Supercomputers/Systems/Khazna Ajman AI Data Center

United Arab Emirates · under construction · ai training

Khazna Ajman AI Data Center

Also known as Khazna QAJ1; Ajman AI-optimized data center

Operated by Khazna Data Centers at Khazna QAJ1 Site (Ajman) .

Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Khazna builds and operates the 100 MW AI-optimized QAJ1 data center, 20 halls of 5 MW
Khazna Data Centers
rolls up to G42
- Reported khaznadatacenters.comkhaznadatacenters.com
Cooling -
Advanced liquid cooling for GPU and CPU heat dissipation
Khazna Data Centers
rolls up to G42
- Reported khaznadatacenters.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
IT power 100 MW 2024-10 Design target 100 MW in 20 halls of 5 MW; initial phase due December 2026 per Khazna. khaznadatacenters.comkhaznadatacenters.com

The read

Khazna's 100 MW AI-optimized data center (QAJ1) in Ajman, announced on 15 October 2024 as the first of its kind in the UAE: 20 data halls of 5 MW each, built for high-density GPU and AI workloads with liquid cooling, supplied by Etihad Water and Electricity. The October 2024 release targeted completion in Q3 2025; Khazna's later expansion release says the steel structures are complete and the initial phase is due in December 2026, so it is recorded as under construction. No chip vendor or count is named on either page, so only capacity is recorded. Secondary sites describe it as live, which could not be confirmed from an operator page.

Timeline

Site & facility

Khazna QAJ1 Site (Ajman)

Location
Ajman, United Arab Emirates
Utility
Etihad Water and Electricity

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
khaznadatacenters.comnames system only-
khaznadatacenters.comnames system only-

Checked 2026-10-09 by pnpm verify. Re-run it and the table changes with the web.