Operated by China Mobile at China Mobile Wuhan Future City Data Center .

Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
operator stated
Rpeak
1.50 EFlop/s
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
China Mobile smart computing centre, 1,500 Pflops service capacity at launch
China Mobile
- Reported english.wuhan.gov.cn

The read

China Mobile's smart computing centre in Wuhan Future City, East Lake High-tech Development Zone, began operating on 8 January 2024 with 1,500 Pflops of service capacity serving Hunan, Hubei and Jiangxi, with an expansion to 6,800 Pflops planned by end of 2024 to make it the largest smart computing centre in central China (Wuhan municipal government English news). The Georgetown CSET brief of May 2025 also cites the 1,500 petaflops claim. The unit is a low-precision AI figure on an unstated basis. The 6,800 Pflops expansion is not confirmed by any page fetched, so only the launch figure is recorded. Accelerator vendor, card count and power are not stated.

Timeline

Site & facility

China Mobile Wuhan Future City Data Center

Location
Wuhan, Hubei, China
Commissioned
2024

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page