Supercomputers/Systems/Meta Cheyenne (Wyoming)
USA · operational · ai training
Meta Cheyenne (Wyoming)
Also known as Meta Cheyenne AI data center
Operated by Meta Platforms at Meta Cheyenne Data Center .
Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- -
- Rpeak
- -
- Rmax ÷ Rpeak
- -
- Cores
- -
- Power
- -
- Per watt
- - GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Meta designs, builds and operates the 715,000 sq ft Cheyenne, Wyoming data center, optimized for AI workloads | Meta Platforms | - | Reported | datacenters.atmeta.com |
| Accelerator | - Epoch AI estimate: about 68,400 NVIDIA B300 GPUs (modelled, not disclosed by Meta) | NVIDIA | 68,400 estimated | Reported | epoch.ai |
AI datacenter metrics
Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.
| Metric | Value | As of | Basis | Note | Source |
|---|---|---|---|---|---|
| Accelerators | 68,400 accelerators | 2026-10-02 | Third-party estimate | About 68,400 B300. Epoch AI chip estimate (modelled from satellite imagery, cooling equipment and chip availability); not an operator disclosure. | epoch.ai |
| Stated investment | 0.8 USD bn | 2024-07 | Operator stated | Meta: investment of more than 800 million dollars at announcement; floor value, buildings and fit-out not split from compute | datacenters.atmeta.com |
| IT power | 152 MW | 2026-10-02 | Third-party estimate | Epoch AI modelled IT power from satellite imagery and permits; not operator-stated. Epoch projects 207 MW by Q1 2027. | epoch.ai |
How it is powered
| Source | Provider | MW | Status | As of | Basis | Note | Source link |
|---|---|---|---|---|---|---|---|
| Grid | Black Hills Energy | - | operating | 2026-10 | Operator stated | Meta says it worked with Black Hills Energy to plan energy for the Cheyenne data center and pays full costs; no MW stated. | datacenters.atmeta.com |
| Wind and solar | - | 365 | contracted | 2026-10 | Operator stated | Meta says one Wyoming project it supports adds 365 MW of new clean energy to the grid. Used to match its electricity use; not a direct supply to the site. | datacenters.atmeta.com |
| Battery storage | - | 200 | contracted | 2026-10 | Operator stated | The same Wyoming project Meta supports adds 200 MW of battery storage to the grid; a grid-side addition, not on-site storage. | datacenters.atmeta.com |
How AI campuses are powered: capacities are what the operator, utility or filing states, not what has been delivered.
The read
Meta's Cheyenne, Wyoming data center, announced on 2 July 2024 as an investment of more than 800 million dollars across 715,000 square feet, with Black Hills Energy adding new grid resources and a description of the site as optimized for Meta's AI workloads. Meta publishes no capacity or hardware. Epoch AI's AI data centers dataset (CC BY 4.0) estimates about 68,400 B300 chips and 152 MW of IT power, with both initial buildings estimated operational by July 2026, and projects about 207 MW by Q1 2027, from satellite imagery and permit records. Meta has not announced an in-service date, so operational status and these figures are Epoch's modelled estimates in the metrics table only. Hardware rests on Epoch alone, so the tier is reported. Separate from NCAR's Cheyenne supercomputer.
Timeline
- 2024-07-02 Announced source
Site & facility
Meta Cheyenne Data Center
- Location
- Cheyenne, WY, USA
- Utility
- Black Hills Energy
Change history
- 2026-10-04 Added Meta Cheyenne (Wyoming)
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| datacenters.atmeta.com | names system only | - |
| epoch.ai | names system only | - |
Checked 2026-10-09 by pnpm verify. Re-run it and the table changes with the web.