Supercomputers/Systems/Cascade (PNNL)
USA · operational · hpc
Cascade (PNNL)
Also known as EMSL Cascade; HPCS-4A
Operated by Pacific Northwest National Laboratory at EMSL at PNNL (Richland) .
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 2.54 PFlop/s
- Rpeak
- 3.39 PFlop/s
- Rmax ÷ Rpeak
- 74.9%
- Cores
- 194,616
- Power
- 1.38 MW
- Per watt
- 1.8 GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
How it compares
Ranked against the other machines in this dataset that report the same figure: those that first came into service within two years of Cascade (PNNL), and those in USA. Computed from our tables; a metric is ranked only when at least eight peers report it.
| Metric | Value | Against its era | Against its country |
|---|---|---|---|
| Rmax | 2.54 PFlop/s | #20 of 227 · top 8% | #128 of 332 · top 38% |
| Energy efficiency | 1.8 GF/W | #64 of 186 · top 34% | #87 of 162 · bottom 48% |
| Rmax ÷ Rpeak | 74.9 % | #143 of 226 · bottom 38% | #163 of 331 · top 49% |
| Power draw | 1,384 kW | #32 of 188 · top 17% | #47 of 171 · top 27% |
Every metric is ranked largest-first, so a high power-draw rank means a big power draw, not a good one. Rmax ÷ Rpeak uses HPL-measured results only. Rankings move as machines are added; they describe this dataset, not the world.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - Atipa Visione IF442 blade server, 1,440 nodes in 42 racks | Atipa Technologies | - | Reported | top500.orgtheregister.com |
| Accelerator | - Intel Xeon Phi 5110P coprocessors, two per node on 1,440 nodes | Intel | - | Reported | theregister.comtop500.org |
| CPU | Intel Xeon E5-2670 CPUs x86-64 · 8C · 2.6 GHz · 32 nm · 115 W Intel Xeon E5-2670 8C 2.6GHz, two per node | Intel | - | Reported | theregister.comtop500.org |
| Interconnect | Mellanox InfiniBand FDR Interconnect Fat tree · 56 Gb/s per 4x port · About 1 microsecond Mellanox FDR InfiniBand 56Gb/s | NVIDIA | - | Reported | theregister.comtop500.org |
| Storage | - 2.7 PB shared file system from DataDirect Networks | DDN | - | Reported | theregister.com |
Engineering, funding and access
What Cascade (PNNL) runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 1,440 nodesPlanned configuration reported while the machine was still unnamed (HPCS-4A): 42 racks, two Xeon E5-2670 and two Xeon Phi 5110P per node. | 2013-01 | Press report | theregister.com |
| Storage capacity | 2.7 PBShared DataDirect Networks file system, as planned. | 2013-01 | Press report | theregister.com |
| Interconnect and topology | Mellanox 56 Gb/s FDR InfiniBand, chosen over Intel's QLogic offering | 2013-01 | Press report | theregister.com |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Programming and software stack | Linux, initially a CentOS clone of Red Hat Enterprise Linux, then Scientific Linux | 2013-01 | Press report | theregister.com |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Funded by | US Department of Energy Office of Science | 2013-01 | Press report | theregister.com |
| Stated cost | 17 USD mAbout USD 17 million total including storage, per The Register. | 2013-01 | Press report | theregister.com |
| Procurement | DOE HPCS-4A project; Atipa Technologies (division of Microtech Computers, Lawrence, Kansas) with Super Micro boards; parts due July 2013, running by October 2013, replacing the Chinook clusterA second phase (HPCS-4B) was to be bid in 2014. | 2013-01 | Press report | theregister.com |
The read
Atipa Visione IF442 blade cluster for the DOE Environmental Molecular Sciences Laboratory (EMSL) on the PNNL campus in Richland, Washington. The Register's January 2013 report describes 1,440 nodes in 42 racks, each with two eight-core Xeon E5-2670 CPUs and two 60-core Xeon Phi 5110P coprocessors on Mellanox FDR InfiniBand, 128 GB of memory per node, a 2.7 PB DDN shared file system, 3.4 PFlop/s peak, a cost of about 17 million dollars and a target date of October 2013. TOP500 lists 194,616 cores, Rmax 2.539 PFlop/s, Rpeak 3.388 PFlop/s and 1,384 kW; it ranked 14th on the November 2013 list and was still on the list at rank 481 in June 2025, across 24 lists.
Timeline
- 2013 First operational source
- 2013-01 Announced source
- 2013-01 DOE Office of Science selected Atipa Technologies to build the HPCS-4A system for PNNL for about USD 17 million including storage source
- 2013-11 Listed at #14 on the TOP500 (November 2013) source
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Change history
- 2026-10-07 Added Cascade, the EMSL cluster at PNNL
Nearby in scale
The machines closest to Cascade (PNNL) by Rmax, smaller to larger.
Related systems
Same site
Same operator
- Constance · USA, operational, 2014
- Olympus (PNNL) · USA, operational, 2012
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| top500.org | names system and part | Intel Xeon E5-2670, Mellanox InfiniBand FDR |
| theregister.com | does not name this system | Intel Xeon E5-2670, Mellanox InfiniBand FDR |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.