Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 4.29 PFlop/s
- Rpeak
- 6.62 PFlop/s
- Rmax ÷ Rpeak
- 64.8%
- Cores
- 76,608
- Power
- 845.09 kW
- Per watt
- 5.1 GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Oakbridge-CX, and those in Japan. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 4.29 PFlop/s | #95 of 230 · top 41% | #41 of 131 · top 31% |
| Energy efficiency | 5.1 GF/W | #64 of 129 · top 49% | #32 of 74 · top 42% |
| Rmax ÷ Rpeak | 64.8 % | #140 of 224 · bottom 39% | #100 of 130 · bottom 24% |
| Power draw | 845 kW | #51 of 132 · top 38% | #28 of 74 · top 37% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Fujitsu PRIMERGY CX2550/CX2560 M5, 1,368 nodes | Fujitsu | - | Reported | top500.orgcc.u-tokyo.ac.jp |
| CPU | Intel Xeon Platinum 8280 CPUs x86-64 · 28C · 2.7 GHz · 14 nm · 205 W Two Intel Xeon Platinum 8280 28C 2.7GHz per node | Intel | - | Verified | top500.orgcc.u-tokyo.ac.jp |
| Interconnect | Omni-Path Architecture Interconnect Fat tree · 100 Gb/s per port · About 1 microsecond Intel Omni-Path 100 Gbps | Intel | - | Verified | top500.orgcc.u-tokyo.ac.jp |
Engineering, funding and access
What Oakbridge-CX runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 1,368 nodes1,240 standard nodes plus 128 nodes with 1.6 TB NVMe SSDs, all Fujitsu PRIMERGY CX2550 M5 with two 28-core Xeon Platinum 8280. | 2023 | Operator stated | cc.u-tokyo.ac.jpcc.u-tokyo.ac.jp |
| Total memory | 282 TB256.5 TiB stated (192 GiB per node); 256.5 x 1.0995 = 282.0 TB. | 2023 | Operator stated | cc.u-tokyo.ac.jp |
| Storage capacity | 12.4 PBLustre on a DDN ES18K. | 2023 | Operator stated | cc.u-tokyo.ac.jp |
| Interconnect and topology | Intel Omni-Path at 100 Gb/s in a full-bisection fat tree | 2023 | Operator stated | cc.u-tokyo.ac.jp |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Parallel filesystem | Lustre on a DDN ES18K with 2 OSS servers, 12.4 PB at 193.9 GB/s | 2023 | Operator stated | cc.u-tokyo.ac.jp |
| Programming and software stack | Red Hat Enterprise Linux 7 and CentOS 7; GNU and Intel compilers; Intel MPI and Open MPI; Singularity containers | 2023 | Operator stated | cc.u-tokyo.ac.jp |
Access
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| How researchers get time | University of Tokyo programmes: general use, educational use, corporate use, young and women researchers, exploratory joint research calls including AI for HPC, the Large-scale HPC Challenge and trial use | 2023-09 | Operator stated | cc.u-tokyo.ac.jp |
The read
The University of Tokyo Information Technology Center's Fujitsu PRIMERGY cluster of 1,368 nodes (1,240 standard and 128 with SSD), each with two Xeon Platinum 8280 (28-core) CPUs and 192 GiB memory on 100 Gbps Intel Omni-Path. The centre quotes 6.61 PFlop/s peak; TOP500 lists 76,608 cores, Rmax 4.29 and Rpeak 6.62 PFlop/s at 845 kW, debuting 45th in June 2019 and last listed in June 2023. The centre's service page states operation has been terminated; the exact end date was not found. The University of Tokyo's Oakbridge-CX service page (https://www.cc.u-tokyo.ac.jp/supercomputer/obcx/service/) says service ended on 29 September 2023.
Timeline
- 2019 First operational source
- 2019-06 Listed at #45 on the TOP500 (June 2019) source
- 2023-09-29 Oakbridge-CX service ended at the University of Tokyo source
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Change history
- 2026-11-08 Oakbridge-CX retirement date added
- 2026-10-02 Added Oakbridge-CX, the University of Tokyo Omni-Path cluster, 45th on the June 2019 TOP500
Nearby in scale
The machines closest to Oakbridge-CX by Rmax, smaller to larger.
- Vulcan · USA, decommissioned · 4.29 PFlop/s
- Manzano · USA, operational · 4.28 PFlop/s
- Cannon2-H200 · USA, operational · 4.24 PFlop/s
- Viper-CPU · Germany, operational · 4.29 PFlop/s
- CRONOS · France, operational · 4.3 PFlop/s
- Sugon Advanced Computing System PreE · China, operational · 4.33 PFlop/s
Related systems
Same operator
- mdx I · Japan, operational, 2021
- Reedbush-H · Japan, decommissioned, 2017
- Reedbush-L · Japan, decommissioned, 2017
- Wisteria/BDEC-01 · Japan, operational, 2021
- Reedbush-U · Japan, decommissioned, 2016
- Shirokane3 · Japan, operational, 2015
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| top500.org | names system and part | Intel Xeon Platinum 8280, Omni-Path Architecture |
| cc.u-tokyo.ac.jp | names system and part | Intel Xeon Platinum 8280, Omni-Path Architecture |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.