Tera-1000-1

Also known as CEA Tera-1000 phase 1 Xeon system

Operated by CEA at CEA/DAM .

Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
1.87 PFlop/s
HPL measured
Rpeak
2.59 PFlop/s
Rmax ÷ Rpeak
72.2%
Cores
70,272
Power
1.04 MW
Per watt
1.8 GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Bull bullx DLC 720 (Atos)
Eviden
ATOEPA rolls up to Atos
- Reported top500.orgteratec.eu
CPU Intel Xeon E5-2698 v3
CPUs
x86-64 · 16C · 2.3 GHz · 22 nm · 135 W
Xeon E5-2698v3 16C 2.3GHz
Intel - Reported top500.org
Interconnect Mellanox InfiniBand FDR
Interconnect
Fat tree · 56 Gb/s per 4x port · About 1 microsecond
Infiniband FDR
Mellanox
NVDANASDAQ rolls up to NVIDIA
- Reported top500.org

The read

CEA's first Tera-1000 compute system at its DAM centre near Paris, a Bull/Atos bullx DLC 720 machine of Xeon E5-2698v3 16-core processors on InfiniBand FDR running Bullx Linux. TOP500 lists 70,272 cores, 1.87 PFlop/s Rmax, 2.59 PFlop/s peak and 1,042 kW, ranking it 45th in June 2016 and still listed at 457th in November 2022. Teratec's account says the Atos-installed first phase, completed on 4 December 2015, had two compute systems, this Xeon E5 v3 one and a Sequana X1000 pre-production Xeon Phi one, ahead of the 25 PFlop/s second phase. TOP500 is the only source for the core count and Rmax, so the tier is reported; the status date is the last TOP500 listing.

Timeline

Public list appearances

Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.

Site & facility

CEA/DAM

Location
Bruyeres-le-Chatel, France
Commissioned
2024

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
teratec.eudoes not name this systemIntel Xeon E5-2698 v3
top500.orgnames system and partIntel Xeon E5-2698 v3, Mellanox InfiniBand FDR

Checked 2026-10-09 by pnpm verify. Re-run it and the table changes with the web.

Further reading