Supercomputers/Systems/Mogon II
Germany · operational · hpc
Mogon II
Operated by Johannes Gutenberg University Mainz at JGU Mainz HPC Site .
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 1.97 PFlop/s
- Rpeak
- 2.80 PFlop/s
- Rmax ÷ Rpeak
- 70.4%
- Cores
- 49,432
- Power
- 657 kW
- Per watt
- 3.0 GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Mogon II, and those in Germany. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 1.97 PFlop/s | #97 of 234 · top 41% | #47 of 95 · top 49% |
| Energy efficiency | 3.0 GF/W | #71 of 158 · top 45% | #39 of 68 · bottom 44% |
| Rmax ÷ Rpeak | 70.4 % | #120 of 229 · bottom 49% | #53 of 94 · bottom 45% |
| Power draw | 657 kW | #77 of 161 · top 47% | #28 of 69 · top 40% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - MEGWARE MiriQuid cluster (NEC/MEGWARE per TOP500) | MEGWARE | - | Reported | megware.comtop500.org |
| CPU | - Intel Xeon E5-2630v4 10C 2.2GHz Broadwell nodes (822 nodes, two CPUs each) | Intel | 822 reported | Reported | hpc-en.uni-mainz.de |
| CPU | - Intel Xeon Gold 6130 16C 2.1GHz Skylake nodes (1,136 nodes, two CPUs each) | Intel | 1,136 reported | Reported | hpc-en.uni-mainz.detop500.org |
| Interconnect | Omni-Path Architecture Interconnect Fat tree · 100 Gb/s per port · About 1 microsecond Intel Omni-Path 50 Gbit/s fat tree | Intel | - | Reported | hpc-en.uni-mainz.detop500.org |
Engineering, funding and access
What Mogon II runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 1,876 nodesJGU pages split this as 822 Broadwell nodes plus 1,046 (press release) or 1,136 (systems page) Skylake nodes, so the parts do not sum to the stated total | 2017-11 | Operator stated | press.uni-mainz.dehpc-en.uni-mainz.de |
| Storage capacity | 7.5 PBUsable capacity; the 2014 plan called for more than 7 PB at up to 100 GB/s | 2017-11 | Operator stated | press.uni-mainz.de |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Programming and software stack | Intel compiler suite, Intel MKL and Intel MPI 2017 Update 2 on CentOSTOP500 list entry (HPL submission) | 2017-11 | Operator stated | top500.org |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Funded by | German federal government, one of the funders of the EUR 10.6 million invested since 2016 | 2017-11 | Operator stated | press.uni-mainz.de |
| Funded by | State of Rhineland-Palatinate | 2017-11 | Operator stated | press.uni-mainz.de |
| Funded by | Johannes Gutenberg University Mainz | 2017-11 | Operator stated | press.uni-mainz.de |
| Funded by | Helmholtz Institute Mainz, which also co-operates the system | 2017-11 | Operator stated | press.uni-mainz.dehpc-en.uni-mainz.de |
| Funding programme | Joint federal, state and university investment backed by the German Council of Science and Humanities (Wissenschaftsrat); EUR 8.7 million was announced in April 2014 for 2015 to 2017, and JGU later put the total at EUR 10.6 million | 2017-11 | Operator stated | press.uni-mainz.depress.uni-mainz.de |
| Procurement | Two phases: MEGWARE won the EUR 2.8 million tender for the first 820 Broadwell nodes (16,400 cores), announced on 2 September 2016; TOP500 credits NEC with the 2017 Skylake expansion | 2017 | Vendor stated | megware.comtop500.org |
Access
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| How researchers get time | Free for researchers at Rhineland-Palatinate universities and research institutions through AHRP project applications, reviewed by the AHRP and where needed external scientists, with use metered in Nutzungseinheiten | 2025 | Operator stated | ahrp.info |
| Access page | www.ahrp.info/ressourcen.shtmlAHRP resources page with the application forms; JGU announced in September 2017 that MOGON II applications open there | 2025 | Operator stated | ahrp.infohpc.uni-mainz.de |
The read
Johannes Gutenberg University Mainz's HPC cluster, acquired in 2016 and 2017 and operated by the university's data centre together with the Helmholtz Institute Mainz. The university lists 822 Broadwell nodes (Xeon E5-2630v4) and 1,136 Skylake nodes (Xeon Gold 6130) on a 50 Gbit/s Omni-Path fat tree; MEGWARE supplied the first phase of 820 nodes. TOP500 gives 49,432 cores and 1.97 PFlop/s Rmax, listed from June 2017 to June 2023 and 216th in June 2020.
Timeline
- 2014-04-11 JGU announced EUR 8.7 million from the federal government, the state and the university for MOGON II after the German Council of Science and Humanities agreed to fund it source
- 2016-09-02 MEGWARE announced it had won the EUR 2.8 million tender for MOGON II's first phase of 820 Broadwell nodes with 16,400 cores source
- 2017 First operational source
- 2017-10 The second phase of Skylake nodes went into operation, bringing MOGON II to about 2 PFlop/s source
- 2017-11 JGU said its 65th place on the November 2017 TOP500 made MOGON II the fastest supercomputer then installed at a German university source
- 2020-06 Listed at #216 on the TOP500 (June 2020) source
- 2025-04-03 JGU said MOGON II's file servers would be retired in summer 2025 after rising disk failures and that MOGON II must shut down no later than the release of a successor planned for early 2026 source
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Change history
- 2026-10-02 Added Mogon II, Mainz University's HPC cluster
Nearby in scale
The machines closest to Mogon II by Rmax, smaller to larger.
- amplitUDE · Germany, operational · 1.95 PFlop/s
- Alvis · Sweden, decommissioned · 1.94 PFlop/s
- RE1 (Flatiron) · USA, operational · 1.93 PFlop/s
- Biowulf · USA, operational · 1.97 PFlop/s
- Gaïa (EDF) · France, operational · 1.98 PFlop/s
- A64FX Prototype · Japan, operational · 2 PFlop/s
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| hpc-en.uni-mainz.de | names system only | - |
| top500.org | names system and part | Omni-Path Architecture |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.