liu.se |
AI datacenter metrics
Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.
| Metric | Value | As of | Basis | Note | Source |
|---|---|---|---|---|---|
| Accelerators | 880 accelerators | 2026-10 | Operator stated | 752 A100 (94 DGX-A100 nodes) plus 128 H200 (16 DGX-H200 nodes) per NSC; sum is our addition. | nsc.liu.se |
The read
Sweden's AI-focused NVIDIA DGX SuperPOD at the National Supercomputer Centre in Linkoping, installed in spring 2021 with 60 DGX A100 nodes, expanded in 2023 to 94 DGX A100 nodes (60 with 40 GB and 34 with 80 GB A100 GPUs, HDR InfiniBand) and again with Berzelius Hopper, 16 DGX H200 nodes on NDR InfiniBand, plus a 3 PB VAST Data storage cluster. TOP500 lists the system as built by Bull and ranked it 82nd on the June 2021 list at 5.25 PFlop/s Rmax on 59,520 cores; those TOP500 figures describe the 2021 configuration and are not restated for the expanded machine.
Timeline
- 2021 First operational source
- 2021-03 Digitally inaugurated with 60 NVIDIA DGX A100 systems (480 GPUs) funded by a EUR 29.5 million Knut and Alice Wallenberg Foundation donation source
- 2021-06 Listed at #82 on the TOP500 (June 2021) source
- 2023 Expanded to 94 DGX A100 nodes through a further Knut and Alice Wallenberg Foundation donation source
- 2025 Hopper section added with 16 DGX H200 nodes, funded by a further Knut and Alice Wallenberg Foundation donation source
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Change history
- 2026-10-04 Added AI datacenter metrics for berzelius
- 2026-10-01 Added Berzelius (NSC)
Nearby in scale
The machines closest to Berzelius by Rmax, smaller to larger.
- CLAIX-2023 · Germany, operational · 5.24 PFlop/s
- Tursa · United Kingdom, operational · 5.23 PFlop/s
- Cosmos (SDSC) · USA, operational · 5.18 PFlop/s
- Pangea II · France, upgraded · 5.28 PFlop/s
- Wind River · USA, operational · 5.33 PFlop/s
- Mahti · Finland, decommissioned · 5.39 PFlop/s
Related systems
Same site
- Stratus (NSC) · Sweden, operational, 2018
- Tetralith · Sweden, decommissioned, 2018
- Bifrost · Sweden, operational, 2015
- Triolith · Sweden, decommissioned, 2012
- Neolith · Sweden, operational, 2007
Same operator
- NSC Monolith · Sweden, operational, 2002
Same accelerator
- ABCI 2.0 · Japan, operational, 2021
- AlphaCentauri · Germany, operational, 2021
- Athena · Poland, operational, 2021
- Baskerville · United Kingdom, decommissioned, 2021
- Earth Simulator 4 · Japan, operational, 2021
- Hortense · Belgium, operational, 2021
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| top500.org | names system and part | AMD EPYC 7742 (Rome), NVIDIA A100 SXM4 40GB, NVIDIA InfiniBand HDR, NVIDIA InfiniBand NDR (Quantum-2) |
| nsc.liu.se | names system, part and count | AMD EPYC 7742 (Rome), NVIDIA A100 SXM4 40GB, NVIDIA H200 SXM, VAST Data Platform · counts: 480 |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.