Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
100.00 MW
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

How it compares

Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Cerebras Guyana AI Data Center, and those in Guyana. Computed from our tables; a metric is ranked only when at least eight peers report it.

MetricValueAgainst its eraAgainst its country
Power draw100,000 kW#1 of 104 · highest-

Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Cerebras Systems to build and operate the AI data center under a revenue-sharing MoU with the Government of Guyana
Cerebras - Reported cerebras.aidevelopingtelecoms.com
Accelerator Cerebras WSE-3
Accelerators
Cerebras (wafer-scale) · 900,000C · TSMC N5 · 23,000 W
Cerebras CS-3 AI supercomputers (planned; unit count not disclosed in the MoU announcement)
Cerebras - Reported cerebras.aidevelopingtelecoms.com

Engineering, funding and access

What Cerebras Guyana AI Data Center runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Funding

ItemDetailAs ofBasisSource
Funded byCerebras Systems, which says it will make an investment in the facility (amount not disclosed)2025-11-11Operator statedcerebras.ai
ProcurementMemorandum of Understanding between the Government of Guyana and Cerebras for an AI data center of up to 100 MW at Wales, with EY facilitating; Cerebras CS-3 systems to be deployedNo construction or operating timeline is given in the release2025-11-11Operator statedcerebras.ai

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Facility power 100 MW 2025-11 Design target MOU announced Nov 2025 for an AI data center of up to 100 MW at Wales, Guyana; value is an upper bound, no build commitment stated. cerebras.ai

The read

Announced 11 November 2025 as a Memorandum of Understanding between the Government of Guyana and Cerebras Systems to build and operate an AI data center of up to 100 MW at Wales, on Guyana's Demerara coast, deploying Cerebras CS-3 wafer-scale AI supercomputers as the flagship of Cerebras' 'Cerebras for Nations' sovereign-AI initiative. The facility is planned near Guyana's Gas-to-Energy plant and is intended to draw on natural gas piped from the Stabroek Block offshore oilfield. Cerebras and the Guyana government are to share revenue from the facility. Cerebras' own press release and independent trade press (Developing Telecoms) agree on the MoU date, the 100 MW target, the CS-3 platform and the Wales location, but neither discloses a unit count, GPU or core count, or FLOPS figure beyond the stated power target, and no ground-breaking or hardware delivery has been confirmed as of the most recent reporting found, so status is recorded as planned. Confidence stays reported because Cerebras is a party to the deal and no fully independent source restates the specific technical figures.

Timeline

Site & facility

Change history

Same operator

Same accelerator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
developingtelecoms.comblocked our fetch-
cerebras.ainames system and partCerebras WSE-3

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.