Supercomputers/Systems/Lem
Poland · operational · mixed
Lem
Also known as WCSS Lem
Operated by WCSS at WCSS Data Centre (Wroclaw) .
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 12.80 PFlop/s
- Rpeak
- 20.37 PFlop/s
- Rmax ÷ Rpeak
- 62.8%
- Cores
- 44,992
- Power
- -
- Per watt
- - GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Lem, and those in Poland. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 12.80 PFlop/s | #112 of 234 · top 48% | #3 of 19 · top 11% |
| Rmax ÷ Rpeak | 62.8 % | #185 of 231 · bottom 21% | #15 of 19 · bottom 23% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Dell (TOP500 manufacturer) | Dell Technologies | - | Reported | top500.org |
| Accelerator | NVIDIA H100 SXM5 94GB Accelerators CUDA (Hopper GH100) · 16,896C · 1.98 GHz · TSMC 4N · 700 W NVIDIA H100 94GB SXM5; 304 accelerators on 76 GPU nodes per WCSS | NVIDIA | 304 reported | Reported | top500.orgwcss.pl |
| CPU | Intel Xeon Platinum 8462Y+ CPUs x86-64 · 32C · 2.8 GHz · Intel 7 Intel Xeon Platinum 8462Y+ 32C 2.8GHz | Intel | - | Reported | top500.org |
| Interconnect | NVIDIA InfiniBand NDR (Quantum-2) Interconnect Fat tree or dragonfly+ · 400 Gb/s per port · Under 0.6 microseconds InfiniBand NDR200 (4x NDR 200 Gb/s on GPU nodes) | NVIDIA | - | Verified | top500.orgwcss.pl |
Engineering, funding and access
What Lem runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Interconnect and topology | NVIDIA InfiniBand NDR200 | 2026-06 | Operator stated | top500.org |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Programming and software stack | AlmaLinux 9.3 operating system | 2026-06 | Operator stated | top500.org |
| Programming and software stack | NVIDIA NVCC, cuBLAS and HPC-X for the TOP500 run | 2026-06 | Operator stated | top500.org |
The read
Flagship cluster of the Wroclaw Centre for Networking and Supercomputing (WCSS), launched in 2024 and ranked 80th on the June 2024 TOP500. WCSS describes a CPU partition of 188 nodes (23,808 cores, 279 TB RAM) and a GPU partition of 76 nodes with 304 NVIDIA H100 accelerators linked by NVLink, plus 64 service nodes, InfiniBand NDR200 on the compute nodes, about 21 PFlops total and 2 PB NFS, 2 PB Lustre and 6 PB S3 storage; funding came in part from the EuroHPC PL and CLARIN-PL-BIZ projects. TOP500 lists a Dell system with Intel Xeon Platinum 8462Y+ 32-core 2.8 GHz CPUs, NVIDIA H100 94 GB SXM5 and InfiniBand NDR200 under AlmaLinux 9.3: 44,992 cores, Rmax 12.80 PFlop/s, Rpeak 20.37 PFlop/s. Its TOP500 history is 80th (June 2024), 99th (November 2024), 121st (June 2025), 141st (November 2025) and 162nd (June 2026). WCSS gives the H100 memory as 96 GB where TOP500 says 94 GB.
Timeline
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Change history
- 2026-10-02 Added Lem, WCSS's H100 cluster in Wroclaw
Nearby in scale
The machines closest to Lem by Rmax, smaller to larger.
Related systems
Same site
- Bem 2 · Poland, operational, 2021
- BEM · Poland, operational, 2015
- Supernova · Poland, decommissioned, 2010
Same accelerator
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
One cited source was readable and does not mention this system; another could not be read because the host returned a bot challenge. The unreadable one may well be fine, so this is weaker evidence than a corroborated row and much stronger than an unsupported one. See how this check works.
| Cited source | Result | Found on the page |
|---|---|---|
| top500.org | does not name this system | Intel Xeon Platinum 8462Y+, NVIDIA H100 SXM5 94GB, NVIDIA InfiniBand NDR (Quantum-2) |
| wcss.pl | could not be fetched | - |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.