Supercomputers/Systems/AWS Homer City Campus

USA · planned · mixed

AWS Homer City Campus

Also known as PIT100 Masterplan; Homer City Energy Campus

Operated by Homer City Redevelopment at Homer City Energy Campus .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1350 of 1540 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Homer City Redevelopment develops the 3,200 acre gas-powered campus; AWS is the anticipated end user
Homer City Redevelopment
- Reported gevernova.combaxtel.com
Power -
Seven GE Vernova gas turbines for up to 4.5 GW of on-site generation
GE Vernova
7
reported
Reported gevernova.combaxtel.com

How it is powered

SourceProviderMWStatusAs ofBasisNoteSource link
On-site gas Homer City Redevelopment 4,500 planned 2025-04 Operator stated Up to 4.5 GW from seven GE Vernova turbines; behind-the-meter with FirstEnergy grid backup per Baxtel; Baxtel (Aug 2026) says the plant is under construction for 2028 gevernova.combaxtel.com

How AI campuses are powered: capacities are what the operator, utility or filing states, not what has been delivered.

The read

Proposed AWS data center campus at the Homer City Energy Campus in Indiana County, Pennsylvania, on the site of a former 2 GW coal plant that ran from 1969 to mid 2023. Homer City Redevelopment's April 2025 announcement with GE Vernova and Kiewit describes a gas-powered campus of more than 3,200 acres with up to 4.5 GW of generation from seven GE Vernova turbines, designed for AI and high-performance computing demand. Baxtel reports that Amazon confirmed talks with the developer in August 2026 with no definitive agreement, and that a preliminary land development plan filed on 28 August 2026 (PIT100 Masterplan) shows 36 data center buildings with AWS as the anticipated end user, built in phases to about 2036; county commissioners tabled the application after a 9 September meeting. The 4.5 GW is generation capacity, not data center load, and no accelerator type or count is public. AWS's other Pennsylvania campus is aws-susquehanna-campus.

Timeline

Site & facility

Homer City Energy Campus

Location
Homer City, PA, USA
Utility
FirstEnergy (grid backup to on-site gas plant)

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
baxtel.comnames system only-
gevernova.comnames system only-