COMPUTE ATLAS Supercomputer supply-chain graph
1581 systems 558 sites Sourced data

Supercomputers/Systems/Stargate Shackelford County (Frontier)

USA · under construction · ai training

Stargate Shackelford County (Frontier)

Also known as Vantage Frontier

Operated by Oracle at Vantage Frontier Campus (Shackelford County) .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Vantage Data Centers develops the 1.4 GW, ten-building Frontier campus
Vantage Data Centers
- Reported vantage-dc.comconstructionowners.com
Cooling -
Air-cooled and liquid-to-liquid cooling on a closed-loop chilled-water system for racks above 250 kW
Vantage Data Centers
- Reported vantage-dc.com

Engineering, funding and access

What Stargate Shackelford County (Frontier) runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Cooling designLiquid cooling for next-generation GPU loads plus a closed-loop chiller system needing minimal water; racks of 250 kW and aboveBoth describe air and liquid cooling support.2025-08-19Operator statedvantage-dc.comconstructionowners.com

Funding

ItemDetailAs ofBasisSource
Funded byVantage Data Centers, backed by DigitalBridge and Silver Lake; no project-level financing disclosed2025-12Press reportconstructionowners.com
Stated cost25,000 USD mVantage says investment of over $25 billion for the 10-building campus; its largest to date.2025-08-19Operator statedvantage-dc.comconstructionowners.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Stated investment 25 USD bn 2025-08 Operator stated Vantage: $25 bn Frontier campus, ten data centers on 1,200 acres; Vantage figure, not OpenAI or Oracle vantage-dc.com
Facility power 1,400 MW 2025-08 Design target Vantage: 1.4 GW Frontier campus, ten buildings; later tied to Oracle/OpenAI Stargate; planned capacity, first building 2H 2026 vantage-dc.comconstructionowners.com
Rack power 250 kW 2025-08 Design target Vantage: campus can accommodate ultra high-density racks of 250 kW or more with liquid cooling; capability, not a measured load vantage-dc.com

How it is powered

SourceProviderMWStatusAs ofBasisNoteSource link
On-site gas VoltaGrid 2,580 planned 2026-04 Third-party estimate Off-grid gas microgrid; Cleanview tallies INNIO Jenbacher engines at 2.58 GW gross. Epoch confirms on-site gas. Oracle-VoltaGrid 2.3 GW deal names only Texas. cleanview.coepoch.ai

How AI campuses are powered: capacities are what the operator, utility or filing states, not what has been delivered.

The read

Vantage Data Centers' 1.4 GW Frontier campus in Shackelford County, Texas, ten single-story buildings totalling 3.7 million square feet on 1,200 acres, with racks above 250 kW and a mix of air and liquid-to-liquid cooling on a closed-loop chilled-water system. Vantage's own announcement (19 August 2025) gives the capacity, buildings and a first-building delivery in the second half of 2026 but does not mention Oracle or OpenAI; a December 2025 groundbreaking report ties the campus to the Oracle and OpenAI Stargate expansion, and Epoch AI's Stargate site tracker separately lists Shackelford as a Stargate site with Vantage as developer, while giving a larger projected capacity of 2.0 GW than Vantage's own 1.4 GW. Oracle is recorded as operator on the strength of that Stargate association and to match the Stargate Abilene row. No accelerator type or count has been published, and power is blank because 1.4 GW is a campus design capacity.

Timeline

  • 2025-08-19 Announced source
  • 2025-12 Vantage holds a groundbreaking for the Frontier campus, described as part of Oracle and OpenAI's Stargate expansion source

Site & facility

Vantage Frontier Campus (Shackelford County)

Location
Shackelford County, TX, USA
Cooling
Air and liquid-to-liquid, closed-loop chilled water

Change history

Same operator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
vantage-dc.comnames system only-
constructionowners.comnames system only-

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.

Further reading