Supercomputers/Systems/Ascend (OSC)
USA · operational · mixed
Ascend (OSC)
Also known as Ohio Supercomputer Center Ascend
Operated by Ohio Supercomputer Center .
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- -
- Rpeak
- 2.00 PFlop/s
- Rmax ÷ Rpeak
- -
- Cores
- -
- Power
- -
- Per watt
- - GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Dell Technologies PowerEdge servers (24 compute nodes) | Dell Technologies | - | Reported | osc.edu |
| Accelerator | - 96 NVIDIA A100 80GB Tensor Core GPUs with NVLink | NVIDIA | 96 reported | Reported | osc.edu |
| CPU | - 48 AMD EPYC CPUs | AMD | - | Reported | osc.edu |
| Interconnect | NVIDIA InfiniBand HDR Interconnect Fat tree or dragonfly+ · 200 Gb/s per port · About 0.6 microseconds NVIDIA Quantum 200Gb/s InfiniBand | NVIDIA | - | Reported | osc.edu |
Engineering, funding and access
What Ascend (OSC) runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 322 nodes24 original Dell PowerEdge XE8645 nodes with four A100 80 GB each, plus 214 dual-GPU and 84 triple-GPU A100 40 GB nodes added in 2025; 24 dual-GPU nodes are reserved for Kubernetes | 2025-12 | Operator stated | osc.eduosc.edu |
| Total memory | 173 TBDerived from per-node RAM in OSC's release: 24 nodes x 1 TB + 298 nodes x 0.5 TB = 173 TB | 2025-12 | Operator stated | osc.edu |
| Interconnect and topology | NVIDIA HDR InfiniBand: HDR200 (200 Gb/s) on the 24 quad-GPU nodes and HDR100 (100 Gb/s) on the 298 expansion nodes | 2025-12 | Operator stated | osc.eduosc.edu |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Job scheduler | Slurm | 2026 | Operator stated | osc.edu |
| Programming and software stack | Red Hat Enterprise Linux 9 | 2026 | Operator stated | osc.edu |
| Programming and software stack | Lmod module system with versioned modules, for example intel/2021.10.0 | 2026 | Operator stated | osc.edu |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Funded by | Ohio State University Wexner Medical Center and College of Medicine, which transferred a research computing cluster with $8 million in hardware to OSC for the expansionOSC said it was investing over $1 million to move the equipment to its Columbus data centre and integrate it with Ascend | 2024-09 | Operator stated | osc.eduosc.edu |
| Procurement | Dell designed and built the original system, with AMD supplying CPUs and NVIDIA the A100 GPUs and InfiniBand, announced 12 April 2022 for a fall 2022 launch | 2022-04-12 | Operator stated | osc.edu |
Access
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| How researchers get time | OSC client model: subsidized Ohio academic research projects, free classroom projects, paid priority or condo access by service agreement, and other clients at standard prices with a $500 depositOhio academic requests may need host-institution approval; Ohio State College of Medicine affiliates get priority scheduling and zero-cost jobs funded by the college (December 2025 release) | 2026 | Operator stated | osc.eduosc.edu |
| Access page | www.osc.edu/node/4887OSC service categories page listing client types, eligibility and how to apply | 2026 | Operator stated | osc.edu |
AI datacenter metrics
Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.
| Metric | Value | As of | Basis | Note | Source |
|---|---|---|---|---|---|
| Accelerators | 96 accelerators | 2023-01 | Operator stated | 96 NVIDIA A100 80GB GPUs at launch per OSC's January 2023 release. | osc.edu |
The read
The Ohio Supercomputer Center's first dedicated GPU cluster, launched on 19 January 2023 for AI, data analytics and machine learning after testing from late October to mid-December 2022. OSC's release describes Dell PowerEdge servers (24 compute nodes) with 48 AMD EPYC CPUs and 96 NVIDIA A100 80 GB GPUs linked by NVLink and NVIDIA Quantum 200 Gb/s InfiniBand, adding 2 PFlop/s of theoretical peak performance. The release is from launch, so later expansions are not captured.
Timeline
- 2022-04-12 OSC announced Ascend, a Dell-built cluster of 96 NVIDIA A100 80 GB GPUs and 48 AMD EPYC CPUs, for launch in fall 2022 source
- 2023-01 First operational source
- 2024-09-25 Ohio State Wexner Medical Center transferred ownership of a research computing cluster with $8 million in hardware to OSC to expand Ascend source
- 2025-12 OSC launched the expanded Ascend with 322 Dell nodes, 776 NVIDIA A100 GPUs, 40,448 cores and about 16 PFlop/s peak, eight times the original system source
Where sources disagree
We record conflicts instead of picking a winner quietly. All open questions.
- Peak performance: About 2 PFlop/s peak at launch, as recorded against About 16 PFlop/s, 322 nodes and 40,448 cores after the December 2025 expansion. The recorded figure predates the expansion.
Change history
- 2026-10-07 Added Ascend (OSC)
Nearby in scale
The machines closest to Ascend (OSC) by accelerator count, smaller to larger.
- Aire (Leeds) · United Kingdom, operational · 84 accelerators
- Ginsburg (Columbia) · USA, operational · 78 accelerators
- NPS DGX GB300 · USA, operational · 72 accelerators
- Zaratan · USA, operational · 112 accelerators
- Hopper (Yale) · USA, operational · 116 accelerators
- ai& Tenstorrent Galaxy Supercluster · Japan, operational · 120 accelerators
Related systems
Same operator
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| osc.edu | names system and part | NVIDIA InfiniBand HDR |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Why accelerators exist, what the memory hierarchy costs, and how the CPU and accelerator merged onto one package.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.