Supercomputers/Systems/Stargate Michigan (Saline Township)

USA · under construction · ai training

Stargate Michigan (Saline Township)

Also known as The Barn

Operated by Oracle at Related Digital Saline Township Campus .

Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Related Digital develops three 550,000 sq ft buildings, more than 1 GW planned, purpose-built for Oracle
Related Digital
- Reported related.comrelated.com
Cooling -
Closed-loop, air-cooled system limiting water use to that of a standard office building
Related Digital
- Reported related.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Stated investment 16 USD bn 2026-04 Operator stated Related Digital and Blackstone: financing secured for the $16 bn Saline Township campus built for Oracle; whole-campus project cost, supersedes the $7 bn announcement floor related.com
Stated investment 7 USD bn 2025-10 Operator stated Project value above $7 bn announced by Gov. Whitmer with OpenAI, Oracle and Related Digital; press repeats the announcement, not independent confirmation planetdetroit.orgbridgemi.com
Facility power 1,000 MW 2026-04 Design target Related Digital: three buildings with "more than a gigawatt of capacity" at Saline Township, built for Oracle; value is the floor related.com

How it is powered

SourceProviderMWStatusAs ofBasisNoteSource link
Grid DTE Energy - planned 2026-06 Operator stated Related Digital: DTE supplies all power from existing resources, paid by the project. Epoch also lists DTE as the 100% supplier. MW not stated. related.comepoch.ai
Battery storage DTE Energy - planned 2026-06 Operator stated New battery storage financed by the project; Related Digital estimates 300 million USD of grid savings for DTE customers. MW not stated. related.comepoch.ai

How AI campuses are powered: capacities are what the operator, utility or filing states, not what has been delivered.

The read

The Saline Township, Michigan campus that Related Digital is building for Oracle as part of the Oracle and OpenAI Stargate expansion: three single-story, 550,000 square foot buildings with more than one gigawatt of planned capacity per Related Digital's April 2026 financing release (16 billion dollars, equity from Related Digital and Blackstone-affiliated funds with PIMCO-anchored debt), a closed-loop air-cooled design, and all power supplied by DTE Energy plus a project-financed battery system. Related Digital's 1 June 2026 release with Oracle, OpenAI and Blackstone reports all buildings under construction and the first nearly complete. Epoch AI's Stargate tracker independently lists Saline as a Stargate site with Related Digital as developer and a 1.4 GW projection, which is a higher and analyst-side figure than the developer's own 'more than one gigawatt'. No accelerator type or count has been published, and power is blank because the capacity is a planned design figure.

Timeline

No dated events recorded.

Site & facility

Related Digital Saline Township Campus

Location
Saline Township, MI, USA
Utility
DTE Energy
Cooling
Closed-loop air-cooled

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
epoch.ainames system only-
related.comblocked our fetch-

Checked 2026-10-09 by pnpm verify. Re-run it and the table changes with the web.