Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 1.01 PFlop/s
- Rpeak
- 1.41 PFlop/s
- Rmax ÷ Rpeak
- 71.5%
- Cores
- 38,400
- Power
- 864 kW
- Per watt
- 1.2 GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Tryton, and those in Poland. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 1.01 PFlop/s | #96 of 230 · top 41% | #12 of 19 · bottom 40% |
| Energy efficiency | 1.2 GF/W | #136 of 180 · bottom 26% | #11 of 11 · bottom 1% |
| Rmax ÷ Rpeak | 71.5 % | #141 of 226 · bottom 39% | #8 of 19 · top 39% |
| Power draw | 864 kW | #57 of 182 · top 31% | #1 of 11 · highest |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| CPU | - Intel Xeon E5 v3 12-core 2.3 GHz (E5-2670v3) | Intel | - | Verified | top500.orgdocs.task.gda.pl |
| Interconnect | Mellanox InfiniBand FDR Interconnect Fat tree · 56 Gb/s per 4x port · About 1 microsecond InfiniBand FDR 56 Gb/s fat tree, Mellanox switches | Mellanox NVDANASDAQ
rolls up to NVIDIA | - | Reported | docs.task.gda.pltop500.org |
Engineering, funding and access
What Tryton runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 1,607 nodesFinal configuration: 3,214 processors, 38,568 cores and 64 accelerators (NVIDIA, Intel Xeon Phi and AMD FirePro) in 44 cabinets | 2023 | Operator stated | docs.task.gda.pl |
| Total memory | 218 TB128 or 256 GB of DDR4 per server | 2023 | Operator stated | docs.task.gda.pl |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Parallel filesystem | Lustre workspace and NFS home directories on the Roro 2 storage cluster (integrated by WASKO, installed 25 February 2014, with Hitachi HUS VM arrays), expanded in 2015 for PL-Grid | 2026 | Operator stated | task.gda.pl |
| Programming and software stack | Intel MKL and Intel MPITOP500 list entry (HPL submission) | 2016-06 | Operator stated | top500.org |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Funded by | European Union funds through the Innovative Economy Operational Programme (POIG), measure 2.3 | 2014 | Operator stated | task.gda.pl |
| Funding programme | CD NIWA project (1 November 2013 to 31 December 2015), funded under POIG measure 2.3 | 2014 | Operator stated | task.gda.pl |
Access
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| How researchers get time | Logically split into Tryton/KDM for users of CI TASK's KDM computing grants, Tryton/Plgrid for PL-Grid infrastructure users and Tryton/Cloud for cloud environments | 2023 | Operator stated | docs.task.gda.pl |
The read
Gdansk University of Technology's Tryton cluster, launched in March 2015 as the first petascale system in the Tricity area. TOP500 lists 38,400 cores of Xeon E5-2670v3 12-core processors on InfiniBand, 1.01 PFlop/s Rmax, 1.41 PFlop/s peak and 864 kW, ranking it 93rd in June 2016 and 421st in November 2018. TASK's documentation, which still describes it as in use, counts 1,607 servers, 3,214 processors, 38,568 cores, 64 accelerators and 218 TB of memory on InfiniBand FDR with Mellanox switches and quotes about 1.8 PFlop/s for the expanded cluster, so the TOP500 figures are used for performance. Science in Poland put the price at 30 million zlotys for the machine and 40 million for the whole project. TOP500 is the only source for Rmax. CI TASK's documentation (https://docs.task.gda.pl/kdm/zasoby-sprzetowe/tryton) says Tryton was withdrawn from use in 2023.
Timeline
- 2015-03 First operational source
- 2016-06 Listed at #93 on the TOP500 (June 2016) source
- 2016-06 TOP500 entry grew from 17,280 cores and 0.53 PFlop/s on the 2015 lists to 38,400 cores and 1.01 PFlop/s source
- 2023 Withdrawn from use in 2023, according to CI TASK documentation, which now treats the Tryton page as archival source
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Change history
- 2026-11-08 Tryton marked decommissioned
- 2026-10-02 Added Tryton, CI TASK
Nearby in scale
The machines closest to Tryton by Rmax, smaller to larger.
- CRESCO6 · Italy, operational · 1.01 PFlop/s
- ASPIRE 1 · Singapore, decommissioned · 1.01 PFlop/s
- Zenith (Dell EMC) · USA, operational · 1.01 PFlop/s
- PSNC Eagle · Poland, operational · 1.01 PFlop/s
- MareNostrum P9 CTE · Spain, operational · 1.02 PFlop/s
- QUARTETTO · Japan, operational · 1.02 PFlop/s
Related systems
Same site
- Galera Plus · Poland, operational, 2011
- Tryton Plus · Poland, operational, 2021
- Galera · Poland, decommissioned, 2008
- Kraken-Fregata · Poland, operational, 2024
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| docs.task.gda.pl | names system and part | Mellanox InfiniBand FDR |
| top500.org | names system and part | Mellanox InfiniBand FDR |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.