Vantage Data Centers
Hyperscale data center developer building the 1.4 GW Frontier campus in Shackelford County, Texas, reported as part of the Oracle and OpenAI Stargate expansion.
Systems this company appears in
- Systems
- 2
- Aggregate Rmax
- 0.0 GFlop/s
- Aggregate power
- 0 kW
- First appearance
- 2025-08-19
- Most recent
- 2025-10-22
- Concentration
- -
systems it appears in
where disclosed
largest is Stargate Shackelford County (Frontier)
Aggregate Rmax is the sum of the systems this company supplies any part of. It is not revenue and not attributable share: an integrator and a memory vendor in the same machine both count its full FLOPS here. Attribution weighted by role is Phase 4.
Role breakdown
| Role | Systems | Rmax in those systems |
|---|---|---|
| Integrator | 2 | 0.0 GFlop/s |
| Cooling | 2 | 0.0 GFlop/s |
Appearances
| System | Supplied as | Shipped under | Rmax | Rank |
|---|---|---|---|---|
| Stargate Shackelford County (Frontier) USA · | Integrator, Cooling | Vantage Data Centers | - | unranked |
| Stargate Port Washington (Lighthouse) USA · | Integrator, Cooling | Vantage Data Centers | - | unranked |
Sites operated
| Site | Location | Cooling | Commissioned |
|---|---|---|---|
| Vantage Frontier Campus (Shackelford County) | Shackelford County, TX, USA | Air and liquid-to-liquid, closed-loop chilled water | - |
| Vantage Lighthouse Campus (Port Washington) | Port Washington, WI, USA | Closed-loop liquid cooling | - |