Denmark · operational · ai training

Gefion

Operated by Danish Centre for AI Innovation at Danish Centre for AI Innovation (Digital Realty) .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
66.59 PFlop/s
HPL measured
Rpeak
100.6 PFlop/s
Rmax ÷ Rpeak
66.2%
Cores
223,088
Power
1.75 MW
Per watt
38.0 GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

How it compares

Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Gefion, and those in Denmark. Computed from our tables; a metric is ranked only when at least eight peers report it.

MetricValueAgainst its eraAgainst its country
Rmax66.59 PFlop/s#41 of 234 · top 17%-
Energy efficiency38.0 GF/W#66 of 121 · bottom 47%-
Rmax ÷ Rpeak66.2 %#163 of 231 · bottom 31%-
Power draw1,753 kW#26 of 126 · top 20%-

Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
NVIDIA DGX SuperPOD, assembled by Eviden
Eviden
ATOEPA rolls up to Atos
- Verified top500.orgnovonordiskfonden.dk
Accelerator NVIDIA H100 SXM5
Accelerators
CUDA (Hopper GH100) · 16,896C · 1.98 GHz · TSMC 4N · 700 W
1,528 NVIDIA H100 GPUs
NVIDIA - Verified top500.orgnovonordiskfonden.dk
CPU Intel Xeon Platinum 8480C
CPUs
x86-64 · 56C · 2 GHz · Intel 7 · 350 W
Xeon Platinum 8480C 56C 2GHz
Intel - Reported top500.org
Interconnect NVIDIA InfiniBand HDR
Interconnect
Fat tree or dragonfly+ · 200 Gb/s per port · About 0.6 microseconds
Octo-rail NVIDIA HDR100 Infiniband / NVIDIA Quantum-2
NVIDIA - Verified top500.orgnovonordiskfonden.dk
Operating system Red Hat Enterprise Linux
Operating systems
Linux distribution · Open source, commercial support subscription
Red Hat Enterprise Linux
Red Hat
IBMNYSE rolls up to IBM
- Reported top500.org

Engineering, funding and access

What Gefion runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Interconnect and topologyOcto-rail NVIDIA HDR100 InfiniBandThe Novo Nordisk Foundation article names NVIDIA Quantum-2 InfiniBand networking2024-11Operator statedtop500.org

Software

ItemDetailAs ofBasisSource
Programming and software stackRed Hat Enterprise Linux, NVIDIA HPC-Benchmarks, NVIDIA cuBLAS and HPC-X MPI (as submitted for the TOP500 HPL run)2024-11Operator statedtop500.org

Funding

ItemDetailAs ofBasisSource
Funded byNovo Nordisk Foundation, about DKK 600 million toward initial centre costs2024-10Operator statednovonordiskfonden.dk
Funded byExport and Investment Fund of Denmark (EIFO), DKK 100 million for a 15% minority stake in DCAI2024-10Operator statednovonordiskfonden.dk
ProcurementAssembled and installed by Eviden on an NVIDIA DGX SuperPOD; six months from announcement to completion2024-10Operator statednovonordiskfonden.dk

Access

ItemDetailAs ofBasisSource
How researchers get timePilot phase for select customers after a competition with over 50 proposals in three weeks and 6 winners, then wider use2024-10Operator statednovonordiskfonden.dk

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Accelerators 1,528 accelerators 2024-10 Operator stated H100 GPUs in the DGX SuperPOD, per the Novo Nordisk Foundation launch release (23 Oct 2024). novonordiskfonden.dk

The read

Denmark's first AI supercomputer, funded jointly by the Novo Nordisk Foundation and the state export-credit fund EIFO rather than by a research-council budget alone: a novel funding pattern for a national AI resource. Built and assembled by Eviden in six months from announcement to completion, per the operator's own account.

Timeline

  • 2024-10 First operational source
  • 2024-10 Gefion launched in Copenhagen and put into pilot use, six months after announcement source
  • 2024-11 Gefion debuted at rank 21 on the November 2024 TOP500 at 66.59 PFlop/s source
  • 2025-06 Listed at #54 on the Green500 (June 2025) source

Public list appearances

Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.

Site & facility

Danish Centre for AI Innovation (Digital Realty)

Location
Copenhagen, Denmark
Commissioned
2024

Change history

Nearby in scale

The machines closest to Gefion by Rmax, smaller to larger.

Same accelerator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
novonordiskfonden.dknames system and partNVIDIA H100 SXM5, NVIDIA InfiniBand HDR
top500.orgnames system and partNVIDIA H100 SXM5, Intel Xeon Platinum 8480C, NVIDIA InfiniBand HDR

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.