COMPUTE ATLAS Supercomputer supply-chain graph
1581 systems 558 sites Sourced data

Supercomputers/Systems/Tryton Plus

Poland · operational · hpc

Tryton Plus

Also known as TASK Tryton Plus

Operated by CI TASK at CI TASK Data Centre (Gdansk) .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
1.73 PFlop/s
HPL measured
Rpeak
2.82 PFlop/s
Rmax ÷ Rpeak
61.3%
Cores
30,432
Power
307 kW
Per watt
5.6 GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

How it compares

Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Tryton Plus, and those in Poland. Computed from our tables; a metric is ranked only when at least eight peers report it.

MetricValueAgainst its eraAgainst its country
Rmax1.73 PFlop/s#201 of 210 · bottom 5%#9 of 19 · top 44%
Energy efficiency5.6 GF/W#73 of 109 · bottom 34%#3 of 11 · top 20%
Rmax ÷ Rpeak61.3 %#169 of 207 · bottom 19%#16 of 19 · bottom 18%
Power draw307 kW#86 of 112 · bottom 24%#10 of 11 · bottom 11%

Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Huawei CH121L V5 liquid-cooled nodes
Huawei
- Verified top500.orgdocs.task.gda.pl
CPU -
Xeon Platinum 8268 24C 2.9GHz, 1,268 processors
Intel 1,268
reported
Verified top500.orgdocs.task.gda.pl
Interconnect Mellanox InfiniBand EDR
Interconnect
Fat tree · 100 Gb/s per 4x port · About 0.9 microseconds
InfiniBand EDR 100 Gbps fat tree
NVIDIA - Verified top500.orgdocs.task.gda.pl

Engineering, funding and access

What Tryton Plus runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Compute nodes634 nodesCPU servers (1,268 processors, 30,432 cores); a 16-node GPU partition is listed separately. Both pages are CI TASK's.2026Operator stateddocs.task.gda.pltask.gda.pl
Total memory166 TBCPU partition, with 192 or 384 GB per server2026Operator stateddocs.task.gda.pltask.gda.pl
Cooling designDirect liquid cooling of the Huawei CH121L V5 nodes through CDU heat exchangers in 3 of the 18 cabinets2026Operator stateddocs.task.gda.pl

Software

ItemDetailAs ofBasisSource
Programming and software stackCentOS with precompiled Intel binaries, Intel MKL and Intel MPITOP500 list entry (HPL submission)2021-06Operator statedtop500.org

Funding

ItemDetailAs ofBasisSource
Funding programmePRACE-LAB project (1 January 2019 to 31 December 2023), under which it was bought in mid-20212021Operator stateddocs.task.gda.pltask.gda.pl

Access

ItemDetailAs ofBasisSource
How researchers get timeFree for scientific research by people affiliated with scientific institutions: users create an SSO account with an institutional email, apply for or join a computing grant, log in via kdm.task.gda.pl and file yearly reports2026Operator statedtask.gda.pl
Access pagetask.gda.pl/en/resources/supercomputer/access-to-ci-task-computing-resourcesCI TASK access page with the user and computing grant application forms2026Operator statedtask.gda.pl

The read

Liquid-cooled Huawei CH121L V5 cluster at CI TASK, Gdansk University of Technology, bought in mid-2021 through the PRACE-LAB project. TOP500 lists 30,432 cores of Xeon Platinum 8268 24C 2.9GHz on InfiniBand EDR, 1.73 PFlop/s Rmax, 2.82 PFlop/s Rpeak and 307 kW running CentOS; it ranked 360th in June 2021 (entry recorded here) and 462nd in June 2022. TASK documentation lists 634 servers with 1,268 processors and 166 TB of RAM on a fat-tree EDR fabric, plus a 16-node GPU partition of A100 80GB cards, quoting 3.8 PFLOPS overall.

Timeline

  • 2021 First operational source
  • 2021-06 Listed at #360 on the TOP500 (June 2021) source

Public list appearances

Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.

Site & facility

CI TASK Data Centre (Gdansk)

Location
Gdansk, Poland

Change history

Nearby in scale

The machines closest to Tryton Plus by Rmax, smaller to larger.

  • Puhti · Finland, decommissioned · 1.71 PFlop/s
  • Peta4 · United Kingdom, upgraded · 1.7 PFlop/s
  • AFI-NITY · Japan, operational · 1.69 PFlop/s
  • Quriosity (2017) · Germany, decommissioned · 1.75 PFlop/s
  • CARA · Germany, operational · 1.75 PFlop/s
  • Jaguar · USA, upgraded · 1.76 PFlop/s

Same site

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
docs.task.gda.plnames system and partMellanox InfiniBand EDR
top500.orgnames system and partMellanox InfiniBand EDR

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.