Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 558.80 TFlop/s
- Rpeak
- 730.66 TFlop/s
- Rmax ÷ Rpeak
- 76.5%
- Cores
- 11,424
- Power
- 319.87 kW
- Per watt
- 1.7 GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of ILGTI Cray XC30, and those in India. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 558.80 TFlop/s | #146 of 230 · bottom 38% | #13 of 16 · bottom 21% |
| Energy efficiency | 1.7 GF/W | #106 of 180 · bottom 42% | #6 of 9 · bottom 39% |
| Rmax ÷ Rpeak | 76.5 % | #107 of 226 · top 47% | #9 of 16 · bottom 48% |
| Power draw | 320 kW | #125 of 182 · bottom 32% | #7 of 10 · bottom 34% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Cray XC30 | Cray HPENYSE
rolls up to Hewlett Packard Enterprise | - | Reported | top500.org |
| Accelerator | NVIDIA Tesla K20X Accelerators CUDA (Kepler GK110) · 2,688C · 0.732 GHz · 28 nm · 235 W NVIDIA K20x | NVIDIA | - | Reported | top500.org |
| CPU | - Intel Xeon E5-2680v2 10C 2.8GHz | Intel | - | Reported | top500.org |
| Interconnect | Cray Aries Interconnect Dragonfly · About 10 GB/s per direction · Around 1 microsecond Aries interconnect | Cray HPENYSE
rolls up to Hewlett Packard Enterprise | - | Reported | top500.org |
| Operating system | Cray Linux Environment Operating systems Linux, Cray-customised · Proprietary layer over open-source Linux Cray Linux Environment | Cray HPENYSE
rolls up to Hewlett Packard Enterprise | - | Reported | top500.org |
Engineering, funding and access
What ILGTI Cray XC30 runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 476 nodesEach node has a 10-core Xeon E5-2680 v2 at 2.8 GHz and one 2,688-core NVIDIA Kepler GPU, per the ILGTI page | 2015 | Operator stated | theory.tifr.res.in |
| Interconnect and topology | Cray Aries | 2015 | Operator stated | theory.tifr.res.in |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Procurement | Cray contract announced 16 July 2014 for India's first XC30, with Xeon E5-2600 v2 CPUs and NVIDIA Tesla K20X GPUs; financial terms not disclosedBoth pages carry Cray's release | 2014-07-16 | Vendor stated | in.marketscreener.comscientific-computing.com |
Access
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| How researchers get time | Used by the Indian Lattice Gauge Theory Initiative, a loose national collaboration whose membership is open to lattice gauge theorists with a regular faculty position anywhere in IndiaILGTI members share machines and work; gauge configurations are available on request | 2015 | Operator stated | theory.tifr.res.in |
The read
Cray XC30 installed in 2015 for the Indian Lattice Gauge Theory Initiative at the Tata Institute of Fundamental Research, the first XC30 delivered to India. TOP500 lists Xeon E5-2680v2 10C 2.8GHz with NVIDIA K20x accelerators on Aries, 11,424 cores, Rmax 558.8 TFlop/s, Rpeak 730.66 TFlop/s and 319.87 kW; it entered at rank 114 in June 2015 and last appeared at rank 488 in November 2017 (the status date used here). IIT Guwahati's HPC page independently lists 730.7 TFlop/s peak and 476 Ivy Bridge nodes.
Timeline
- 2014-07-16 Cray announced a contract to supply TIFR with India's first Cray XC30, rated above 730 TFlop/s peak, for the ILGTI consortium's new Hyderabad facility source
- 2015 First operational source
- 2015-03 The XC30 was installed in a purpose-built data centre on TIFR's old campus in Hyderabad source
- 2015-06 Listed at #114 on the TOP500 (June 2015) source
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Change history
- 2026-10-02 Added the TIFR ILGTI Cray XC30, 114th on the June 2015 TOP500
Nearby in scale
The machines closest to ILGTI Cray XC30 by Rmax, smaller to larger.
- SuperMIC · USA, decommissioned · 0.56 PFlop/s
- BrENIAC · Belgium, decommissioned · 0.55 PFlop/s
- KEK SAKURA · Japan, decommissioned · 0.54 PFlop/s
- Tianhe-1 · China, upgraded · 0.56 PFlop/s
- Sator · France, operational · 0.58 PFlop/s
- CRIEPI SGI ICE X · Japan, operational · 0.58 PFlop/s
Related systems
Same operator
- PARAM Rudra (GMRT) · India, operational, 2024
Same accelerator
- Mesabi · USA, operational, 2015
- HPC2 · Italy, operational, 2014
- QB-2 · USA, operational, 2014
- Blue Waters · USA, decommissioned, 2013
- Fionn · Ireland, decommissioned, 2013
- Hydra (MPCDF) · Germany, decommissioned, 2013
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| top500.org | names system and part | Cray Aries, Cray Linux Environment |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.