Supercomputers/Systems/LUMI-AI

Finland · planned · mixed

LUMI-AI

Quantum: linked to LUMI-IQ (150 superconducting qubits)

Also known as LUMI AI Factory supercomputer

Operated by CSC at LUMI Data Center, Kajaani .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Bull BullSequana XH3500 supercomputer, integrator under the EuroHPC contract
Bull
ATOEPA rolls up to Atos
- Reported eurohpc-ju.europa.euresultsense.com
Accelerator AMD Instinct MI430X
Accelerators
AMD Instinct MI430X GPUs
AMD - Reported eurohpc-ju.europa.euresultsense.com
CPU -
6th Gen AMD EPYC 256-core processors
AMD - Reported eurohpc-ju.europa.eu

Engineering, funding and access

What LUMI-AI runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Funding

ItemDetailAs ofBasisSource
Funded byEuroHPC Joint Undertaking, 50 percent of the 387.8 million euro total costBudget covers acquisition, delivery, installation and maintenance.2026-08-31Operator statedeurohpc-ju.europa.eu
Funded byLUMI AI Factory consortium led by Finland with Czechia, Denmark, Estonia, Norway and Poland, the other 50 percent2026-08-31Operator statedeurohpc-ju.europa.eu
Funding programmeDigital Europe Programme for the EuroHPC JU share2026-08-31Operator statedeurohpc-ju.europa.eu
ProcurementBull selected after a EuroHPC JU call for tender launched in May 2025; Finland had been chosen as hosting site in December 2024, and CSC hosts the system in Kajaani2026-08-31Operator statedeurohpc-ju.europa.eu

Access

ItemDetailAs ofBasisSource
How researchers get timePrimarily for start-ups and SMEs doing research and innovation, and open to the wider research community; the EuroHPC JU and the consortium allocate time jointly in line with their investments2026-08-31Operator statedeurohpc-ju.europa.eu

The read

AI-optimised EuroHPC supercomputer for the LUMI AI Factory consortium (Finland, Czechia, Denmark, Estonia, Norway, Poland), contract signed with Bull on 31 August 2026 at 387.8 million euros split between EuroHPC JU and the consortium. It uses AMD Instinct MI430X GPUs and 6th generation 256-core AMD EPYC CPUs, expects a tenfold increase in AI capacity over LUMI, and will sit at CSC's data centre in Kajaani. Resultsense and TechTimes put operation in the second half of 2027 (EuroHPC says 2027); TechTimes also names IBM storage and Nokia networking and an MI430X FP64 rating of 288 teraFLOPS per GPU. GPU count, FLOPS and power are not published.

Timeline

  • 2024-12 Finland was selected as the hosting site for the LUMI AI Factory supercomputer source
  • 2025-05 The EuroHPC JU launched the call for tender for the system, which Bull won source
  • 2026-08-31 Announced source

Site & facility

LUMI Data Center, Kajaani

Location
Kajaani, Finland
Cooling
Direct liquid cooling with waste-heat recovery
PUE
1.03
Commissioned
2022

Change history

Same site

  • Roihu · Finland, operational, 2026
  • LUMI · Finland, upgraded, 2022

Same operator

  • Mahti · Finland, decommissioned, 2020
  • Puhti · Finland, decommissioned, 2019
  • Sisu · Finland, decommissioned, 2012
  • Taito (CSC) · Finland, operational, 2012
  • Louhi · Finland, operational, 2007

Same accelerator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
eurohpc-ju.europa.eunames system and partAMD Instinct MI430X
resultsense.comnames system only-

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.