Supercomputers/Systems/Theta
USA · decommissioned · hpc
Theta
Operated by Argonne National Laboratory at Argonne Leadership Computing Facility .
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 5.88 PFlop/s
- Rpeak
- 9.63 PFlop/s
- Rmax ÷ Rpeak
- 61.1%
- Cores
- 231,424
- Power
- 1.09 MW
- Per watt
- 5.4 GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Theta, and those in USA. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 5.88 PFlop/s | #31 of 234 · top 13% | #73 of 332 · top 22% |
| Energy efficiency | 5.4 GF/W | #31 of 158 · top 19% | #42 of 162 · top 25% |
| Rmax ÷ Rpeak | 61.1 % | #185 of 229 · bottom 20% | #272 of 331 · bottom 19% |
| Power draw | 1,087 kW | #50 of 161 · top 31% | #57 of 171 · top 33% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Cray XC40 | Cray HPENYSE
rolls up to Hewlett Packard Enterprise | - | Reported | top500.orgweb.archive.org |
| Interconnect | Cray Aries Interconnect Dragonfly · About 10 GB/s per direction · Around 1 microsecond Cray Aries interconnect, three-tier dragonfly | Cray HPENYSE
rolls up to Hewlett Packard Enterprise | - | Reported | cug.org |
| Operating system | Cray Linux Environment Operating systems Linux, Cray-customised · Proprietary layer over open-source Linux Cray Linux Environment | Cray HPENYSE
rolls up to Hewlett Packard Enterprise | - | Reported | top500.org |
Engineering, funding and access
What Theta runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Interconnect and topology | Cray AriesTOP500 list entry | 2018-06 | Operator stated | top500.org |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Programming and software stack | Cray Linux EnvironmentTOP500 list entry | 2018-06 | Operator stated | top500.org |
Results
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Notable result | 2017 to 2023: one of the largest collections of 3D supernova simulations and the longest full-physics 3D supernova calculation, by Adam Burrows's team at PrincetonArgonne's December 2023 feature says Theta delivered 202 million compute hours to more than 600 projects. | 2023-12 | Operator stated | eurekalert.org |
| Notable result | 2017 to 2023: screening of nearly 10,000 compounds for solar-cell materials that found five high-performing candidates for lab testing, by Jacqueline Cole's University of Cambridge team under the ALCF Data Science Program | 2023-12 | Operator stated | eurekalert.org |
| Notable result | 2017 to 2023: the largest simulation of flow inside an internal combustion engine | 2023-12 | Operator stated | eurekalert.org |
The read
Argonne's Cray XC40 of Xeon Phi 7230 nodes, sixteenth on the June 2017 TOP500 at 231,424 cores, retired at the end of 2023 according to ALCF and Argonne, which are one organization and reachable here only through archived copies. TOP500 kept listing it until 2025. The later ThetaGPU expansion is not recorded. TOP500 is the only source for Rmax, Rpeak and core count, so the tier is reported.
Timeline
- 2017-06 Listed at #16 on the TOP500 (June 2017) source
- 2017-07 First operational source
- 2018-06 TOP500 entry grew from 231,424 to 280,320 cores, raising Rmax from 5.88 to 6.92 PFlop/s source
- 2020 ThetaGPU, an NVIDIA GPU expansion funded under the CARES Act, was added and first dedicated to COVID-19 research source
- 2023-12 Retired at year end; ThetaGPU hardware later repurposed into a new system, Sophia source
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Argonne Leadership Computing Facility
- Location
- Lemont, IL, USA
- Cooling
- Direct liquid cooling (warm water)
- Commissioned
- 2006
Change history
- 2026-09-20 Added with a rank pointer on the edition where it ranked highest
Nearby in scale
The machines closest to Theta by Rmax, smaller to larger.
- Sawtooth · USA, operational · 5.78 PFlop/s
- JMA Cray XC50 · Japan, operational · 5.73 PFlop/s
- Lynx (LLNL) · USA, operational · 5.65 PFlop/s
- Narval · Canada, operational · 5.89 PFlop/s
- Arunika · India, operational · 5.94 PFlop/s
- Pleiades · USA, decommissioned · 5.95 PFlop/s
Related systems
Same site
- Cooley · USA, operational, 2015
- Polaris · USA, operational, 2021
- Cetus · USA, operational, 2012
- Mira · USA, decommissioned, 2012
- Sunspot · USA, operational, 2022
- Vesta (Argonne) · USA, operational, 2012
Same operator
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| web.archive.org | names system only | - |
| top500.org | names system and part | Cray Aries, Cray Linux Environment |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.
Programming a supercomputer
The software stack beneath the application, and why the OS is now a sovereignty signal as much as a technical choice.