Supercomputers/Systems/ABCI 3.0

Japan · operational · ai training

ABCI 3.0

Operated by AIST at ABCI Data Center, Kashiwa .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
145.1 PFlop/s
HPL measured
Rpeak
181.5 PFlop/s
Rmax ÷ Rpeak
79.9%
Cores
479,232
Power
3.60 MW
Per watt
40.3 GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

How it compares

Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of ABCI 3.0, and those in Japan. Computed from our tables; a metric is ranked only when at least eight peers report it.

MetricValueAgainst its eraAgainst its country
Rmax145.1 PFlop/s#14 of 202 · top 6%#2 of 131 · top 1%
Energy efficiency40.3 GF/W#54 of 99 · bottom 47%#7 of 74 · top 8%
Rmax ÷ Rpeak79.9 %#72 of 199 · top 36%#54 of 130 · top 41%
Power draw3,596 kW#15 of 104 · top 14%#3 of 74 · top 3%

Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
HPE-built
Hewlett Packard Enterprise - Verified top500.orgnextplatform.com
Accelerator NVIDIA H200 SXM
Accelerators
CUDA (Hopper GH100) · 16,896C · 1.98 GHz · TSMC 4N · 700 W
NVIDIA H200 SXM5 141GB
NVIDIA - Verified top500.orgnextplatform.com
CPU Intel Xeon Platinum 8558
CPUs
x86-64 · 48C · 2.1 GHz · Intel 7
Xeon Platinum 8558 48C 2.1GHz
Intel - Reported top500.org
Interconnect NVIDIA InfiniBand NDR (Quantum-2)
Interconnect
Fat tree or dragonfly+ · 400 Gb/s per port · Under 0.6 microseconds
Infiniband NDR200
NVIDIA - Reported top500.org

Engineering, funding and access

What ABCI 3.0 runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Compute nodes766 nodesHPE Cray XD670 nodes with 8 NVIDIA H200 each, 6128 GPUs in total2025Operator statedabci.aidocs.abci.ai
Total memory1,532 TBABCI states 2 TB DDR5 per node, multiplied here by 766 nodes; excludes GPU HBM2025Operator statedabci.ai
Storage capacity75 PBAll-flash (three DDN ES400NVX2 systems), Lustre plus S3-compatible object storage2025Operator statedabci.ai
Interconnect and topologyInfiniBand NDR200: 8 x 200 Gb/s per compute node, three-tier fat-tree with full bisection bandwidth; HDR 200 Gb/s per node to storage; SINET6 at 400 Gb/s2025Operator statedabci.aiarxiv.org
Cooling designHot-aisle fan coil units stacked on the racks; 5.2 MW cooling capacityRack fan coil design per the Monoist report; capacity per the arXiv paper2025-01Press reportmonoist.itmedia.co.jparxiv.org

Software

ItemDetailAs ofBasisSource
Parallel filesystemLustre: /home 10 PB, /groups 63 PB, plus 1 PB S3-compatible object store; about 75 PB effective2026Operator stateddocs.abci.ai
Job schedulerAltair PBS Professional 2022.1.6Resource types rt_HF (8 GPUs), rt_HG (1 GPU), rt_HC (CPU only)2026Operator stateddocs.abci.aiarxiv.org
Programming and software stackRocky Linux 9.4 on interactive nodes and Red Hat Enterprise Linux 9.4 on compute nodes2026Operator stateddocs.abci.ai
Programming and software stackNVIDIA CUDA Toolkit and HPC SDK, GCC, Intel oneAPI, Intel MPI and HPC-X, SingularityCE containers, Open OnDemand2026Operator stateddocs.abci.aiarxiv.org

Funding

ItemDetailAs ofBasisSource
Funded byMinistry of Economy, Trade and Industry (METI), JapanOECD.AI dashboard attributes funding to METI Economic Security Fund2025-01Press reportoecd.ai
Funding programmeMETI Economic Security Fund2025-01Press reportoecd.ai
Stated cost232 USD mStated as an initial investment of 36 billion yen (about 232 million USD)2025-01Press reportoecd.ai
ProcurementHPE selected as integrator in July 2024, replacing Fujitsu and NEC who built earlier ABCI generations2024-07Press reportnextplatform.com

Access

ItemDetailAs ofBasisSource
How researchers get timeGeneral provision of ABCI 3.0 to researchers, industry and the LLM building support program, via AIST2025-01Press reportmonoist.itmedia.co.jp
Access pageabci.ai2025Operator statedabci.ai

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Accelerators 6,128 accelerators 2025-06 Operator stated 766 compute nodes with 8 NVIDIA H200 each, per AIST documentation. docs.abci.aiunit.aist.go.jp
Facility power 6 MW 2024-11 Operator stated Electrical capacity of the AIST AI data centre after the ABCI 3.0 upgrade (5.2 MW cooling, 144 racks). Facility figure from the ABCI 3.0 paper. arxiv.org
PUE 1.15 2025-06 Operator stated AIST states PUE '< 1.15' as of June 2025 (32 C water cooled by a cooling tower). Value is the stated upper bound. unit.aist.go.jp

The read

AIST's third physical ABCI generation, not an upgrade of the machine already in this dataset: HPE replaced the NEC and Fujitsu integrators that built ABCI 1.0 and 2.0, on Xeon Platinum hosts paired with NVIDIA H200. The original `abci` row (1.0, 2018, Fujitsu-built, Tesla V100) is a genuinely different, still-correctly-recorded machine, not an outdated figure for this one.

Timeline

  • 2024-07 Announced source
  • 2024-07 AIST selected HPE and NVIDIA to build ABCI 3.0, replacing the Fujitsu and NEC integrators of earlier generations source
  • 2024-11 ABCI 3.0 began gradual rollout to users source
  • 2025-01-24 AIST announced the start of general provision of ABCI 3.0 source
  • 2025-06 Listed at #65 on the Green500 (June 2025) source
  • 2025-06 First operational source

Public list appearances

Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.

Site & facility

ABCI Data Center, Kashiwa

Location
Kashiwa, Japan
Cooling
Direct liquid cooling with hot-water loop
PUE
1.1
Commissioned
2018

Where sources disagree

We record conflicts instead of picking a winner quietly. All open questions.

Change history

Nearby in scale

The machines closest to ABCI 3.0 by Rmax, smaller to larger.

Same site

  • ABCI-Q · Japan, operational, 2025
  • ABCI 2.0 · Japan, operational, 2021
  • ABCI · Japan, decommissioned, 2018

Same operator

Same accelerator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
top500.orgnames system and partNVIDIA H200 SXM, Intel Xeon Platinum 8558, NVIDIA InfiniBand NDR (Quantum-2)
nextplatform.comnames system and partNVIDIA H200 SXM, Intel Xeon Platinum 8558, NVIDIA InfiniBand NDR (Quantum-2)