Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- -
- Rpeak
- -
- Rmax ÷ Rpeak
- -
- Cores
- -
- Power
- -
- Per watt
- - GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Core Scientific hosts CoreWeave at Denton: about 260 MW of critical IT load, about 260 MW billing in July 2026 | Core Scientific | - | Reported | investors.corescientific.cominvestors.corescientific.com |
Engineering, funding and access
What Denton (CoreWeave) runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Funded by | Core Scientific funds $104 million of the expansion capex ($1.5 million per MW) and CoreWeave funds the remaining capex | 2025-02-26 | Operator stated | investors.corescientific.com |
| Procurement | 26 February 2025 expansion adds 70 MW and $1.2 billion of contracted revenue, taking Denton to about 260 MW; CoreWeave's contract totals about 590 MW across six Core Scientific sites on 12-year terms with two five-year renewal options | 2025-02-26 | Operator stated | investors.corescientific.com |
AI datacenter metrics
Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.
| Metric | Value | As of | Basis | Note | Source |
|---|---|---|---|---|---|
| Accelerators | 100,000 accelerators | 2026-07-03 | Third-party estimate | Epoch AI chip estimate, latest per chip type (B200); some rows are company disclosures, others modelled. Epoch notes Core Scientific cites over 50,000 GPUs at about 130 MW. | epoch.ai |
| Stated investment | 9.9 USD bn | 2026-09-01 | Third-party estimate | Epoch AI modelled build cost, compute plus construction, 2025 USD, scaled from IT power; not a disclosed spend. | epoch.ai |
| Facility power | 367 MW | 2026-09-01 | Third-party estimate | Epoch AI modelled gross facility power (IT plus cooling and overhead) at this timeline date. | epoch.ai |
| IT power | 260 MW | 2026-07 | Operator stated | Core Scientific Q2 FY26 deck (mid-July 2026): Denton about 260 MW leased to CoreWeave, substantially complete. Feb 2025 release also says about 260 MW critical IT. | investors.corescientific.cominvestors.corescientific.com |
The read
Core Scientific's Denton, Texas campus, the largest of its CoreWeave-contracted sites. A 26 February 2025 expansion added 70 MW, bringing Denton to about 260 MW of critical IT load for CoreWeave and CoreWeave's total contract with Core Scientific to about 590 MW across six sites. Core Scientific's Q2 2026 earnings deck of 28 July 2026 lists Denton at about 260 MW leased and billing, marked substantially complete, so the status is operational. CoreWeave is recorded as operator because it is the named tenant; Core Scientific is landlord. Neither page names the GPU model or count, so no accelerator edge is recorded. Both sources are Core Scientific's own, so the tier is reported. It has never submitted an HPL result.
Timeline
- 2025-02-26 Core Scientific and CoreWeave add 70 MW at Denton for $1.2 billion of extra contracted revenue, taking critical IT load to about 260 MW source
Site & facility
Core Scientific Denton Data Center
- Location
- Denton, TX, USA
Change history
- 2026-10-04 AI datacenter metrics: Denton (CoreWeave)
- 2026-10-02 Added Denton (CoreWeave) (CoreWeave tenant)
Nearby in scale
The machines closest to Denton (CoreWeave) by accelerator count, smaller to larger.
- JD Cloud 100,000-GPU Cluster · China, planned · 100,000 accelerators
- Solstice · USA, planned · 100,000 accelerators
- xAI Colossus · USA, operational · 100,000 accelerators
- STACKIT Lubbenau AI Data Center · Germany, under construction · 100,000 accelerators
- Google Pryor North TPU Campus · USA, operational · 101,400 accelerators
- Microsoft Project Osmium · USA, operational · 103,200 accelerators
Related systems
Same operator
- Carina · USA, operational
- Marble (CoreWeave) · USA, operational
- CoreWeave AI cluster for Inflection AI · USA, operational, 2023
- Muskogee (CoreWeave) · USA, under construction
- CoreWeave Cambridge (Cohere) · Canada, operational, 2025
- CoreWeave Hammond AI Data Center · USA, planned
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| investors.corescientific.com | names system only | - |
| investors.corescientific.com | names system only | - |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.