Supercomputers/Systems/Grizzly
USA · operational · hpc
Grizzly
Also known as LANL CTS-1 Grizzly
Operated by Los Alamos National Laboratory at Los Alamos Strategic Computing Complex .
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 1.52 PFlop/s
- Rpeak
- 1.79 PFlop/s
- Rmax ÷ Rpeak
- 84.9%
- Cores
- 53,352
- Power
- 603.4 kW
- Per watt
- 2.5 GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Grizzly, and those in USA. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 1.52 PFlop/s | #95 of 242 · top 39% | #160 of 332 · top 48% |
| Energy efficiency | 2.5 GF/W | #74 of 176 · top 42% | #71 of 162 · top 43% |
| Rmax ÷ Rpeak | 84.9 % | #40 of 238 · top 16% | #53 of 331 · top 16% |
| Power draw | 603 kW | #88 of 178 · top 49% | #81 of 171 · top 47% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Penguin Computing Tundra Extreme Scale (CTS-1) | Penguin Computing | - | Reported | top500.org |
| CPU | Intel Xeon E5-2695 v4 CPUs x86-64 · 18C · 2.1 GHz · 14 nm · 120 W Xeon E5-2695v4 18C 2.1GHz (Broadwell) | Intel | - | Reported | top500.org |
| Interconnect | Omni-Path Architecture Interconnect Fat tree · 100 Gb/s per port · About 1 microsecond Intel Omni-Path | Intel | - | Reported | top500.org |
Engineering, funding and access
What Grizzly runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 1,498 nodesFrom the description of LANL's public Grizzly job-data repository | 2022-11 | Operator stated | github.com |
| Interconnect and topology | Intel Omni-PathTOP500 list entry | 2016-11 | Operator stated | top500.org |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Job scheduler | SlurmLANL's dataset holds Slurm controller logs for January to November 2018 and Slurm accounting data for December 2021 to November 2022 | 2022-11 | Operator stated | github.com |
| Programming and software stack | TOSS Linux; the TOP500 HPL run used Intel compiler 2016u4, MKL 11.3.3.210 and Intel MPI 5.1.3.181TOP500 list entry | 2016-11 | Operator stated | top500.org |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Procurement | Bought through NNSA's tri-lab CTS-1 contract, awarded by LLNL to Penguin Computing on 21 October 2015: $39 million for more than 7 PFlop/s across Los Alamos, Sandia and Livermore, delivered April 2016 to September 2018The LLNL release does not name Grizzly; TOP500 lists the machine as LANL CTS-1 Grizzly, built by Penguin Computing | 2015-10-21 | Operator stated | llnl.govtop500.org |
The read
Los Alamos' institutional-computing Penguin Tundra Extreme Scale cluster from the CTS-1 commodity procurement: Xeon E5-2695v4 18-core Broadwell processors on Intel Omni-Path running TOSS. TOP500 lists 53,352 cores, 1.52 PFlop/s Rmax, 1.79 PFlop/s peak and 603.4 kW, ranking it 67th in November 2016 and 497th in June 2021. LANL's public job-data repository calls it a 1,498-node cluster and holds accounting records to November 2022, which sets the status date. TOP500 is the only source for the core count and Rmax.
Timeline
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Los Alamos Strategic Computing Complex
- Location
- Los Alamos, NM, USA
- Cooling
- Chilled water
- Commissioned
- 1993
Change history
- 2026-10-02 Added Grizzly, LANL
Nearby in scale
The machines closest to Grizzly by Rmax, smaller to larger.
- JADE2 · United Kingdom, operational · 1.47 PFlop/s
- Satori (MIT) · USA, operational · 1.46 PFlop/s
- Salomon · Czechia, decommissioned · 1.46 PFlop/s
- State Grid SGSystem · China, operational · 1.56 PFlop/s
- Cygnus · Japan, decommissioned · 1.58 PFlop/s
- HOKUSAI BigWaterfall · Japan, operational · 1.6 PFlop/s
Related systems
Same site
- Trinity · USA, decommissioned, 2017
- Cielo · USA, decommissioned, 2011
- Mustang (LANL) · USA, decommissioned, 2011
- Crossroads · USA, operational, 2023
- Roadrunner · USA, decommissioned, 2008
- Venado · USA, operational, 2024
Same operator
- Cerrillos · USA, decommissioned, 2008
- Mission (LANL) · USA, planned
- Vision (LANL) · USA, planned
- Veritas (LANL) · USA, planned
- LANL Lightning · USA, operational, 2003
- ASCI Q · USA, decommissioned, 2002
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| github.com | names system only | - |
| top500.org | names system and part | Intel Xeon E5-2695 v4, Omni-Path Architecture |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.