USA · decommissioned · hpc

Yellowstone

Operated by NCAR at NCAR-Wyoming Supercomputing Center .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
1.26 PFlop/s
HPL measured
Rpeak
1.50 PFlop/s
Rmax ÷ Rpeak
84.0%
Cores
-
Power
1.44 MW
Per watt
0.9 GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

How it compares

Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Yellowstone, and those in USA. Computed from our tables; a metric is ranked only when at least eight peers report it.

MetricValueAgainst its eraAgainst its country
Rmax1.26 PFlop/s#25 of 193 · top 12%#167 of 332 · top 50%
Energy efficiency0.9 GF/W#84 of 149 · bottom 45%#105 of 162 · bottom 36%
Rmax ÷ Rpeak84.0 %#71 of 192 · top 37%#61 of 331 · top 18%
Power draw1,437 kW#25 of 151 · top 16%#43 of 171 · top 25%

Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
IBM iDataPlex dx360 M4
IBM - Verified cisl.ucar.edutop500.org
Interconnect Mellanox InfiniBand FDR
Interconnect
Fat tree · 56 Gb/s per 4x port · About 1 microsecond
Mellanox FDR InfiniBand, single-plane full fat tree
Mellanox
NVDANASDAQ rolls up to NVIDIA
- Verified cisl.ucar.edutop500.org

Engineering, funding and access

What Yellowstone runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Compute nodes4,536 nodesIBM dx360 M4 nodes with dual Xeon E5-2650, 72 per frame in 63 frames.2017-12Operator statedcisl.ucar.edu
Total memory145.15 TB32 GB DDR3-1600 per node.2017-12Operator statedcisl.ucar.edu
Storage capacity16 PBGLADE disk storage.2017-12Operator statedcisl.ucar.edu
Interconnect and topologyMellanox FDR InfiniBand, single-plane full fat tree2017-12Operator statedcisl.ucar.edu

Software

ItemDetailAs ofBasisSource
Parallel filesystemIBM GPFS-based GLADE (Globally Accessible Data Environment), 16 PBSupported by the Caldera, Geyser and Pronghorn analysis and visualization clusters.2017-12Operator statedcisl.ucar.edu

Results

ItemDetailAs ofBasisSource
Notable resultOver its service life delivered 2.49 billion CPU hours across 18.64 million jobs for 2,958 users, at 1.96 percent downtime (2017)User communities used 92.57 percent of capacity.2017-12Operator statedcisl.ucar.edu
Notable resultNCAR's first petascale computer, ranked 13th in the world when installed (2012)About 30 times Bluefire's power at roughly twice its electrical draw.2012Operator statedcisl.ucar.edu

The read

NCAR's first petascale machine and the first system at the NCAR-Wyoming centre: an IBM iDataPlex of 4,536 dx360 M4 nodes on FDR InfiniBand, 13th on the November 2012 TOP500, in production from 20 December 2012 and retired at the end of 2017 in favour of Cheyenne. NCAR and TOP500 disagree on the processor (E5-2650 against E5-2670), the core count (72,576 against 72,288) and the power draw (about 1.2 MW against 1,437 kW), so none of those is recorded and each is logged. The site row for the Wyoming centre carries 2016 as its commissioning year, which is Cheyenne's date rather than Yellowstone's. TOP500 is the only source for Rmax and Rpeak, so the tier is reported.

Timeline

  • 2012-06 Yellowstone entered use on 4 June 2012 ahead of full-scale production in December source
  • 2012-11 Listed at #13 on the TOP500 (November 2012) source
  • 2012-12 First operational source
  • 2017-12 Performed its last calculation on December 30 after five and a half years source

Public list appearances

Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.

Site & facility

NCAR-Wyoming Supercomputing Center

Location
Cheyenne, WY, USA
Commissioned
2016

Where sources disagree

We record conflicts instead of picking a winner quietly. All open questions.

Change history

Nearby in scale

The machines closest to Yellowstone by Rmax, smaller to larger.

Same site

Same operator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
cisl.ucar.edunames system and partMellanox InfiniBand FDR
top500.orgnames system and partMellanox InfiniBand FDR

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.