Supercomputers/Systems/Great Lakes

USA · operational · mixed

Great Lakes

Also known as U-M Great Lakes

Operated by University of Michigan .

Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
860.00 TFlop/s
HPL measured
Rpeak
1.32 PFlop/s
Rmax ÷ Rpeak
65.2%
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Dell EMC PowerEdge C6420 compute, R640 high-memory and R740 GPU nodes
Dell Technologies - Verified top500.orgnextplatform.com
Accelerator NVIDIA Tesla V100
Accelerators
CUDA (Volta GV100) · 5,120C · 1.53 GHz · 12 nm · 300 W
NVIDIA Tesla V100 GPUs in R740 nodes
NVIDIA - Verified top500.orgnextplatform.com
CPU -
Intel Xeon Gold 6154 18C 3 GHz per TOP500
Intel - Reported top500.org
Interconnect NVIDIA InfiniBand HDR
Interconnect
Fat tree or dragonfly+ · 200 Gb/s per port · About 0.6 microseconds
Mellanox HDR InfiniBand fabric with HDR100 to the nodes
NVIDIA - Verified top500.orgnextplatform.com
Storage -
DDN GRIDScaler 14KX with 100 TB of Infinite Memory Engine
DDN
- Reported top500.org

The read

The University of Michigan's shared HPC cluster for thousands of researchers, built by Dell EMC as lead vendor (about 4.8 million dollars) with Mellanox HDR/HDR100 InfiniBand and DDN GRIDScaler 14KX storage with 100 TB of Infinite Memory Engine. Nodes are PowerEdge C6420 compute, R640 high-memory and R740 GPU servers with NVIDIA Tesla V100 GPUs; Next Platform reports about 13,000 cores and scheduled a late-2019 start for users, while TOP500 lists the installation year as 2018 with Xeon Gold 6154 18C, 16,960 cores, 0.86 PFlop/s Rmax and 1.32 PFlop/s Rpeak. The core counts differ between sources, so no core figure is recorded and no go-live date is asserted. Later additions such as A100 and A40 nodes are not covered by these sources.

Timeline

No dated events recorded.

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
nextplatform.comnames system only-
top500.orgnames system and partNVIDIA Tesla V100, NVIDIA InfiniBand HDR

Checked 2026-10-09 by pnpm verify. Re-run it and the table changes with the web.