Supercomputers/Systems/Polaris Forge 2 (Harwood)

USA · under construction · ai training

Polaris Forge 2 (Harwood)

Also known as Applied Digital Polaris Forge 2

Operated by Applied Digital at Applied Digital Polaris Forge 2 Campus (Harwood) .

Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Applied Digital builds and leases the 200 MW critical IT Polaris Forge 2 campus to an unnamed investment-grade hyperscaler
Applied Digital - Reported ir.applieddigital.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
IT power 200 MW 2025-10-22 Design target Applied Digital: 200 MW critical IT leased to a hyperscaler (about 15 years) in 2 buildings, online 2026 to 2027. Campus designed for 1 GW; first 200 MW only. ir.applieddigital.com
PUE 1.18 2025-10-22 Design target Applied Digital: projected PUE of 1.18 for Polaris Forge 2 with near-zero water consumption. Design projection, not measured. ir.applieddigital.com

The read

Applied Digital's second North Dakota AI factory, a two-building campus near Harwood in Cass County. Applied Digital signed an approximately 15-year take-or-pay lease with a US investment-grade hyperscaler (unnamed) for 200 MW of critical IT load on 22 October 2025, worth about 5 billion dollars of prospective lease revenue, and funded it with a 2.15 billion dollar senior secured notes offering. Groundbreaking was 18 August 2025, with initial capacity anticipated in calendar 2026 and full capacity by early 2027; the company's July 2026 results still list the campus as under construction and give no ready-for-service date. Because the tenant is not named, Applied Digital is recorded as operator. Both sources are Applied Digital's own, so the tier is reported. Power is from Cass County Electric Cooperative per trade press. It has never submitted an HPL result.

Timeline

Site & facility

Applied Digital Polaris Forge 2 Campus (Harwood)

Location
Harwood, ND, USA
Utility
Cass County Electric Cooperative

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
ir.applieddigital.comnames system only-
ir.applieddigital.comnames system only-

Checked 2026-10-09 by pnpm verify. Re-run it and the table changes with the web.