Supercomputers/Systems/KISTI-6
South Korea · under construction · mixed
KISTI-6
Quantum: linked to IonQ Tempo at KISTI (100 trapped ion qubits)
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- -
- Rpeak
- -
- Rmax ÷ Rpeak
- -
- Cores
- -
- Power
- -
- Per watt
- - GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - HPE Cray Supercomputing EX4000 | Hewlett Packard Enterprise | - | Reported | finance.yahoo.comintelligentcio.com |
| Accelerator | NVIDIA GH200 Grace Hopper Superchip Accelerators Arm CPU + CUDA GPU · TSMC 4N NVIDIA GH200 GPUs | NVIDIA | - | Reported | evertiq.com |
| Storage | HPE Cray ClusterStor E2000 Storage HPE Cray E2000 with NVMe and NL-SAS | Hewlett Packard Enterprise | - | Reported | finance.yahoo.com |
Engineering, funding and access
What KISTI-6 runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Storage capacity | 205 PBBoth reports give 205 PB; HPE's release names Cray E2000 storage with NVMe and NL-SAS disks but no capacity | 2026-09 | Press report | digitaltoday.co.krevertiq.com |
| Interconnect and topology | HPE Slingshot interconnect 400, with 400 Gb/s transfers between compute and storageHPE release as carried by Business Wire; DigitalToday gives network performance of at least 400 Gb/s | 2025-05 | Vendor stated | finance.yahoo.comdigitaltoday.co.kr |
| Cooling design | 100% fanless direct liquid cooling architecture, per HPEHPE says the system is housed in a government datacenter adapted for liquid cooling; the system notes record a conflicting report of 96 percent liquid cooling with rear-door heat exchangers | 2025-05 | Vendor stated | finance.yahoo.com |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Parallel filesystem | HPE Cray Supercomputing Storage Systems E2000 with NVMe and NL-SAS disks, managed with HPE Data Management Framework (DMF)HPE release as carried by Business Wire | 2025-05 | Vendor stated | finance.yahoo.com |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Funded by | Korean government through the Ministry of Science and ICTDigitalToday says the government signed the HPE contract and the ministry announced the user call with KISTI; HPE describes KISTI as a government-funded institute | 2026-09 | Press report | digitaltoday.co.kr |
| Stated cost | 275 USD mTotal budget of KRW 382.5 billion including KRW 78 billion (about USD 56 million) for five years of maintenance; the USD conversion is evertiq's | 2025-07 | Press report | evertiq.com |
| Procurement | HPE Cray Supercomputing EX4000 with an NVIDIA GH200 partition and a 5th Gen AMD EPYC partition, announced by HPE on 13 May 2025; evertiq reported on 31 July 2025 that KISTI had signed the construction contractDigitalToday (September 2026) says the government signed the HPE contract in May 2025; evertiq scheduled completion for the first half of 2026 | 2025-07 | Press report | evertiq.comfinance.yahoo.com |
Access
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| How researchers get time | 2026 National Supercomputer No. 6 Innovation Support Programme: industry, academic and institute researchers apply through the National Supercomputing Center website; tracks for national strategy (about 30%), R&D innovation (about 55%), industrial innovation and 1-node exploratory researchOfficial applications ran from 28 September to 16 October 2026 with document review and committee screening; R&D innovation gives 50 nodes for large-scale and 2 to 49 nodes for creative research | 2026-09-09 | Press report | digitaltoday.co.kr |
The read
South Korea's sixth national supercomputer, an HPE Cray EX4000 with NVIDIA GH200 and H200 GPUs and AMD EPYC CPUs. Installation finished in August 2026 and official service is targeted for December 2026. Its sources disagree on almost every headline figure: peak is given as 588, 600 and 614 PFlop/s, GPUs as 8,496 against node counts that do not reconcile, and cooling as fully fanless direct liquid against 96% liquid with rear-door exchangers, so no peak, GPU count or cooling edge is recorded. HPE's own release is reachable here only through a Business Wire copy, so the tier is reported.
Timeline
- 2025-05 Announced source
- 2026-08 KISTI completed installation and basic checks of the system and moved on to performance and stability testing source
- 2026-09-09 The Ministry of Science and ICT and KISTI opened the call for users, with pilot use planned from late October and official service targeted for December 2026 source
Site & facility
Where sources disagree
We record conflicts instead of picking a winner quietly. All open questions.
- Peak performance: 600 PFlop/s (HPE release copy) against 614 PFlop/s (DigitalToday). A third source gives 588; no peak is recorded.
- Cooling: 100% fanless direct liquid cooling (HPE) against 96% liquid cooled with rear-door exchangers. No cooling edge is recorded.
Change history
- 2026-09-20 Planned system added; its sources disagree on peak, GPUs and cooling
Related systems
Same site
- Nurion · South Korea, operational, 2018
- KISTI GAIA · South Korea, operational, 2009
- Tachyon II · South Korea, decommissioned, 2009
- Tachyon · South Korea, operational, 2008
Same operator
- KISTI Cray T3E-900 · South Korea, operational, 1997
- KISTI Cray Y-MP C916 · South Korea, operational, 1993
Same accelerator
- DAEDALUS · Greece, under construction
- Discovery 6 · USA, operational, 2025
- Isambard-AI Phase 2 · United Kingdom, operational, 2025
- JUPITER · Germany, operational, 2025
- KAIROS · France, operational
- Levante GPU Extension · Germany, operational, 2025
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
One cited source was readable and does not mention this system; another could not be read because the host returned a bot challenge. The unreadable one may well be fine, so this is weaker evidence than a corroborated row and much stronger than an unsupported one. See how this check works.
| Cited source | Result | Found on the page |
|---|---|---|
| finance.yahoo.com | could not be fetched | - |
| digitaltoday.co.kr | does not name this system | NVIDIA GH200 Grace Hopper Superchip |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Why accelerators exist, what the memory hierarchy costs, and how the CPU and accelerator merged onto one package.
Storage and I/O
Parallel file systems, why checkpointing dominates the write load, and the metadata failure mode nobody expects.