COMPUTE ATLAS Supercomputer supply-chain graph
1581 systems 558 sites Sourced data

Supercomputers/Systems/Cedar (SFU)

Canada · decommissioned · hpc

Cedar (SFU)

Also known as Cedar

Operated by Simon Fraser University at SFU Burnaby .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
1.34 PFlop/s
HPL measured
Rpeak
2.86 PFlop/s
Rmax ÷ Rpeak
46.9%
Cores
35,712
Power
167 kW
Per watt
8.0 GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

How it compares

Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Cedar (SFU), and those in Canada. Computed from our tables; a metric is ranked only when at least eight peers report it.

MetricValueAgainst its eraAgainst its country
Rmax1.34 PFlop/s#127 of 234 · bottom 47%#15 of 27 · bottom 47%
Energy efficiency8.0 GF/W#28 of 158 · top 17%#5 of 15 · top 29%
Rmax ÷ Rpeak46.9 %#220 of 229 · bottom 5%#24 of 27 · bottom 13%
Power draw167 kW#136 of 161 · bottom 17%#15 of 16 · bottom 8%

Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Dell EMC PowerEdge C4130 and C6320 servers, 902 nodes, sold by Scalar Decisions
Dell Technologies - Reported digitalengineering247.comtop500.org
Accelerator NVIDIA Tesla P100
Accelerators
CUDA (Pascal GP100) · 3,584C · 1.48 GHz · 16 nm · 300 W
584 NVIDIA P100 Tesla GPUs in 146 nodes
NVIDIA 584
reported
Reported top500.orgtop500.org
CPU Intel Xeon E5-2650 v4
CPUs
x86-64 · 12C · 2.2 GHz · 14 nm
Intel Xeon E5-2650v4 12C 2.2GHz
Intel - Reported top500.org
Interconnect Omni-Path Architecture
Interconnect
Fat tree · 100 Gb/s per port · About 1 microsecond
Intel Omni-Path Architecture fabric
Intel - Reported digitalengineering247.comtop500.org

Engineering, funding and access

What Cedar (SFU) runs on, who paid for it and how people get time on it. Each line carries who said it and when.

Hardware

ItemDetailAs ofBasisSource
Compute nodes902 nodesDell EMC PowerEdge C4130 and C6320 servers at launch, with 27,696 Xeon cores for computation; later CPU and GPU expansions are separate TOP500 entries.2017-04Vendor stateddigitalengineering247.com
Storage capacity11.4 PB2017-04Vendor stateddigitalengineering247.com

Software

ItemDetailAs ofBasisSource
Programming and software stackCentOS operating systemTOP500 list entry2017-06Operator statedtop500.org

The read

Compute Canada national system launched in April 2017 at Simon Fraser University's Burnaby data centre: Dell EMC PowerEdge C4130 and C6320 servers on Intel Omni-Path, 3.6 PFlop/s peak and 11.4 PB of storage per a Digital Engineering 24/7 article. The TOP500 entry for this original configuration (Xeon E5-2650v4 and 584 NVIDIA P100 GPUs in 146 nodes, 35,712 cores) was listed June 2017 to November 2020 and reached 1.34 PFlop/s Rmax, 410th on the November 2019 list. It was later expanded with new CPU and GPU partitions that the TOP500 lists as separate Cedar (CPU) and Cedar (GPU) entries.

Timeline

  • 2017-04 First operational source
  • 2019-11 Listed at #410 on the TOP500 (November 2019) source
  • 2025-09-12 Decommissioned source

Public list appearances

Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.

Site & facility

SFU Burnaby

Location
Burnaby, Canada
Commissioned
2025

Change history

Nearby in scale

The machines closest to Cedar (SFU) by Rmax, smaller to larger.

Same site

  • Fir · Canada, operational, 2025

Same accelerator

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
top500.orgnames system and partIntel Xeon E5-2650 v4, NVIDIA Tesla P100, Omni-Path Architecture
digitalengineering247.comnames system and partIntel Xeon E5-2650 v4, Omni-Path Architecture

Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.

Further reading