Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
4.07 PFlop/s
HPL measured
Rpeak
6.64 PFlop/s
Rmax ÷ Rpeak
61.2%
Cores
79,488
Power
917 kW
Per watt
4.4 GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

How it compares

Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Joliot-Curie SKL, and those in France. Computed from our tables; a metric is ranked only when at least eight peers report it.

MetricValueAgainst its eraAgainst its country
Rmax4.07 PFlop/s#47 of 234 · top 20%#15 of 52 · top 27%
Energy efficiency4.4 GF/W#39 of 158 · top 24%#16 of 42 · top 37%
Rmax ÷ Rpeak61.2 %#183 of 229 · bottom 21%#45 of 51 · bottom 13%
Power draw917 kW#58 of 161 · top 36%#18 of 42 · top 41%

Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Bull Sequana X1000
Eviden
ATOEPA rolls up to Atos
- Reported top500.org
CPU -
Xeon Platinum 8168 24C 2.7GHz (Skylake), 1,656 dual-socket nodes, 79,488 cores
Intel - Verified top500.orgwww-hpc.cea.fr
Interconnect Mellanox InfiniBand EDR
Interconnect
Fat tree · 100 Gb/s per 4x port · About 0.9 microseconds
InfiniBand EDR
Mellanox
NVDANASDAQ rolls up to NVIDIA
- Verified top500.orgwww-hpc.cea.fr
Operating system -
bullx SCS
Eviden
ATOEPA rolls up to Atos
- Reported top500.org

Engineering, funding and access

What Joliot-Curie SKL runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Compute nodes1,656 nodesDual-socket nodes with two 24-core Xeon Platinum 8168 at 2.7 GHz (79,488 cores) and 192 GB DDR4 each2018Operator statedwww-hpc.cea.frprace-ri.eu
Total memory317.95 TBDerived: 1,656 nodes x 192 GB DDR4 = 317,952 GB2018Operator statedwww-hpc.cea.frprace-ri.eu
Storage capacity5 PBScratch storage shared by all Joliot-Curie partitions at 300 GB/s; the 2017 contract required at least 5 PiB2017-06Operator statedwww-hpc.cea.frgeneration-nt.com
Interconnect and topologyInfiniBand EDR (Mellanox), 100 Gb/sCEA and TOP500 both give InfiniBand EDR; PRACE's system page gives 100 Gb/s2018Operator statedwww-hpc.cea.frtop500.org
Cooling designBull patented direct liquid cooling with hot waterThe Atos release claims up to 40 percent less energy than air cooling2017-06Vendor statedgeneration-nt.com

Software

ItemDetailAs ofBasisSource
Parallel filesystemMulti-level Lustre storage shared by all Joliot-Curie partitions: at least 5 PiB at 300 GB/s in the 2017 contract, rising to 500 GB/sPRACE describes a 500 GB/s multi-level Lustre file system2017-06Vendor statedgeneration-nt.comprace-ri.eu
Programming and software stackHPL run used Intel icc 17, MKL and Intel MPI 2018.1TOP500 list entry2018-06Operator statedtop500.org
Programming and software stackBull Supercomputer Suite (SCS) 5 on Red Hat Linux 7.xTOP500 lists the operating system as bullx SCS2017-06Vendor statedgeneration-nt.comtop500.org

Funding

ItemDetailAs ofBasisSource
Funded byGENCI (Grand Equipement National de Calcul Intensif)CEA says an integrated GENCI-CEA team ran the purchase; the Atos release names GENCI as the client2017-06Operator statedwww-hpc.cea.frgeneration-nt.com
ProcurementContract between GENCI and Atos (Bull) formalised on 14 June 2017 for a roughly 9 PFlop/s Sequana X1000 (6.86 PFlop/s Skylake plus 2.08 PFlop/s KNL) to succeed Curie, delivery due at the end of 20172017-06-15Vendor statedgeneration-nt.comwww-hpc.cea.fr

Access

ItemDetailAs ofBasisSource
How researchers get timeCalls for proposals run by GENCI (DARI portal) for French academic and industrial researchers, and PRACE calls for European researchers2019-11Operator statedwww-hpc.cea.frgeneration-nt.com

The read

Skylake partition of the GENCI-owned Joliot-Curie machine, an Atos Bull Sequana X1000 at CEA's TGCC, 34th on the June 2018 TOP500. TOP500 and CEA's own page agree on the hardware: 1,656 dual-socket Xeon Platinum 8168 24-core 2.7 GHz nodes (79,488 cores) on InfiniBand EDR; TOP500 gives 4.07 PFlop/s Rmax and 6.64 PFlop/s Rpeak while CEA quotes 6.86 PFlop/s peak. CEA says the machine was deployed at the end of 2017 and that this partition is now stopped, so it is recorded as decommissioned with no stop date, even though TOP500 still lists the entry in June 2026. The later AMD Rome partition is a separate row (joliot-curie-rome).

Timeline

  • 2017 First operational source
  • 2017-06-14 GENCI and Atos formalised the contract for the roughly 9 PFlop/s Bull Sequana system that became the first phase of Joliot-Curie source
  • 2018-06 Listed at #34 on the TOP500 (June 2018) source

Public list appearances

Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.

Site & facility

Very Large Computing Centre (TGCC)

Location
Bruyeres-le-Chatel, France

Change history

Nearby in scale

The machines closest to Joliot-Curie SKL by Rmax, smaller to larger.

  • Abel · USA, operational · 4.04 PFlop/s
  • Warhawk · USA, operational · 4.03 PFlop/s
  • Raider · USA, operational · 4.02 PFlop/s
  • Raphael · USA, operational · 4.09 PFlop/s
  • Alpha (Flatiron) · USA, operational · 4.1 PFlop/s
  • Cirrus · United Kingdom, operational · 4.12 PFlop/s

Same site

Same operator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
www-hpc.cea.frnames system and partMellanox InfiniBand EDR
top500.orgnames system and partMellanox InfiniBand EDR