USA · under construction · mixed

Beacon Point (Hut 8)

Also known as Hut 8 Beacon Point AI campus

Operated by Hut 8 at Hut 8 Beacon Point Campus .

Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Hut 8 develops and leases the 1 GW Beacon Point campus (704 MW of IT leases) designed to NVIDIA DSX reference architecture
Hut 8 - Reported prnewswire.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Facility power 1,000 MW 2026-07-20 Design target Hut 8: 1,000 MW of utility capacity secured under an AEP Texas interconnection agreement. Utility capacity, not measured facility draw. sec.gov
IT power 704 MW 2026-07-20 Design target Hut 8 release: two 352 MW IT leases total 704 MW at Beacon Point. First Phase 2 hall Q2 2028; energization Q1 2027. Contracted, not yet built. sec.gov

The read

Hut 8's 1 GW Beacon Point campus in Nueces County, Texas, fully leased to one unnamed high-investment-grade tenant for AI training and inference: a 15-year 352 MW IT lease signed 6 May 2026 (9.8 billion dollars, first data hall Q3 2027) and a second identical lease on 20 July 2026 bringing contracted IT load to 704 MW (first Phase 2 hall Q2 2028). Initial energization is scheduled for Q1 2027 under a 1,000 MW AEP Texas interconnection agreement, and Hut 8 says the design follows NVIDIA's DSX reference architecture. No accelerator count is stated, and the tenant is undisclosed. Hut 8 is the only source organisation, so the tier is reported.

Timeline

Site & facility

Hut 8 Beacon Point Campus

Location
Nueces County, TX, USA
Utility
AEP Texas

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
prnewswire.comnames system only-
stocktitan.netnames system only-

Checked 2026-10-09 by pnpm verify. Re-run it and the table changes with the web.

Further reading