Supercomputers/Systems/Dogwood
USA · operational · hpc
Dogwood
Operated by GDIT at GDIT/NOAA WCOSS (Manassas) .
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 10.01 PFlop/s
- Rpeak
- 11.80 PFlop/s
- Rmax ÷ Rpeak
- 84.8%
- Cores
- 327,680
- Power
- -
- Per watt
- - GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Dogwood, and those in USA. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 10.01 PFlop/s | #48 of 213 · top 22% | #51 of 332 · top 15% |
| Rmax ÷ Rpeak | 84.8 % | #15 of 209 · top 7% | #55 of 331 · top 16% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - HPE Cray EX | Hewlett Packard Enterprise | - | Verified | top500.orgfedscoop.com |
| CPU | AMD EPYC 7742 (Rome) CPUs x86-64 · 64C · 2.25 GHz · 7 nm · 225 W AMD EPYC 7742 64C 2.25GHz | AMD | - | Reported | top500.org |
| Interconnect | HPE Slingshot-10 Interconnect Dragonfly · 100 Gb/s per port HPE Slingshot-10 | Hewlett Packard Enterprise | - | Reported | top500.org |
| Operating system | HPE Cray Operating System Operating systems SUSE-derived Linux, container-based management · Proprietary layer over open-source Linux HPE Cray OS | Hewlett Packard Enterprise | - | Reported | top500.org |
Engineering, funding and access
What Dogwood runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Storage capacity | 26 PBEach of the two WCOSS systems has 26 PB of storage | 2022-06 | Press report | fedscoop.com |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Procurement | Weather and Climate Operational Supercomputing System contract worth $505.2 million: GDIT received a $150 million task order in February 2020, with an eight-year base and two-year renewalContract covers both Dogwood (Manassas, Virginia) and Cactus (Phoenix, Arizona) | 2020-02 | Press report | fedscoop.com |
Results
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Notable result | Each WCOSS system runs at 12.1 petaflops, about three times faster than the IBM predecessors; Dogwood and Cactus ranked 49th and 50th on the TOP500 at the time | 2022-06 | Press report | fedscoop.com |
The read
One half of NOAA's Weather and Climate Operational Supercomputing System (WCOSS), an HPE Cray EX built on AMD EPYC 7742 processors over Slingshot-10, installed at a GDIT-operated data centre in Manassas, Virginia and named for local flora, the same convention its Phoenix twin Cactus follows. GDIT holds NOAA's WCOSS contract and operates both machines. NOAA's own National Weather Service director stated the upgrade exists so forecasters can run higher-resolution models for severe thunderstorms, better cloud and precipitation physics, and larger ensembles, as weather and climate events become more extreme; a later 20% capacity expansion is reported by NOAA and trade press at 14.5 PFlop/s per machine, a figure this dataset does not record since TOP500 has not re-benchmarked the expanded configuration. TOP500 is the only source for Rmax, Rpeak and core count, so the tier is reported.
Timeline
- 2020 First operational source
- 2020-02 General Dynamics IT receives a $150 million first task order under the $505.2 million NOAA WCOSS contract for two HPE Cray systems source
- 2021-06 Listed at #38 on the TOP500 (June 2021) source
- 2022-06-28 Dogwood and Cactus became operational for NOAA forecasting at 8 a.m. Eastern source
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Where sources disagree
We record conflicts instead of picking a winner quietly. All open questions.
- First operational date: 2020 as recorded against Operational for forecasting at 8 a.m. Eastern on 2022-06-28. Delivery and production dates differ; both machines show the 2022-06-28 production date as a milestone event.
Change history
- 2026-09-24 Added with a rank pointer on the edition where it ranked highest
Nearby in scale
The machines closest to Dogwood by Rmax, smaller to larger.
- Earth Simulator 4 · Japan, operational · 9.99 PFlop/s
- Dardel · Sweden, operational · 9.9 PFlop/s
- ROMEO-2025 · France, operational · 9.86 PFlop/s
- Cactus · USA, operational · 10.01 PFlop/s
- Hops · USA, operational · 10.03 PFlop/s
- GMO GPU Cloud · Japan, operational · 10.05 PFlop/s
Related systems
Same operator
- Cactus · USA, operational, 2021
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| fedscoop.com | names system and part | HPE Cray Operating System |
| top500.org | names system and part | AMD EPYC 7742 (Rome), HPE Slingshot-10, HPE Cray Operating System |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.