Supercomputers/Systems/Project Jade (Cheyenne)

USA · under construction · ai training

Project Jade (Cheyenne)

Also known as Crusoe-Tallgrass Wyoming AI campus; Cheyenne Power Hub data center campus

Operated by Tallgrass Energy at Project Jade Site (Cheyenne) .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Tallgrass leads development of Project Jade and builds the Cheyenne Power Hub gas generation next to the data center
Tallgrass Energy
- Reported cowboystatedaily.com
Integrator -
Crusoe was the original data center builder and operator for Project Jade before demobilising in 2026
Crusoe
- Reported convergedigest.com

Engineering, funding and access

What Project Jade (Cheyenne) runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Cooling designClosed-loop cooling; initial fill equal to about 20 households of water and about 3 households per year after2026-06Press reportcowboystatedaily.com

Funding

ItemDetailAs ofBasisSource
Funded byTallgrass, USD 7 billion investment; the unnamed client has provided over USD 200 million in refundable contributions in aid of construction2026-06Press reportcowboystatedaily.com
Stated cost7,000 USD mTallgrass investment in Project Jade2026-06Press reportcowboystatedaily.com
ProcurementSelf-generated natural-gas power (Cheyenne Power Hub); Black Hills Energy agreed in April 2026 to procure long-lead generation equipment under Wyoming large-load tariff2026-06Press reportcowboystatedaily.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Facility power 2,700 MW 2026-10 Operator stated 2.7 GW at buildout per the June 2026 report (originally 1.8 GW); potential to scale to 10 GW. Scope is campus power, IT versus facility not stated. cowboystatedaily.comconvergedigest.com

How it is powered

SourceProviderMWStatusAs ofBasisNoteSource link
On-site gas Tallgrass Energy - planned 2026-06 Design target Cheyenne Power Hub: Tallgrass gas facility with large turbine generators, behind the meter. Campus approved to 2.7 GW; generation MW not stated. Crusoe exited. cowboystatedaily.com
Fuel cells Tallgrass Energy - planned 2026-06 Design target Fuel-cell systems are named as part of the Cheyenne Power Hub alongside turbines; MW not stated. cowboystatedaily.com
Grid Black Hills Energy - planned 2026-01 Regulatory filing Black Hills Energy filed a CPCN in Jan 2026 for a substation supporting the project; the campus is designed to generate its own power rather than draw from the grid. cowboystatedaily.com

How AI campuses are powered: capacities are what the operator, utility or filing states, not what has been delivered.

The read

Project Jade, a behind-the-meter AI data center campus south of Cheyenne, Wyoming, first announced in July 2025 by Crusoe and Tallgrass as a 1.8 GW campus scalable to 10 GW. Laramie County approved it in January 2026 at up to 2.7 GW. Crusoe, which was to build and operate the data halls, demobilised from the site roughly two months before June 2026 at the request of its customer; Tallgrass now leads development with an undisclosed data center client that has contributed over 200 million dollars of refundable construction aid, and Tallgrass says work never stopped. The project has three parts: the Cheyenne Power Hub (natural-gas generation with CO2 sequestration), the data center buildings and the client's compute. First power is expected in 2027 and data center service in early 2028. No accelerator vendor or count is stated. Tallgrass is recorded as operator because Crusoe left. The tier is reported. It has never submitted an HPL result.

Timeline

  • 2025-07 Announced source
  • 2026 Crusoe, which was to build the data halls, exited the project in early 2026 while Tallgrass says the project was never paused. source
  • 2026-04 Black Hills Energy agreed to procure long-lead generation equipment for Project Jade under Wyoming large-load tariff. source

Site & facility

Where sources disagree

We record conflicts instead of picking a winner quietly. All open questions.

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
convergedigest.comnames system only-
cowboystatedaily.comnames system only-

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.