Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- -
- Rpeak
- 2.00 PFlop/s
- Rmax ÷ Rpeak
- -
- Cores
- -
- Power
- -
- Per watt
- - GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Dell PowerEdge dual-socket servers | Dell Technologies | - | Reported | docs.hpc.cineca.ithpc.cineca.it |
| Accelerator | - 36 GPU nodes x 2 NVIDIA V100 (quantity derived as 36 x 2) | NVIDIA | 72 reported | Reported | hpc.cineca.itdocs.hpc.cineca.it |
| CPU | - Dual-socket Intel Xeon Cascade Lake nodes (docs: Platinum 8276/8276L 2.4 GHz, hardware page: 8260), 384 GiB per node | Intel | - | Reported | docs.hpc.cineca.ithpc.cineca.it |
| Interconnect | - Mellanox InfiniBand 100 Gb/s internal network | Mellanox NVDANASDAQ
rolls up to NVIDIA | - | Reported | docs.hpc.cineca.ithpc.cineca.it |
Engineering, funding and access
What Galileo100 runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 630 nodesIncludes the 82 nodes added in November 2022; CINECA's hardware page still lists 528 compute nodes (348 thin, 180 fat) plus 36 GPU nodes. | 2026 | Operator stated | docs.hpc.cineca.ithpc.cineca.it |
| Storage capacity | 20 PB20 PB of active storage shared by cloud and HPC nodes, plus 5 PB of fast HPC storage and 1 PB of all-flash Ceph for the cloud. | 2025 | Operator stated | hpc.cineca.it |
| Interconnect and topology | Mellanox InfiniBand at up to 100 Gb/s between any pair of nodes; the cloud servers use 100 Gb/s Ethernet | 2025 | Operator stated | hpc.cineca.it |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Job scheduler | Slurm, with a g100_usr_prod partition for 1 to 32 nodes over 24 hours, quality-of-service levels for up to 64 nodes or 4 days, and fat-node and GPU partitions | 2026 | Operator stated | docs.hpc.cineca.it |
| Programming and software stack | Environment modules with GNU compilers (gcc 12.2.0), Intel VTune and Advisor, the TotalView debugger, ParaView and VMD | 2026 | Operator stated | docs.hpc.cineca.it |
| Programming and software stack | OpenStack cloud service on 77 Cascade Lake servers with 768 GB each, alongside the Slurm HPC partitions | 2025 | Operator stated | hpc.cineca.it |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Funded by | European ICEI (Interactive Computing e-Infrastructure) project, which co-funded the system | 2021-09 | Operator stated | hpc.cineca.itdocs.hpc.cineca.it |
| Funding programme | 2024 upgrade financed through Italian national projects: Terabit (OGS), MEET (INGV), the ICSC National Centre and PNC D34Health | 2024 | Operator stated | hpc.cineca.it |
| Procurement | E4 Computer Engineering won CINECA's tender in April 2024 to upgrade Galileo100 with Dell PowerEdge HS7710 CPU and R760xa GPU nodes (NVIDIA L40S and A30) and a VAST Data 50 PB multi-protocol datalakeCINECA required at least a tenfold increase in vCPUs for virtual machine services; the cloud software is based on OpenStack. | 2024-04 | Vendor stated | hpcwire.comhpc.cineca.it |
Access
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| How researchers get time | ISCRA calls: Class B projects of up to 3.6 million core hours for 12 months, Class C projects of up to 100,000 core hours for up to 9 months, and short Try projects, plus EuroHPC projects and agreements | 2026 | Operator stated | hpc.cineca.it |
| Access page | www.hpc.cineca.it/services/iscra/iscra-project-sizeCINECA ISCRA project-size page with the Galileo100 limits. | 2026 | Operator stated | hpc.cineca.it |
The read
CINECA's Dell PowerEdge Tier-1 cluster for the Italian public and industrial research community, co-funded by the European ICEI project and available since September 2021, with a stated peak of 2 PFlop/s. CINECA's documentation describes dual-socket Intel Cascade Lake nodes (the docs page names Xeon Platinum 8276/8276L at 2.4 GHz and 48 cores per node, the hardware page names the 8260), 384 GiB per node with 180 data-processing nodes carrying 3 TB of Intel Optane, and 36 GPU nodes with two NVIDIA V100 each, on a Mellanox InfiniBand 100 Gb/s network. The two CINECA pages disagree on node totals (528 versus 630 nodes, the latter including a November 2022 expansion of 82 nodes), and 77 OpenStack cloud servers and 20 PB of shared active storage sit alongside the HPC partitions, so no core count is recorded. It does not appear on the TOP500 pages checked. Both sources are CINECA pages, so the tier is reported.
Timeline
Site & facility
CINECA Casalecchio di Reno
- Location
- Casalecchio di Reno, Italy
- Commissioned
- 2015
Change history
- 2026-10-04 Added Galileo100, CINECA
Related systems
Same site
- Galileo · Italy, decommissioned, 2015
Same operator
- Leonardo · Italy, upgraded, 2022
- Marconi-100 · Italy, decommissioned, 2020
- PITAGORA · Italy, operational, 2024
- IT4LIA · Italy, planned
- LISA (Leonardo) · Italy, operational, 2026
- Marconi · Italy, decommissioned, 2016
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| docs.hpc.cineca.it | names system only | - |
| hpc.cineca.it | names system only | - |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.