Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 460.70 TFlop/s
- Rpeak
- 790.00 TFlop/s
- Rmax ÷ Rpeak
- 58.3%
- Cores
- 10,080
- Power
- 32.8 kW
- Per watt
- 14.0 GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Kukai, and those in Japan. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 460.70 TFlop/s | #203 of 234 · bottom 14% | #87 of 131 · bottom 35% |
| Energy efficiency | 14.0 GF/W | #9 of 158 · top 5% | #18 of 74 · top 23% |
| Rmax ÷ Rpeak | 58.3 % | #198 of 229 · bottom 15% | #113 of 130 · bottom 14% |
| Power draw | 33 kW | #160 of 161 · bottom 2% | #73 of 74 · bottom 2% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - ExaScaler ZettaScaler-1.6 GPGPU system | ExaScaler | - | Reported | top500.orgtop500.org |
| Accelerator | NVIDIA Tesla P100 Accelerators CUDA (Pascal GP100) · 3,584C · 1.48 GHz · 16 nm · 300 W NVIDIA Tesla P100 | NVIDIA | - | Reported | top500.org |
| CPU | - Intel Xeon E5-2650L v4 14C 1.7GHz | Intel | - | Reported | top500.org |
| Interconnect | Mellanox InfiniBand FDR Interconnect Fat tree · 56 Gb/s per 4x port · About 1 microsecond Infiniband FDR | Mellanox NVDANASDAQ
rolls up to NVIDIA | - | Reported | top500.org |
Engineering, funding and access
What Kukai runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Cooling design | Immersion cooling: the whole system sits in Fluorinert non-conductive coolant circulated to outdoor radiators, using ExaScaler's immersion systemYahoo Japan estimated about 15 percent better power efficiency than equivalent air-cooled GPU servers | 2017-07-26 | Press report | businessinsider.jpitmedia.co.jp |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Programming and software stack | CentOS with GCC 4.8.5, Intel MKL 2017 and Open MPI 1.10 (HPL run)TOP500 list entry | 2017-06 | Operator stated | top500.org |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Procurement | Project began in earnest in late 2015, was downsized around August 2016 from an initial TSUBAME 2.5-scale plan and was completed at the end of March 2017; budget about 400 million yen including equipment, data-centre works for the immersion cooling and maintenanceInstalled in a data centre of group company IDC Frontier; 80 Xeon CPUs and 160 NVIDIA Tesla P100 GPUs in total | 2017-07-26 | Press report | businessinsider.jp |
Results
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Notable result | 2017: Its first workload was training for Yahoo Japan's YJVOICE speech recognition | 2017-07-26 | Press report | businessinsider.jp |
The read
ExaScaler ZettaScaler-1.6 GPGPU cluster at Yahoo Japan Corporation: Xeon E5-2650L v4 14C 1.7GHz hosts with NVIDIA Tesla P100 GPUs on Infiniband FDR. It placed second on the June 2017 Green500 at 14.046 GFlops/Watt (460.7 TFlop/s Rmax on 32.8 kW; TOP500 rank 467), behind only TSUBAME3.0. The June 2017 list is its only TOP500 appearance, so status is carried as of that list.
Timeline
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Change history
- 2026-10-07 Added Kukai
Nearby in scale
The machines closest to Kukai by Rmax, smaller to larger.
- Reedbush-U · Japan, decommissioned · 0.46 PFlop/s
- Intrepid · USA, decommissioned · 0.46 PFlop/s
- CARL and EDDY · Germany, decommissioned · 0.46 PFlop/s
- Shadow (Mississippi State) · USA, operational · 0.46 PFlop/s
- Weta Digital Apollo 6000 · New Zealand, upgraded · 0.47 PFlop/s
- iREMB · South Korea, operational · 0.47 PFlop/s
Related systems
Same accelerator
- AIST AI Cloud · Japan, operational, 2017
- Cedar (SFU) · Canada, decommissioned, 2017
- CNIC Era-AI · China, operational, 2017
- Facebook DGX-1 Cluster · USA, operational, 2017
- Graham · Canada, decommissioned, 2017
- MN-1 · Japan, operational, 2017
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| top500.org | names system and part | NVIDIA Tesla P100, Mellanox InfiniBand FDR |
| top500.org | names system and part | NVIDIA Tesla P100, Mellanox InfiniBand FDR |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.