COMPUTE ATLAS Supercomputer supply-chain graph
1581 systems 558 sites Sourced data

Supercomputers/Systems/CoreWeave Kenilworth (NEST)

USA · under construction · ai training

CoreWeave Kenilworth (NEST)

Also known as CoreWeave NEST Campus; Northeast Science and Technology Center AI data center

Operated by CoreWeave at NEST Campus (Kenilworth NJ) .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
CoreWeave develops the 250 MW AI data center at the former Merck NEST campus in Kenilworth
CoreWeave
- Reported re-nj.com

Engineering, funding and access

What CoreWeave Kenilworth (NEST) runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Funding

ItemDetailAs ofBasisSource
Funded byNew Jersey Economic Development Authority: 250 million dollar tax credit issued at up to 50 million dollars a year over five years, the first award under the programFunded from 500 million dollars of uncommitted Aspire and Emerge funds2025-11-25Press reportre-nj.com
Stated cost1,760 USD mReal Estate NJ says nearly 1.8 billion dollars; the EDA describes roughly 1.76 billion dollars2025-11-25Press reportre-nj.com
ProcurementCoreWeave leased the 11 NEST building in October 2024, bought it with 27 adjacent acres for 322 million dollars in August 2025 and began construction in mid-September 2025; operation expected early 2027Site partners named are Onyx Equities, Machine Investment Group and Pivot Real Estate Partners2025-11-25Press reportre-nj.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Stated investment 1.8 USD bn 2026-10 Regulatory filing Project cost of about 1.8 billion dollars (about 1.76 billion) as reported for the NJEDA tax credit approval; the 322 million dollar property purchase is separate. re-nj.com
Facility power 250 MW 2026-10 Operator stated Described as a 250 MW AI data center in coverage of the NJEDA award; IT versus facility scope is not stated. re-nj.comrealclear.ai

The read

CoreWeave's 250 MW AI data center at the former Merck research campus in Kenilworth, New Jersey (now the Northeast Science and Technology Center, NEST). CoreWeave bought the property and 27 adjacent acres in August 2025 for 322 million dollars, began construction in September 2025 and was awarded a 250 million dollar tax credit over five years, the first award under New Jersey's Next New Jersey Program - AI, in November 2025. The project is about 392,600 square feet (284,500 square feet retrofit of building 11 NEST plus 108,100 square feet of new construction), has a stated cost of about 1.8 billion dollars and targets operation in early 2027. Neither page names a GPU model or count, so no accelerator edge is recorded. Both sources are trade or analysis coverage of the NJEDA award rather than a CoreWeave page, so the tier is reported. It has never submitted an HPL result.

Timeline

  • 2025-08 Announced source
  • 2025-09 Construction began on the retrofit and new build at the Kenilworth NEST campus source
  • 2025-11 New Jersey EDA awarded a 250 million dollar tax credit, the first award under its AI data center program source

Site & facility

NEST Campus (Kenilworth NJ)

Location
Kenilworth, NJ, USA

Change history

Same operator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
re-nj.comnames system only-
realclear.ainames system only-