Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
1.95 PFlop/s
HPL measured
Rpeak
3.80 PFlop/s
Rmax ÷ Rpeak
51.3%
Cores
6,768
Power
37.98 kW
Per watt
51.3 GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

How it compares

Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of amplitUDE, and those in Germany. Computed from our tables; a metric is ranked only when at least eight peers report it.

MetricValueAgainst its eraAgainst its country
Rmax1.95 PFlop/s#232 of 234 · bottom 2%#48 of 95 · top 50%
Energy efficiency51.3 GF/W#38 of 121 · top 31%#9 of 68 · top 12%
Rmax ÷ Rpeak51.3 %#220 of 231 · bottom 6%#92 of 94 · bottom 3%
Power draw38 kW#124 of 126 · bottom 3%#69 of 69 · bottom 1%

Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
MEGWARE D50DNP
MEGWARE
- Reported top500.orguni-due.de
Accelerator NVIDIA H100 80GB PCIe
Accelerators
CUDA (Hopper)
17 nodes with four and 2 nodes with two NVIDIA H100 PCIe GPUs
NVIDIA 72
reported
Reported uni-due.detop500.org
CPU -
Intel Xeon Platinum 8480+ 56C 2GHz, dual-socket nodes
Intel - Reported top500.orguni-due.de
Interconnect NVIDIA InfiniBand NDR (Quantum-2)
Interconnect
Fat tree or dragonfly+ · 400 Gb/s per port · Under 0.6 microseconds
Mellanox InfiniBand NDR200, 1:1.66 blocking
NVIDIA - Reported uni-due.detop500.org

Engineering, funding and access

What amplitUDE runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Compute nodes259 nodesSum of 240 CPU nodes (176 with 512 GB, 51 with 1 TB and 13 with 2 TB) and 19 GPU nodes (17 with four and 2 with two H100), all with two Xeon Platinum 8480+2024-11Operator stateduni-due.de
Storage capacity2.1 PBLustre, about 2.1 PB usable2024-11Operator stateduni-due.de

Software

ItemDetailAs ofBasisSource
Parallel filesystemLustre2024-11Operator stateduni-due.de
Programming and software stackAlmaLinux 9.1 with NVCC and GCC, cuBLAS 12.0 and OpenMPI from NVIDIA HPC-X 2.15TOP500 list entry (HPL submission on the GPU partition)2023-06Operator statedtop500.org

Funding

ItemDetailAs ofBasisSource
Funded byGerman Research Foundation (DFG), through a large research instrumentation (Forschungsgroßgeräte) application2024-12Operator stateduni-due.de
Funded byState of North Rhine-Westphalia2024-12Operator stateduni-due.de
Funding programmeDFG large research instrumentation programme (Forschungsgroßgeräte) with the State of NRW; the commissioning project totalled EUR 7.6 million2024-12Operator stateduni-due.de

The read

The University of Duisburg-Essen's MEGWARE supercomputer, whose GPU partition was benchmarked in 2023 and placed eighth on the June 2023 Green500 at 51.3 GFlops/Watt. TOP500 lists the GPU partition at 6,768 cores, 1.95 PFlop/s Rmax and 37.98 kW (Xeon Platinum 8480+, H100 80GB PCIe, InfiniBand NDR, ranked 483rd in June 2023). The university's page describes the installed machine as 240 CPU nodes and 19 GPU nodes (17 with four and 2 with two H100), 2.1 PB of Lustre and NDR200 InfiniBand, in place since mid-2024 with official operation from early December 2024.

Timeline

  • 2023-06 Listed at #8 on the Green500 (June 2023) source
  • 2024-12 First operational source

Public list appearances

Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.

Site & facility

UDE Duisburg Campus

Location
Duisburg, Germany
Commissioned
2024

Change history

Nearby in scale

The machines closest to amplitUDE by Rmax, smaller to larger.

Same accelerator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
top500.orgnames system and partNVIDIA H100 80GB PCIe, NVIDIA InfiniBand NDR (Quantum-2)
uni-due.denames system and partNVIDIA H100 80GB PCIe, NVIDIA InfiniBand NDR (Quantum-2)

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.